Resolved
The Board noted the contents of the report.
Lancashire Enterprise Partnership noted this item on Tuesday 23 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The Board noted the contents of the report.
This report provides the Lancashire Enterprise Partnership (LEP) Board with high level updates for each of the LEP programmes.
The Lancashire Enterprise Partnership (LEP) is asked to note the contents of this report.
BACKGROUND AND ADVICE
The purpose of this report is to provide Members of the Board with a single high-level programme report, including an update on each of the LEP programmes, with the aim to:
Provide regular and consistent updates across all programmes, which can be used when Members are promoting / engaging / conducting LEP business. Recognise, appreciate and explore the synergies / linkages between programmes to allow a more holistic delivery model. Allow members to make individual programme decisions in the context of the complete portfolio of Programmes. Assurance of the Performance of individual programmes for which the LEP is accountable to government for. Identify any programme risks and agree remedial actions.
PERFORMANCE
Programme Update Reports
Please find attached at Appendices A–L updates for each of the LEP programmes as detailed below:
Boost – Lancashire Business Growth Hub City Deal Enterprise Zones X 4 Getting Building Fund Growing Places Growth Deal Inward Investment Lancashire Skills and Employment Hub Social Value
Key Performance Indicators
The table below contains the combined current core KPIs for all the LEP programmes as sourced from the individual reports (Appendices A-L). Data is as at Qtr. 3 2020/21 (31st Dec 20).
Key Performance Indicator - Programmes Combined
Key Performance Indicator Actuals Target % achieved Capital Funding Invested £m £235.46 £307.10 77% Private Sector Investment £m £193 £431 45% Other Investment £m £328 £818 40% Housing Units 19006 22315 85% Jobs Created / Jobs Safeguarded / Apprentices 27,126 43,469 62% Commerical floor space constructed or refurbished (sqm) 373,526 924,234 40% New or Resurfaced Road (km) 5 5 100% New or improved cycle ways (km) 20.57 28.1 73% New or Improved Training learning facility (sqm) 42371 42969 99% Additional Leaners leading to qualification (up to L4) 10988 10793 102% Enterprises or Businesses receiving support (SME) 4644 6167 75% Specalist Equipment 19 118 16% New products to Market 40 40 100% Social and Economic Value Impact £m £31.10 N/A N/A
In respect to the above table please note:
Growing Places, Warton EZ and Social Value programmes – Whilst the programmes have reported 'actuals' which are included in the table above, they do not currently have 'targets' to measure performance against. Lancashire Skills and Employment Hub programme - As a strategic unit, gathering local labour market intelligence to identify skills and employment priorities, the programme is not measured against the KPIs within the table above. Please refer to programme report for performance data. An outcome of the KPI review would be to establish if there are KPIs for this programme which should be included in the LEP KPI document. Inward Investment programme – The 'actuals' within the report are not included in the table above as these have been achieved through the wider partnership working. Double Counting - Some of the programmes crosscut, as such there is the potential for double counting of KPI 'actuals', when combining all the programmes. An exercise has been undertaken to remove the duplicates. Reporting Period – Programmes performance periods range from 2013 – 2041. Programme review – It is anticipated, as an outcome of the Programme Review, that additional KPIs are identified within programmes to report against. Programme Review
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Boost UpdateAppendix A | 253 KB | Download |
PDF |
City DealAppendix B | 377 KB | Download |
PDF |
Blackpool Airport EZAppendix C | 216 KB | Download |
PDF |
HillhouseAppendix D | 301 KB | Download |
PDF |
Samlesbury EZAppendix E | 292 KB | Download |
PDF |
Programmes Update ReportReport | 145 KB | DownloadRead as text |
PDF |
View as DOCX (7./2) 33 KBAppendix | 4 pages | Download |
PDF |
View as DOCX (7./3) 20 KBAppendix | 1 pages | Download |
PDF |
View as DOCX (7./4) 29 KBAppendix | 2 pages | Download |
PDF |
View as DOCX (7./5) 27 KBAppendix | 1 pages | Download |
PDF |
View as DOCX (7./6) 32 KBAppendix | 2 pages | Download |
PDF |
View item 7. as DOCX 47 KBReport | 2 pages | Download |
Follow Lancashire Enterprise Partnership at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Sep 2023 | Minutes of the meeting held on 21 June 2023Following this amendment, the minutes were approved as an accurate recor d. | Approved | Open |
| 20 Sep 2023 | 23/24 mid-year Business Plan Delivery UpdateResolved : The Lancashire Enterprise Partnership Board noted the report as presented. | Noted | Open |
| 20 Sep 2023 | LEP Governance and Committees Report - September 2023The Lancashire Enterprise Partnership Board noted the report as set out. | Noted | Open |
| 20 Sep 2023 | Establishment of a Business Board for Lancashire - UpdateResolved : The Lancashire Enterprise Partnership Board noted the update as provided and gave the above comments for c... | Noted | Open |
| 20 Sep 2023 | Energy and Low Carbon Implementation PlanResolved : The Lancashire Enterprise Partnership Board noted the update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.