Wyre Borough: LCC/2025/0010, Land at Hillhouse International Business Park
DecidedPlanning5 papers
AI summaryLancashire County Council approves waste-to-fuel plant at Hillhouse Enterprise Zone in Wyre, capable of processing up to 250,000 tonnes a year into solid recovered fuel, subject to planning conditions.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions in Appendix A
MoneyNo financial implications for the County Council
What happens nextConditions to be dischargedIncluding Biodiversity Net Gain Plan before commencement
Who it affectsHillhouse Enterprise Zone, Thornton areaAdjacent to Trunnah residential properties, 140m away
What was decided
Planning permission was granted for a new waste processing building, portacabin office and boundary fencing to convert household, commercial and industrial waste into solid recovered fuel, after taking the environmental information into account under the 2017 EIA Regulations. Report P3, P123
The facility is sized for a maximum annual throughput of up towards 250,000 tonnes, with 24-hour operation, 4 to 12 operatives, and around 40 HGV movements per day. Report P9, P10, P11, P17
The main building would be approximately 108m long, up to 64m wide and 13.4m high at the ridge, with two 20m high flue stacks and solar panels on the roof. Report P5, P6
Why
The site lies within the Hillhouse Enterprise Zone, allocated as a strategic employment site in the Wyre Local Plan and identified for large scale built waste management in policy WM2; the proposal would divert waste from landfill and recover energy. Report P73, P74, P117
Officers concluded that with mitigation, the noise impact at the nearest homes would be comparable to background levels, and air quality and odour impacts would not be significant, with the Environment Agency regulating emissions through a separate environmental permit. Report P108, P109, P111
An updated shadow habitats assessment found no likely significant effect on European protected sites, but 4.97 biodiversity units must be provided off-site to meet the mandatory 10% net gain, and a contaminated land assessment is required. Report P50, P67, P91
What happens next
A Biodiversity Gain Plan must be submitted and approved before any development begins, alongside discharge of conditions on contaminated land, drainage, noise verification, nesting birds and ecological mitigation. Report P89, P91, P108
The applicant must demonstrate that the surface water drainage strategy meets Defra Technical Standards through a condition, addressing the objection from the Lead Local Flood Authority. Report P49, P97
An environmental permit from the Environment Agency will be required before the facility can operate. Report P111
Options considered
Chosen: Grant planning permission subject to conditions in Appendix A. Compliant with relevant national and local planning policy, no unacceptable environmental or highways impacts subject to conditions Report P3, P122, P123
Implications
Environment and climate: The facility would process up to 250,000 tonnes of residual waste per year into solid recovered fuel, providing a replacement for primary fossil fuels; solar panels on the roof would power on-site operations. Report P5, P17, P113
Legal: Officers consider the grant of permission a proportionate response under Article 1 of Protocol 1 of the Human Rights Act 1998, with conditions limiting impacts on residents. Report P128
Equalities: The Public Sector Equality Duty has been applied and no disproportionately adverse impact on any protected characteristic is anticipated. Report P132, P133, P134
Risk: No significant risks associated with the decision making process provided it is based on the evidence in the report; future regulation rests with the Environment Agency through the environmental permit. Report P111, P135
Other: The Lead Local Flood Authority objected on drainage grounds, but officers consider this can be addressed by condition. Report P49, P97
Who and where
Residents of Hatfield Close, Trunnah, approximately 140m south-west of the site Report P23, P105
Existing and future operators on the Hillhouse Enterprise Zone and Redmarsh Industrial Estate Report P20
Residents on the new Bourne Road residential development Report P24, P60
Wyre Borough Council as local planning authority Report P48
Timeline
30 January 2024: Screening opinion request submitted Report P39
18 April 2024: EIA screening opinion issued confirming EIA development Report P39
13 September 2024: EIA scoping opinion issued Report P41
19 March 2025: Public exhibition held at Thornton-Cleveleys Football Club, attended by over 50 people Report P47
15 October 2025: Development Control Committee resolves to grant planning permission subject to conditions
Plain English for the jargon
Solid recovered fuel (SRF): A fuel produced from non-hazardous waste after removal of recyclables and moisture, used as a replacement for fossil fuels in industrial plants such as cement kilns.
EIA development: Development requiring an Environmental Impact Assessment under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017.
Biodiversity Net Gain (BNG): A statutory requirement under the Environment Act 2021 for developments to deliver at least a 10% increase in biodiversity relative to the pre-development site value.
HGV: Heavy goods vehicle.
Shadow habitats regulations assessment: A screening assessment of likely significant effects on European protected sites, used where a formal Habitats Regulations Assessment is not required.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
That, after first taking into consideration the environmental information, as defined in the Town and Country Planning (Environmental Impact Assessment) Regulations 2017, planning permission be granted subject to the conditions set out in Appendix 'A'.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
To consider and determine the following planning application:
Wyre Borough Council: LCC/2025/0010 New building, portacabin style office and erection of boundary fencing associated with processing of household, commercial and industrial waste to produce a solid recovered fuel (SRF) at Plot CL5, West Road, Hillhouse International Business Park, FY5 4QP.
Recommendation
The Development Control Committee is asked that, after first taking into consideration the environmental information, as defined in the Town and Country Planning (Environmental Impact Assessment) Regulations 2017, planning permission be granted subject to the conditions set out in Appendix 'A'.
Applicant's Proposal
This application is for a new main building, small portacabin style office and erection of boundary fencing associated with processing of household, commercial and industrial waste to produce a solid recovered fuel (SRF). A waste processing building would be constructed to house all processing and storage operations. The building, approximately 108m long and up to 64m wide, would be steel framed incorporating concrete panel walls at the lower elevations and steel panels (coloured grey) on the upper walls and roof. The main building would be 13.4m high at the ridge. The roof of the building would be fitted with solar panels and the energy generated would be used to power the operations on site.
Other equipment to be installed at the site would include a weighbridge, a portacabin style office (20m x 3m x 3m) and welfare facility, two drying cabinets and two sets of abatement equipment, each with a 20m high steel stack for dispersion of emissions. The drying cabinets and abatement equipment would sit within a recess on the western side of the building.
The site would be fenced with 2.4m high green weldmesh fencing including lockable gates at the entrance and exit.
External lighting would be installed around the site. Lights would be double headed and mounted on the building.
The proposed operating hours are 24 hours per day over 7 days per week including bank holidays.
The site would be staffed with a minimum of four operatives at the commencement of operations, rising to 12 full-time operatives once full production is reached.
Waste would be transported to the site in heavy goods vehicles (HGVs) with either 20 or 24 tonne payloads. It is estimated that some 40 heavy goods vehicle (HGV) movements per day would be generated. Although the site would be operational 24 hours per day, the applicant anticipates that the majority of vehicle movements will be undertaken during Monday – Friday 0700 – 1900 hours, and Saturday 0700 – 1300 hours.
Site access for all vehicles would be into the Hillhouse Estate via Bourne Road and then into the site from West Road. A one-way system for heavy goods vehicle (HGV) traffic would be in place. This would allow traffic control inside the site for safety reasons and also allow space for vehicles to queue inside the site before reaching the weighbridge.
14 on-site car parking spaces would be provided to accommodate vehicles generated by staff and visitors. Cycle storage would be provided for within the welfare facility whereby any operatives who cycle to work can safely store their bicycle inside.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.