CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancashire County Council / Rossendale Borough Council

Audit and Governance Committee Work Programme 2026/27

Noted Finance 3 papers

AI summaryLancashire Combined County Authority Audit and Governance Committee notes its 2026/27 work programme and action log, with ongoing review as the authority enters its delivery phase from 1 April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the 2026/27 work programme and action log
MoneyNot stated
What happens nextReviewed at each meetingProgramme considered by committee at every meeting
Who it affectsLCCA governance and oversightInternal audit, external audit, finance, risk

What was decided

The committee noted the 2026/27 work programme and action log set out at Appendix 'A', subject to the request made. Report P2

Officers will continue to consider what information, particularly financial and budget information, to share with the committee now that the LCCA has moved into a delivery phase from 1 April 2026. Report P8

Why

A clear annual work programme ensures the committee meets its responsibilities and stays compliant with its terms of reference. Report P14

The programme gives the committee an independent, high-level focus on the adequacy of the authority's governance, risk and control arrangements, and gives confidence to those charged with governance. Report P19

The work programme reflects the size of the LCCA's current operations and is reviewed to respond to emerging priorities. Report P4

What happens next

The work programme will be considered by the committee at each of its meetings and updated as necessary. Report P11, P4

Each meeting will include an update from the LCCA's Chief Operating Officer on the authority's work and priorities. Report P5

Any options, proposals, legal, financial, equality and diversity, and risk implications tied to individual work programme reports will be considered as part of each report. Report P9, P15, P17, P18, P20

Options considered

  • Chosen: Note the work programme and action log for 2026/27 as set out at Appendix 'A'. Standard approach to maintain oversight of committee business and previously agreed actions. Report P2, P6

Implications

  • Legal: A clear work programme ensures the committee meets its responsibilities and is compliant with its terms of reference. Report P14
  • Risk: The programme enables independent high-level focus on the adequacy of the authority's governance, risk and control arrangements. Report P19
  • Other: The work programme is an evolving document reflecting the size of the LCCA's operations and responding to emerging priorities. Report P4

Who and where

  • Lancashire Combined County Authority Audit and Governance Committee Report P2, P5
  • LCCA Chief Operating Officer, who will provide updates at each meeting Report P5
  • Those charged with governance of the LCCA Report P19

Timeline

  • 23 March 2026: Committee approved the work programme for 2026/27 Report P4
  • 1 April 2026: LCCA moved into its delivery phase following set-up and mobilisation Report P8
  • 2026/27: Work programme to be reviewed at each committee meeting Report P11

Plain English for the jargon

  • LCCA: Lancashire Combined County Authority
  • Action log: Record of actions previously agreed at committee meetings, included to maintain oversight
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

- That, subject to the above request, the committee's work programme and action log for 2026/27 be noted.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Lancashire Combined County Authority - Audit and Governance Committee

Purpose of the report

The purpose of the report is to share the current version of the Audit and Governance Committee's work programme for 2026/27 as set out at Appendix 'A' which also includes an action log for actions raised at previous committee meetings.

Recommendation

The Audit and Governance Committee is asked to consider the current work programme and action log for 2026/27 as set out at Appendix 'A'.

Section 2 - Background

1. At the Audit and Governance Committee meeting on 23 March 2026, the committee approved a work programme for 2026/27. 2. The work programme is an evolving document which reflects the size of the LCCA's current operations and is reviewed and updated as and when necessary and to respond to any emerging priorities. The current work programme is set out at Appendix 'A'.

3. In accordance with the responsibilities set out in the committee's terms of reference, the work programme includes regular reports relating to internal and external audit, finance and risk management. To enable the committee to carry out its role effectively, each meeting will also include an update from the LCCA's Chief Operating Officer on the authority's work and priorities.

4. An action log is also included at the end of the work programme to allow the committee to maintain oversight of previously agreed actions.

Section 3 - Options and Proposals

5. The committee is asked to consider the work programme for 2026/27, noting that it is subject to change as other areas or issues are identified by the committee. In addition, officers will continue to consider what information may be appropriate to share with the committee, particularly financial/budget information, now that the LCCA has moved into a delivery phase from 1 April 2026, following a period of set-up and mobilisation.

6. Any options and proposals associated with reports identified on the work programme at Appendix 'A' will be considered as part of each report individually.

Section 4 - Consultations

7. The work programme has been developed by officers in consultation with the Chair of the committee and will be considered by the committee at each of its meetings.

Section 5 - Context and Implications

Legal (including Human Rights)

8. A clear work programme for each year ensures the Audit and Governance Committee meets its responsibilities and is compliant with its terms of reference.

9. Any legal information or implications associated with reports identified on the work programme at Appendix 'A' will be considered as part of each report individually.

Financial

10. Any financial information or implications associated with reports identified on the work programme at Appendix 'A' will be considered as part of each report individually. Equality and Diversity

11. Any equality and diversity information or implications associated with reports identified on the work programme at Appendix 'A' will be considered as part of each report individually.

Risk management

12. A clear work programme for each year ensures the Audit and Governance Committee can carry out its role effectively, to provide an independent and high-level focus on the adequacy of the authority's governance, risk and control arrangements, and gives confidence to those charged with governance that those arrangements are effective.

13. Any significant risks associated with reports identified as part of the programme of work identified will be considered as part of each report individually.

Policy

14. N/A

Section 6 - Appendices

Appendix Title Appendix 'A' Audit and Governance Committee Work Programme 2026/27

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 160 KB Download
PDF
Audit and Governance Committee Work Programme 2026/27Report 94 KB DownloadRead as text
PDF
View item 14. as DOCX 82 KBReport 2 pages Download

At this meeting

Whole meeting

Who was there

10 of 17 attended
GG
Greg GottigChair, present
CC
County Councillor Peter Buckley Lancashire County CouncilCommittee Member, present
CC
County Councillor Gina DowdingCommittee Member, present
CC
County Councillor Dr Lorenzo MoreCommittee Member, present
CC
County Councillor Luke Parker Lancashire County CouncilCommittee Member, present
CC
County Councillor David Shaw Lancashire County CouncilCommittee Member, present
CC
County Councillor Hannah Whalley Lancashire County CouncilCommittee Member, present
NB
Councillor Neal Brookes Blackpool CouncilCommittee Member, absent
MD
Councillor Mustafa Desai Blackburn with Darwen CouncilCommittee Member, apologies
PG
Councillor Paul Galley Blackpool CouncilCommittee Member, absent
SH
Councillor Simon Hore District Council Representative (Ribble Valley)Co-optee Non-voting, present
TH
Councillor Tony Humphrys Blackburn with Darwen CouncilCommittee Member, absent

All 17 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Audit and Governance Committee Work Programme 2026/27This decision
  2. Annual Report of the Audit, Risk and Governance CommitteeNoted
  3. Lancashire Combined County Authority Audit and Governance Committee - Constitution, Membership and Terms of ReferenceNoted
  4. Report of the Audit, Risk and Governance Committee - Annual Governance Statement 2025/26 and Code of Corporate Governance 2026/27Approved
  5. The Audit, Risk and Governance CommitteeNoted
  6. Audit, Risk and Governance Committee Self-Assessment of Good Practice Summary ReportNoted

More from Lancashire & Rossendale Lancashire Combined County Authority - Audit and Governance Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Minutes of the Meeting held on 23 March 2026- That the minutes of the meeting held on 23 March 2026 be approved as an accurate record and signed by the Chair. Approved Open
13 Jul 2026 Lancashire Combined County Authority Audit and Governance Committee - Constitution, Membership and Terms of Reference- That: (i) The membership of the committee, as set out in the report, be noted. (ii) Subject to further consideratio... Noted Open
13 Jul 2026 Key Updates for Lancashire Combined County Authority Committees - July 2026- That the report and updates be noted. Noted Open
13 Jul 2026 Draft LCCA Code of Corporate Governance- That: (i) The draft LCCA Code of Corporate Governance attached at Appendix 'A' be approved. (ii) It be noted that t... Approved Open
13 Jul 2026 Draft Annual Governance Statement 2025-26- That: (i) The publication of the draft Annual Governance Statement by 30 June 2026 in line with the Accounts and Au... Noted Open