Planning Regulatory Committee approved this item on Monday 10 May 2010. Below is the council's own wording, with the papers it was decided on.

Item229

Resolved

That the application be delegated to the Head of Regeneration and Policy to approve, subject to the receipt of satisfactory plans and to the following conditions, as set out in the report: 1. Standard time limit. 2. Amended plan condition. 3. Development in accordance with approved plans. 4. Samples of all external materials and finishes to be submitted and agreed. 5. Surface Water Management Plan using sustainable drainage systems. 6. Drainage on separate system. 7. Phase 2 – speed reduction markings to Powder House Lane. 8. Visibility splay to north at site exit. 9. Prior to occupation of Phase 1 – cycle storage. 10. Prior to commencement of Phase 3 – new car parking layout to be agreed. 11. Retention of visibility splays. 12. Details of floodlighting. 13. Hours of construction. 14. Desk top contamination study. 15. Prior to commencement of Phase 3 – details of roof construction. 16. Prior to commencement of Phase 3 – scheme for noise assessment control. 17. Maintenance of all plant, machinery and equipment. 18. Prior to commencement of Phase 3 – scheme for odour control. 19. The existing clubhouse to the southern end of the site shall not be demolished until the completion of Phase 3. 20. Scheme to be submitted which incorporates on-site renewable energy measures to provide at least 10% of the predicted energy requirements arising from the development.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Planning Regulatory Committee

Agenda Item Committee Date Application Number

A14 10 May 2010 10/00266/FUL

Application Site Proposal

Vale Of Lune R U F C Phased development of the new clubhouse building

Powderhouse Lane

Lancaster

Lancashire

Name of Applicant Name of Agent

The Vale of Lune RUFC [name removed] Target Date Reason For Delay

17 June 2010 None

Case Officer Petra Williams

Departure No

Summary of Recommendation Approve subject to the receipt of amended plans

1.0The Site and its Surroundings

1.1This site is located at the southern most tip of the North Lancashire Green Belt adjacent to the rear (north) of properties fronting Ingleborough Road, Pendle Road and Powder House Lane. It is a large rectangular shaped site containing a club house at is southern end, a first pitch, with car parking and a small stand along its western side and two second pitches across its northern half. To the east of the site are open fields rising steeply over a small hill/ridge which runs north/south along that side of the site. To the north lies the crematorium and its open, landscaped grounds, while the west side is bounded by Powder House Lane and its roadside hedges with an even larger area of open and flat sports fields beyond.

1.2To the east of the site are open fields rising steeply over a small hill/ridge which runs north/south along that side of the site. To the north lies the crematorium and its open, landscaped grounds, while the west side is bounded by Powder House Lane and its roadside hedges with an even larger area of open and flat sports fields beyond.

1.3Halfway along the site frontage to Powder House Lane lies a small bungalow whose small curtilage projects into the side of the site. Although this site and that on the opposite side of Powder House Lane, project into the Green Belt, both geographically and visually, they do not actually form part of its designated area.

2.0The Proposal

2.1The proposal involves the replacement of the existing stand along the western side of the site in a three-phased approach in order to provide a new clubhouse and improved facilities at the Rugby Club.

2.2The existing car park between the pitch and Powder House Lane would be formally laid out around the new building to create 68 spaces with access only from the southern (existing) access and exit only via the upgraded access to the north of Powder House Cottage. A further 44 spaces would be provided in a grass covered overflow car park between pitches 1 and 2. The new parking will be built as part of the third phase of the development.

The existing club house will not be demolished until the third phase is complete.

3.0Site History

3.1The principle for a replacement clubhouse was established in 2007 following approval of 07/00726/HYB.

Application Number Proposal Decision 07/00726/HYB Outline application for redevelopment of existing land to Permitted include 19 dwellings, rugby clubhouse, squash courts, groundsman’s store and associated landscaping

4.0Consultation Responses

4.1The following responses have been received from statutory consultees:

Statutory Consultee Response Police No objections subject to advice provided, which includes adopting ‘Secured by Design’ principles and ‘Park Mark Award’ principles in relation to the car parking layout.

United Utilities No objections subject to standard advice notes.

Highways No objections subject to the previous highway conditions as imposed on application 07/00726/HYB relating to road markings to Powder House Lane; cycle storage; car parking layout and the retention of visibility splays

Environmental No objections – subject to conditions relating to hours of construction; noise; odour Health control and floodlighting details.

Access Officer Raised accessibility issues – it is anticipated that these points will be addressed by amended plans

5.0Neighbour Representations

5.182 letters of support for the development which will provide improved facilities.

6.0Principal Development Plan Policies

6.1Saved Policy R1 of the Lancaster District Local Plan which states that:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Vale of Lune R U F C, Powderhouse Lane, LancasterReport 25 KB DownloadRead as text

More from Lancaster Planning Regulatory Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. Approved Open
1 Sep 2026 Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... Approved Open
1 Sep 2026 Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... Approved Open
1 Sep 2026 Delegated ListThat the report be noted. Noted Open
27 Jul 2026 Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: · the satisfactory completion of a L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies