That Planning Permission be granted, subject to the following conditions, as set out in the report, subject to amendment of condition 4 (suitably worded): 1. Standard time limit. 2. Details of the treatment of the exposed gable walls of numbers 12, 28 and 38 Bold Street to be submitted. 3. Hours of work restriction 0800 – 1800 Monday to Friday and 0800 – 1400 on Saturday. 4. Site management plan to address the issue of the appearance of the remaining (levelled) land – fencing to be avoided, if possible. 5. Dust control 6. Site clearance. 7. Ground levelling and surfacing – details required.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
6-10 And 30 -36 Demolition of seven two storey residential properties Bold Street for regeneration Heysham Lancashire
Name of Applicant Name of Agent
[name removed] Target Date Reason For Delay
28 December 2010 Committee cycle
Case Officer [name removed] No
Summary of Recommendation Approve subject to conditions
1.0The Site and its Surroundings
1.1The application site is located on the north eastern side of Bold Street, between Heysham Road and Marlborough Road in the Heysham area of Morecambe. The site comprises seven properties from a terrace of sixteen. Three of the properties are situated at the northern end of the terrace (6, 8 and 10) and four are to the southern end (30, 32, 34 and 36). Number 38 forms the end of the terrace and is not included in this application.
1.2The properties currently have accommodation over three and four floors and are boarded up. The properties have a mix of stone faced and dash rendered exteriors and are generally of a poorer quality and build. A small commercial area is close by on Heysham Road with the local health centre at the end of Bold Street. Four of the properties on the south western side of Bold Street have recently undergone alterations to reduce them in size to create family sized dwellings. Works of demolition have also recently been carried out along Marlborough Road which runs perpendicular to Bold Street.
1.3Bold Street was earmarked within the original West End Masterplan as an area of high intervention as it contains some of the poorest quality housing within the area.
2.0The Proposal
2.1The application proposes the demolition of seven properties which have so far been acquired by the Council. Their demolition will result in a terrace of nine properties remaining and one singular property (which is boarded up) will remain at the south eastern end of Bold Street. Following demolition the site will be cleared and levelled with compacted crushed stone.
3.0Site History
3.1None relevant to this application. 4.0 Consultation Responses
4.1The following responses have been received from statutory and internal consultees:
Consultee Response
Environmental Health No objections subject to conditions and advice Parish Council No objections Strategic Housing No objections - the proposals are in continuation of the West End Masterplan
5.0Neighbour Representations
5.1No comments received.
6.0Principal Development Plan Policies
6.1National Planning Policy Statements (PPS) PPS1 (Delivering Sustainable Development) - provides generic advice for all new development. Sites should be capable of optimising the full site boundary and should deliver an appropriate mix of uses, green and other public spaces, safe and accessible environments and visually pleasing architecture. A high level of protection should be given to most valued townscapes.
6.2Lancaster District Core Strategy Policy SC1 (Sustainable Development) - development should be located in an area where it is convenient to walk, cycle or travel by public transport between homes, workplaces, shops and other facilities, must not result in unacceptable flood risk or drainage problems, does not have a significant adverse impact on a site of nature conservation or archaeological importance, uses energy efficient design and construction practices, incorporates renewable energy technologies, creates publicly accessible open space, and is compatible with the character of the surrounding landscape.
7.0Comment and Analysis
7.1The site of the proposed demolition is considered in ‘Winning Back Morecambe’s West End’ Masterplan and Delivery Strategy (2005) which was 'refreshed' through a mid term review and approved at the Cabinet meeting in June 2009. The overarching and fundamental component of the vision for the West End is to create an exceptionally good place to live, work and play.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.