Resolved unanimously: (1) That the current monitoring position be noted. (2) That the proposed adjustments to the 2011/12 Internal Audit Plan, as reflected under the ‘Proposed Plan’ column of the table setting out the monitoring position as at 18 th January 2012, be approved.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
To advise Members of the latest monitoring position regarding the 2011/12 Internal Audit Plan and to seek Members’ approval for proposed adjustments to the plan.
This report is public
Recommendations
(1) That the current monitoring position is noted.
(2) That the proposed adjustments to the 2011/12 internal audit plan set out in paragraphs 2.1 to 2.8 are approved.
1.0Introduction
1.1The 2011/12 Internal Audit Plan was approved by the Audit Committee at its meeting on 29th June 2011 and some minor adjustments were approved by the Committee on 21st September 2011. This report is based on the monitoring position up to 18th January 2012. 2.0 Report
Monitoring Position as at 18th January 2012
2.1A detailed monitoring report as at 18th January 2012 is attached as Appendix A. In summary, the position as that date was as shown in the following table. Resources (audit days) Area of work Actuals Remain- Comm- Approved Proposed to Variance ing itted Plan Plan 18/01/12 Assurance Work Core Financial Systems 81 27 108 82 -26 108 Revenues & Benefits 79 28 107 92 -15 107 Shared Services Core Management 28 2 30 81 51 30 Arrangements Risk Based Assurance 175 17 192 105 -87 192 Audits Follow-Up Reviews 47 13 60 70 10 60 Sub-Total, Assurance 410 87 497 430 -67 497
2.2The monitoring position takes account of ongoing and planned work commitments. The summary shows that overall, current commitments total 677 days compared with the approved plan of 695 days, giving an un-committed balance of 18 days. Pending allocation, these 18 days will remain within the “general contingency”. 2.3 Within the main programme of assurance work, the audits of core financial systems and the Revenues and Benefits Shared Service have exceeded the approved plan by a total of 41 days. This reflects additional work required in developing and refining a new approach to these audits, covering all significant systems in this year and in establishing arrangements with Preston City Council to enable audit work to proceed. 2.4 There is also a significant overspend of resources (87 days) on the Risk Based Assurance audit section of the plan, this arising mainly from the audits of the RMS Partnering Contact and the specific piece of work concerning the Hala Flats Pebbledashing job and also from the audit into Consultancy Commissioning and Procurement. This is partially offset by an “underspend” of 51 days in the “Core Management Arrangements” section of the plan and 10 days in conducting follow-up reviews. 2.5 Other areas of the plan showing a minor overspend are “Support Work” (10 days and “Audit Management” (6 days). 2.6 It is proposed to meet these shortfalls (83 days total) by applying 22 days from the the General Contingency and through savings identified elsewhere in the plan, under the following: Efficiency & VfM 30 days Ad-hoc Advice 10 days Reduction in the investigations contingency 21 days 2.7 Clearly, at this point in the year, with resources for the final quarter of the year almost fully committed to the work programme set out in Appendix A, completion of the plan is at risk should any additional responsive work (investigations, etc) be required.
2.8These adjustments are reflected under the “Proposed Plan” column of the table and the Committee is asked to approve the changes.
3.0Details of Consultation 3.1 Management Team has been consulted in developing the plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Governance Statement 2025/26(1) That the Annual Governance Statement for 2025/26 be recommended for adoption and for signing by the Chief Executi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.