Noted Finance 2 papers

Audit Committee noted this item on Wednesday 18 April 2012. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

Resolved unanimously: That the outturn position for 2011/12 be noted.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Audit Committee

Recommendations

(1) That the outturn position for 2011/12 is noted.

1.0Introduction

1.1The 2011/12 Internal Audit Plan was approved by the Audit Committee at its meeting on 29th June 2011. Adjustments to the plan were approved by the Committee at its meetings on 21st September 2011 and 15th February 2012. This report provides the outturn position as at 31st March 2012. 2.0 Report

Outturn Position as at 31st March 2012

2.1A detailed outturn report as at 31st March 2012 is attached as Appendix A. In summary, the position as that date is as shown in the following table. Resources (days) Area of work Approved Outturn to Original Plan Variance 31/03/12 Plan (15/02/12) Assurance Audit Core Financial Systems 119 108 50 69 Revenues & Benefits Shared Services 113 107 85 28 Core Management Arrangements 28 30 110 -82 Risk Based Assurance Audits 203 192 105 98 Follow-Up Reviews 56 60 70 -14 Sub-Total, Assurance 519 497 420 99

Consultancy Support Work 38 40 30 8 Efficiency & VfM 0 0 30 -30 Ad-Hoc Advice 52 55 65 -13 Sub-Total, Consultancy 90 95 125 -35

Other Work Other Duties (Non-Audit) 20 15 15 5 Audit Management 69 61 55 14 Sub-Total, Other Work 89 76 70 19

Contingencies Investigations 9 9 30 -21 General Contingency 0 18 40 -40 Sub-Total, Contingencies 9 27 70 -61 Total 707 695 685 22

2.2The summary shows that overall, a total of 707 days have been delivered compared with the approved plan of 695 days and the original plan of 685 days. This has largely been possible through a continuing good sickness record within the section and ongoing attention to procedures to ensure that “non-chargeable” time is minimised. 2.3 Within the main programme of assurance work, the audits of core financial systems and the Revenues and Benefits Shared Service exceeded the original plan by a total of 97 days. This reflects additional work required in developing and refining a new approach to these audits, covering all significant systems in this year and in establishing arrangements with Preston City Council to enable audit work to proceed. 2.4 There was also a significant re-focusing of resources (98 days) in to the Risk Based Assurance audit section of the plan, this arising mainly from the audits of the RMS Partnering Contact and the specific piece of work concerning the Hala Flats Pebbledashing job and also from the audit into Consultancy Commissioning and Procurement. These demands were managed in part through a reduction in resources (82 days) devoted to the Core Management Arrangements of the assurance work section of the plan. 2.5 Overall, 99 days more than originally planned were spent on assurance audit work. This shift in resources was mostly managed during the year through reduced time spent on: Efficiency & VfM (30 days); Investigations Contingency (21 days) and by use of the General Contingency (40 days).

3.0Details of Consultation 3.1 Management Team has been consulted during the year in developing the plan. 4.0 Options and Options Analysis (including risk assessment) 4.1 Not applicable – the report is for noting.

5.0Conclusion 5.1 The outturn position for the 2011/12 Internal Audit plan shows an increase in the number of audit days delivered and a significant increase in the level of assurance work. This has been made possible through reductions elsewhere in the plan, including a comparatively low demand for investigative work. 5.2 A full report on the delivery of the audit plan and the outcomes from audit work will be included in the Internal Audit Manager’s “Annual Report and Assurance Statement” to the June meeting of the Audit Committee.

CONCLUSION OF IMPACT ASSESSMENT (including Diversity, Human Rights, Community Safety, Sustainability and Rural Proofing)

Not applicable FINANCIAL IMPLICATIONS None directly arising from this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Monitoring: Appendix AAppendix 39 KB Download
PDF
Internal Audit MonitoringReport 66 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Internal Audit MonitoringThis decision
  2. Internal Audit Progress ReportNoted
  3. Annual Report of the Head of Internal Audit and AssuranceNoted
  4. Review of Internal Audit EffectivenessNoted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit CharterApproved

More from Lancaster Audit Committee

All decisions
MeetingDecisionOutcome
27 May 2026 Appointment of Vice-ChairThat Councillor David Whitaker be appointed Vice-Chair of the Audit Committee for the municipal year 2026/27. Decided Open
27 May 2026 Strategic Risk ManagementThat the report be noted. Noted Open
27 May 2026 AGS Action Plan MonitoringThat the progress and steps yet to be taken on the Action Plan be noted. Noted Open
27 May 2026 Annual Governance Statement 2025/26(1) That the Annual Governance Statement for 2025/26 be recommended for adoption and for signing by the Chief Executi... Approved Open
27 May 2026 Review of the Regulation of Investigatory Powers Act 2020 (RIPA) Policy and ProcedureThat RIPA Policy be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies