Highways Maintenance

Approved Committee 2 papers

Council approved this item on Wednesday 13 June 2012. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

(1) That the City Council continues to deliver a highways maintenance service on behalf of the County Council, on the terms set out within the Cabinet report, and as recommended by Cabinet at its meeting of 29 May 2012. (2) That, as the financial implications of delivering the service fall outside of the existing budgetary framework, Council approves that the Revenue Budget for current and future years be updated to allow for the additional estimated costs involved. (3) That the agreement of the detail of the terms of the highways maintenance service be delegated to the Head of Environmental Services.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Council

Recommendations

1) That Council agrees to the City Council continuing to deliver a highways maintenance service on behalf of the County Council, on the terms set out within the appended Cabinet report, and as recommended by Cabinet at its meeting of 29h May 2012.

2) That as the financial implications of delivering the service fall outside of the existing budgetary framework, Council approves that the Revenue Budget for current and future years be updated to allow for the additional estimated costs involved.

3) That subject to the recommendation above, the agreement of the detail of the terms of the highways maintenance service be delegated to the Head of Environmental Services.

1.0Introduction

1.1The report attached at appendix 1 was considered by Cabinet on the 29th May 2012

1.2At this meeting Cabinet agreed the following recommendations -

(1) That Cabinet agrees to the principle of the City Council continuing to deliver a highways maintenance service on behalf of the County Council, on the terms set out within the report. (2) That as the financial implications of delivering the service on the proposed terms fall outside of the existing budgetary framework, the final decision be referred to Council for approval at its meeting on 13 June 2012. (3) That subject to Council’s approval of recommendation (1), the agreement of the detail of the terms of the highways maintenance service be delegated to the Head of Environmental Services.

1.3Therefore, the final decision is referred to Council for approval at this meeting.

2.0Proposal Details

2.1As set out in the Cabinet report and recommendations.

3.0Details of Consultation

3.1As set out in the Cabinet report

4.0Options and Options Analysis (including risk assessment)

4.1As set out in the Cabinet report.

5.0Officer Preferred Option (and comments)

5.1Option 1 (as set out in the Cabinet report) to continue to provide Highways Maintenance Services on behalf of the County.

6.0Conclusion

6.1As set out in the Cabinet report.

RELATIONSHIP TO POLICY FRAMEWORK

As set out in the Cabinet report. CONCLUSION OF IMPACT ASSESSMENT (including Diversity, Human Rights, Community Safety, Sustainability and Rural Proofing) As set out in the Cabinet report. LEGAL IMPLICATIONS

As set out in the Cabinet report FINANCIAL IMPLICATIONS As set out in the Cabinet report. In summary, continuing to deliver the highways maintenance service is expected to cost around an extra £162K per year (plus inflation), over and above existing budgets. This is around £18K per year more than if the Council decided not to be involved in future delivery – so either way, the Council is facing increased cost pressures. Should Council approve the recommendations, the Revenue Budget for current and future years would be updated accordingly. The updated projections would be reflected in the next formal update of the Medium Term Financial Strategy. Clearly the extra estimated costs would add to the need to make budget savings in future years, if current council tax targets are to be retained. As set out in the attached Cabinet report, opportunities to make savings within the highways maintenance function would be pursued but there are no quantified proposals at this stage.

OTHER RESOURCE IMPLICATIONS

Human Resources: As set out in the Cabinet report Information Services: As set out in the Cabinet report Property: As set out in the Cabinet report Open Spaces: As set out in the Cabinet report,

SECTION 151 OFFICER’S COMMENTS

As set out in the Cabinet report. MONITORING OFFICER’S COMMENTS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways MaintenanceReport 65 KB DownloadRead as text
PDF
Highways Maintenance Report (FINAL)Report 83 KB Download

More from Lancaster Council

All decisions
MeetingDecisionOutcome
22 Jul 2026 Leader's reportThat the report be noted. Having declared an interest, Councillor Keith Budden left the Council Chamber for the durat... Noted Open
22 Jul 2026 Morecambe Business Improvement District (BID) Renewal Ballot - City Council's Voting IntentionResolved (unanimously) that: 1) The Council’s voting allocation be used to vote in favour of Morecambe BID’s Renewal ... Decided Open
22 Jul 2026 Allocation of seats to political groupsResolved (unanimously): That the Council note the establishment of the Independent Group of Councillors and approve t... Noted Open
22 Jul 2026 Minutes of cabinetThat the minutes be noted. Noted Open
25 Jun 2026 Leader's reportThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies