Lancaster City Council
Planning Regulatory Committee, Monday 25 June 2012

National Grid North West Coastal Connections Project - Consultation on Strategic Route Options

Agreed Planning 2 papers

Planning Regulatory Committee agreed this item on Monday 25 June 2012. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

(1) That the City Council informs National Grid that it agrees that Options 3 and 4 are the most appropriate to pursue to the next stage of evaluation, but that it has a clear preference for Option 4. (2) That the City Council specifies that retaining Option 3 in the next round of evaluation is qualified to a preference for utilising the routes of existing power lines and not creating new routes, and addressing fully evidence gaps on connectivity and mitigation. The ... view the full minutes text for item 27.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Planning Regulatory Committee

Purpose of report

To enable the Committee to give informal views on behalf of the City Council on the Strategic Route Options choices which National Grid are considering for this major national infrastructure project.

Recommendations

(1) That the City Council informs National Grid that it agrees that Options 3 and 4 are the most appropriate to pursue to the next stage of evaluation. (2) That the City Council specifies that retaining Option 3 in the next round of evaluation is qualified to a preference for utilising the routes of existing power lines and not creating new routes, and addressing fully evidence gaps on connectivity and mitigation. (3) That the City Council informs National Grid that there should be a more detailed technical and environmental evaluation of Options 3 and 4 before a final preferred option is selected. (4) That the City Council highlights the need for National Grid to give very careful consideration to avoiding adverse impacts on the sensitive protected landscapes of the Arnside/Silverdale and Forest of Bowland Areas of Outstanding Natural Beauty. (5) That the City Council informs National Grid that it requires assurances that the option they eventually choose to pursue will provide for the ability to connect a future new nuclear station at Heysham into the upgraded system with minimal additional impact.

1. Introduction

1.1The National Grid North West Coastal Connections Project will be one of the largest investments in infrastructure in the North West of England for 50 years. It has to find the means by which additional power generated by new nuclear build at Moorside (Sellafield) and Heysham (in a later phase), together with that generated by wind power in the Irish Sea, is transmitted into the main National Grid. The National Grid generally runs north and south within the inland areas of the country, but the next generation of power generation will largely take place on the coasts. National Grid upgrades are therefore proposed in various locations around the country to connect that new power generation into the existing grid system.

1.2The National Grid project team has been working closely with a consortium of Lancashire and Cumbria local authorities for the last 18 months to establish the means by which the application for a Development Consent Order will be handled. The Head of Regeneration and Planning has taken a major role in those negotiations on behalf of the City Council and the project will lead to an application for a Development Consent Order for this is a major infrastructure scheme being determined by the Secretary of State in around 2015/16. The local authorities will play a major role in the determination process as statutory consultees. The National Grid have decided that prior to making their final selection of strategic route option, which will result in the staring of significant evaluation work on route corridor studies, they will engage in a period of consultation with the local planning authorities.

2.0Procedural matters

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
National Grid North West Coastal Connections Project: Consultation on Strategic Route OptionsReport 86 KB DownloadRead as text
PDF
Strategic Route Options LPA reponse template (2)Report 962 KB Download

At this meeting

Whole meeting

More from Lancaster Planning Regulatory Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. Approved Open
1 Sep 2026 Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... Approved Open
1 Sep 2026 Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... Approved Open
1 Sep 2026 Delegated ListThat the report be noted. Noted Open
27 Jul 2026 Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: ยท the satisfactory completion of a L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies