That subject to the submission of satisfactory amended plans, planning permission be granted subject to the following conditions, as set out in the case officer’s report, with an amendment to conditions no. 6, no. 9 and no.11: 1. Standard Time Limit 2. Amended Plans (and other approved plans) (To be confirmed (TBC) via verbal update) 3. Construction Management Plan 4. Materials – samples 5. Detailing of stonework 6. Details of windows/doors/glazing/roof details/balconies/dormers/external surfacing details 7. Parking provision to be provided before occupation 8. Garage use condition 9. Boundary details and retention as approved 10. Tree protection 11. Development to be carried out in accordance with AMS/tree report 12. Development to be carried out in accordance with the FRA 13. Drainage details 14. Habitat protection & management plan (including measures outlined in ecology report) 15. Provision of riverside path 16. Site Investigation – Contamination 17. Contaminated land - importation of soil, materials and hardcore 18. Contaminated land - prevention of new contamination 19. Bunding of tanks 20. PD rights removed
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Halton Mills Erection of 14 dwellings with associated landscaping and parking Mill Lane
Halton
LA12 6ND
Name of Applicant Name of Agent
[name removed]
Barratt Homes Manchester
Decision Target Date Reason For Delay
30th June 2014 None
An extension of time for determination has mutually been agreed between the Developer and the Local Planning Authority
Case Officer [name removed] No
Approval – but subject to the submission of Summary of Recommendation satisfactory amendments
1.0The Site and its Surroundings
1.1The application site is split into two separate parcels of land, totalling to 0.77ha, both relating to land on the former Halton Mills industrial estate located on the banks of the River Lune, about 3 miles east of Lancaster City. Both sites have laid vacant for a considerable length of time.
1.2Halton Mills is located on the edge of the main built up part of the village accessed off Low Road (or Mill Lane via Station Road). The village itself is quite spread out and contains various different styles and periods of development, including a significant amount of reasonably modern housing. The Parish Plan (2003) recognises this and divides the village into a number of different character zones. The village amenities such as the school, shop and health centre are located on and around High Road. The community hall and recreation space (including the allotments) are accessed opposite Halton Mills off Low Road. The national strategic cycle network is located on the opposite side of the Lune, accessed via Halton Bridge. Halton Mills previously occupied a cotton factory and flour mill (dated 1844-5) and has for a number of years (before the proposals for comprehensive redevelopment) was used predominately for industrial purposes. The site now consists of cleared sites, public open space including an equipped play area, a partly developed area of land in the central core of the site consisting of three-storey townhouses and apartments blocks, two modern industrial units, a long established business (Out of the Woods) and the Co-housing development.
1.3The application sites are broadly rectangular in shape running adjacent to the banks of the River Lune. The developable areas of the site are constrained by the steep embankment down towards the River Lune and the relatively dense landscaping in this area. Access to both sites is taken off Mill Lane (via Forge Lane) from the main junction with Low Road.
1.4The two parcels of land shall be referred to as Site A and Site B. Site A is located at the western end of the wider Halton Mills site and is located within the Conservation Area. This site sits adjacent to an existing single storey concrete building (known as the “fisheries building” and previously used as a lawnmower repair business), and located to the south of Town End Farm, which is a grade II listed farm complex – now converted to residential use. The new apartments and townhouses are located to the east of Site A. Site B is located to the west of 27–37 Mill Lane; properties constructed as part of the wider Lancaster Co-housing development with an area of public open space including an equipped play area to the east, and undeveloped land to the north and commercial units to the north east.
1.5The site is allocated in the saved Local Plan as an Employment Opportunity Site. Site A is located in flood zone 2 and Site B within flood zone 2 and 3. A belt of trees along the riverbank and a tree adjacent to 27 Mill Lane are protected by a tree preservation orders numbers TPO 352(2001) and TPO 486(2011) respectively. The River Lune is a biological heritage site.
2.0The Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.