Internal Audit Monitoring Report

Noted Finance 3 papers

Audit Committee noted this item on Wednesday 16 September 2015. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

(1) That the current monitoring position be noted. (2) That the proposed revisions to the audit plan, as set out in the table in paragraph 1.2 of the report be approved. (3) That the proposed rolling programme of Internal Audit work attached as Appendix B be noted. (4) That the results of recent audit activity (sections 3 – 7 of the report) be noted.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Audit Committee

Purpose of report

To advise Members of the latest monitoring position regarding the 2015/16 Internal Audit Plan, seek approval for proposed variations to the plan, and update Members on the results of recent audits.

This report is public

RECOMMENDATIONS (1) That the current monitoring position is noted. (2) That the proposed revisions to the audit plan, as set out in the table in §1.2, are approved. (3) That the proposed rolling programme of Internal Audit work attached as appendix B is noted. (4) That the results of recent audit activity (sections 3 - 7 of the report) are noted.

1.0Audit Plan Monitoring to 21st August 2015 1.1 The 2015/16 Internal Audit Plan was approved by the Audit Committee at its meeting on 17th June 2015. This report is based on the monitoring position up to 21st August 2015 and a detailed monitoring report as at that date is attached as Appendix A. In summary, the position at that date was as shown in the following table. 1.2 Summary of monitoring position at 21st August 2015 Resources (audit days) Area of work Actuals Remain- Comm- Current Proposed to Variance ing itted Plan Plan 21/08/15 Assurance Work Core Financial Systems 10 4 14 50 36 40 Revenues & Benefits 4 13 17 40 23 35 Shared Services Core Management 14 4 18 50 32 40 Arrangements Risk Based Assurance 18 11 29 170 141 135 Audits Follow-Up Reviews 35 20 55 50 -5 55 Sub-Total, Assurance 81 52 133 360 227 305

Consultancy Work Support Work 10 7 17 50 33 35 Ad-Hoc Advice 29 31 60 65 5 60 Sub-Total, Consultancy 39 38 77 115 38 95

Other Work Other Duties (Non-Audit) 19 16 35 35 0 35 Audit Management 30 20 50 50 0 50 Sub-Total, Other Work 49 36 85 85 0 85

Contingencies Investigations 9 4 13 30 17 30 General Contingency 0 0 0 40 40 20 Sub-Total, Contingencies 9 4 13 70 57 50

Total 178 130 308 630 322 535

1.3The monitoring position takes account of ongoing and planned work commitments. This shows that overall, current commitments total 308 days compared with the current plan of 630 days, giving an uncommitted resource of 322 days. This includes both the general contingency of 40 days and the unallocated balance of the contingency for investigation work (17 days). 1.4 The Internal Audit section currently has a vacant post, the Senior Auditor having been promoted to the post of Principal Auditor in May 2015. Options for the future scope and structure of the Internal Audit service are still under review. The outcomes from this review, and the implications for the Audit Committee in terms of the reliance it can place on Internal Audit, will be reported to the Committee in due course, but at this stage the estimated impact is that a reduction in the plan of approximately 10 to 15% (60 - 95 days) should be expected. The Proposed Plan in the above summary is based on a reduction of 95 days. Proposals 1.5 The proposals incorporate reductions across all work headings with the exception of Non-Audit Duties and Audit Management where commitments already exist and/or it will prove difficult to reduce resources under the current circumstances. The proposals also include application of 20 days, i.e. half of the General Contingency. 1.6 As regards the main programme of Assurance Audit work, the proposed reduction amounts to 55 days (15%) against the original plan of 360 days. 2.0 Rolling Internal Audit Plan 2.1 An updated rolling programme of Internal Audit work is attached to this report as Appendix B. Members’ attention is particularly drawn to the list of potential areas for audit coverage during the forthcoming third quarter. This list has been developed through consultation meetings with Chief Officers. The actual programme and timing of work will be subject to the development of detailed scoping exercises.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Monitoring: Appendix AAppendix 23 KB Download
PDF
Internal Audit Monitoring: Appendix BAppendix 124 KB Download
PDF
Internal Audit Monitoring ReportReport 277 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Internal Audit Monitoring ReportThis decision
  2. Internal Audit Progress ReportNoted
  3. Annual Report of the Head of Internal Audit and AssuranceNoted
  4. Review of Internal Audit EffectivenessNoted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit CharterApproved

More from Lancaster Audit Committee

All decisions
MeetingDecisionOutcome
27 May 2026 Appointment of Vice-ChairThat Councillor David Whitaker be appointed Vice-Chair of the Audit Committee for the municipal year 2026/27. Decided Open
27 May 2026 Strategic Risk ManagementThat the report be noted. Noted Open
27 May 2026 AGS Action Plan MonitoringThat the progress and steps yet to be taken on the Action Plan be noted. Noted Open
27 May 2026 Annual Governance Statement 2025/26(1) That the Annual Governance Statement for 2025/26 be recommended for adoption and for signing by the Chief Executi... Approved Open
27 May 2026 Review of the Regulation of Investigatory Powers Act 2020 (RIPA) Policy and ProcedureThat RIPA Policy be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies