That Planning Permission be granted, subject to the conditions relating to the following matters, as set out in the case officer’s report, with amendment to condition 5: 1. Standard 3 year timescale. 2. Development in accordance with approved plans. 3. Ecology: Provision of 8m stand off to Pinfold Beck; and submission and approval of long term Management Plan. 4. Submission and approval of Tree Works Schedule; approved Arboriculture Implications Assessment and Arboriculture Method Statement to be implemented. 5. Submission and approval of a scheme indicating the type and distribution of all new trees and hedgerows to be provided to reinforce boundary planting, including landscape maintenance. 6. Highways and Traffic: C onstruction Method Statement; access dimensions and paving, vehicle manoeuvres in forward gear, visibility splays on Saddler Nook Lane, offsite highway improvements. 7. 8. Surface Water Drainage: development in accordance with the submitted FRA; appropriate surface water drainage scheme to be submitted; no occupation of development until completion of SuDS in accordance with agreed SuDS Scheme and Management & Maintenance Plan; Surface Water Lifetime Management and Maintenance Plan; and Construction Phase Surface Water Management Plan Approval. Removal of the solar installation at the end of its operational life and restoration of site to previous use. And subject to the following conditions (suitably worded): 9. 10. 11. Materials, colours and finishes of all structures to be agreed. Requirement for notification of when development commences the generation of electricity. Restoration of site (in accordance with a scheme to be agreed) no later than 30 years after development first generates electricity or within 6 months of 1 year non-electricity generation (whichever the earlier).
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Land North Of Saddler Nook Lane Installation of arrays of 2.7m high PV panels, Whittington underground cabling, inverter and transformer Lancashire cabinets, substation, control room, 2m high deer proof fencing and CCTV mounted on 3.5m high masts, together with construction of internal access roads to form a solar farm
Name of Applicant Name of Agent
[name removed] Target Date Reason For Delay
9 November 2015 N/A
Case Officer [name removed] No
Summary of Recommendation Approval
1.0The Site and its Surroundings
1.1The proposed application site is approximately 10.1 hectares and comprises agricultural land, located north of Saddler Nook Lane, Whittington. The site is 1km north west of Whittington and 2km south west of Kirkby Lonsdale.
1.2The site is split into two separate fields by a dry stone wall. The western site slopes gently downwards towards the east; the northern part of the eastern site slopes gently downwards towards the south; and the southern part slopes gently downwards towards the north. The boundaries of the site comprise dry stone walls, with intermittent mature trees and low hedges. Existing gates permit access to each field.
1.3The site is bounded to the north and west by agricultural fields and to the east by Saddler Nook Lane and to the south by an unnamed road linking Whittington and Burton-in-Kendal.
2.0The Proposal
2.1The principal elements of the proposed development are as follows:
Solar arrays – Fixed solar PV panels, mounted on metal frames and set into the ground by piling. The panels are non-reflective. They would be arranged in east-west rows and are tilted southwards at approximately 25-30 degrees from the horizontal, with a maximum height above ground of approximately 2.7m to the top of the panel frame on level ground. The lower edge of the array would vary in height above ground, but would be generally between 0.7m and 0.9m above the ground level, which would allow grazing beneath and around them or would promote biodiversity. There would be approximately a 5m gap between the rows of panels.
Inverters and transformers – PV panels generate direct current (DC) electricity, which must be converted to usable alternating current (AC) power for the electricity distribution network. This is done by inverters. Each megawatt (MW) capacity also requires a transformer to increase the AC current from low voltage to high voltage for efficient transportation around the site and to the point of grid connection. These components are stored in cabinets which are approximately 12.8m length x 2.5m width x 3.1m height.
Sub-station – This would consist of two pre-fabricated cabins, located next to each other. One would be for the internal connection of the electrical output from the site, with the other required by the Local Distribution Network Operator (ENW) for connection into the wider electricity network via underground cables (a grid connection agreement with ENW has been secured). The former would be 5.9m long, 2.9m wide and 3.5m high including a 400mm concrete platform whilst the latter would be 5m long, 4.5m wide and up to 4m in height, including a 400mm platform.
Control Room – A control room would be situated next to the substation buildings near the northern boundary of the site. The control room would be a single storey building and would measure up to 12.2m length x 4.1m width x 2.9m height.
Fencing – A security/deer fence up to 2m high is required around the perimeter of the solar farm. The fence would be welded mesh with steel/wooden posts.
Lighting – No permanent lighting is proposed. Manually operated lights may be attached to the substation and transformer and/or inverter cabinets in the event of an emergency maintenance visit being required in the hours of darkness.
CCTV – Twenty four infra-red security cameras would be located around both sites, at a height of approximately 3.5m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.