That subject to the applicant signing and completing a legal agreement to secure the obligations as contained within Paragraph 8.1, Planning Permission be granted subject to the following conditions: 1. Standard 3 year timescale. 2. Development in accordance with approved plans (to be listed). 3. Working programme. 4. Hours of works (0800-1800 Mon to Fri and 0800-1400 Sat only). 5. Detailed plans of site access. 6. Off-site Highway Works. 7. Protection of visibility splays 2.4m x 120m. 8. Car parking to be provided. 9. Garages for use of motor vehicles only. 10. Details of cycle parking and refuse provision (dwellings without garages). 11. Development in accordance with the submitted AIA. 12. Submission of a Tree Works Schedule. 13. Provision of landscaping scheme. 14. Scheme of enhancement for ecology. 15. Development in accordance with the FRA. 16. Surface water drainage scheme. 17. Finished floor and site levels. 18. Open space – including provision of 5 pieces of play equipment, maintenance, timetable for implementation. 19. Material samples. 20. Details of retaining walls and boundary treatments, including finishes. 21. Unforeseen contaminated land assessment. 22. Removal of the PD rights. 23. Vehicle charging points.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Land To The Rear Of Pointer Grove And Erection of 66 dwellings with associated access, Adjacent To High Road landscaping, open space, drainage, highway and Halton parking arrangements and land re-profiling works Lancashire
Name of Applicant Name of Agent
Russell Armer Ltd. [name removed] Target Date Reason For Delay
9 June 2017 Amended plans and re-consultation
Case Officer [name removed] No
Summary of Recommendation Approval
(i) Procedural Note
A site visit was arranged for Committee Members to view this particular site prior to the Committee meeting. This was undertaken on 19 June 2017.
1.0The Site and its Surroundings
1.1The site is in the region of 4.3 hectares in area, and is 47.50 metres Above Ordnance Datum (AOD) at its lowest part of the site (south west corner) and rises to 76.50 AOD metres towards the north eastern corner. The average site gradient is approximately 1:10. The northern half of the site has a steeper gradient when compared to the southern part of the site. The site is located on the eastern periphery of the village in the region of 550 metres from St Wilfrid’s Primary School and 240 metres from the parade of shops on High Road. There are agricultural fields beyond the site to the north west, north, east and south east. To the west and south west are residential properties on High Road and Pointer Grove. Kirkby Lonsdale Road / High Road runs along the southern boundary.
1.2The site is currently used for agricultural purposes and there are no buildings located on the site. The site is bound by a mature hedgerow on all the aspects with some isolated trees on the boundaries of the site. There are two culverted watercourses that traverse the site converging to a single watercourse.
1.3The site is not situated within any ecological designation or nationally protected landscape (although the Forest of Bowland AONB is 500 metres to the south east). Footpath number 11 is located 100 metres to the north west and Halton Conservation Area is located 440 metres to the south west of the site. Whilst not within the site, an Ash Tree in the control of 195 High Road is protected by a Tree Preservation Order 235 (1995).
2.0The Proposal
2.1The scheme proposes a total of 66 residential units and this is proposed to be made up of the following mix: Affordable (26 Units)
Four x 1 bedroom homes Eleven x 2 bedroom homes Nine x 3 bedroom homes Two x 4 bedroom homes
Open Market (40 Units)
Twenty five x 3 bedroom Fifteen x 4 bedroom
2.2The units will consist of detached, semi-detached, townhouses, terraced houses and apartments. Due to the levels across the site some of the units proposed are to be split level units. Materials include a mixture of natural stone, roughcast render and timber style boarding. Roofing materials are proposed to be slate. Boundary treatments predominately consist of 1.8m high fencing however there are hedgerows and stone walls also proposed. Given the change in levels across the site many of the gardens include retaining walls.
2.3A new access is proposed onto High Road which includes a 5.5 metre wide access road with a 6m kerb radii and visibility splays of 2.4 x 120 metres are proposed in each direction. The scheme proposes a sustainable drainage system which would be a feature within the centre of the site with open space and landscaping across the site (incorporating a large woodland area to the north). A play area is proposed in the southern part of the site.
3.0Site History
3.1The only relevant history is the pre-application advice that was offered to the applicants in 2015.
Application Number Proposal Decision 15/01050/PRETWO Residential development including infrastructure and Advice provided access
4.0Consultation Responses
4.1The following responses have been received from statutory and non-statutory consultees:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.