Resolved
- 1) That the latest monitoring position be noted. 2) That the proposed revisions to the audit plan, as set out in 1.3 of the report be approved.
Audit Committee noted this item on Wednesday 13 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
- 1) That the latest monitoring position be noted. 2) That the proposed revisions to the audit plan, as set out in 1.3 of the report be approved.
To advise Members of the latest monitoring position regarding the 2017/18 Internal Audit Plan and seek approval for proposed variations to the plan.
This report is public
RECOMMENDATIONS (1) That the latest monitoring position is noted. (2) That the proposed revisions to the audit plan, as set out in 1.3 are approved.
1.0Audit Plan monitoring to 15 August 2017 1.1 The 2017/18 Internal Audit Plan was approved by the Audit Committee at its meeting on 28 June 2017. This report is based on the monitoring position up to 15 August 2017 and a monitoring report as at that date is detailed below. A further table at 1.3 shows the minor amendments made to the audit plan since its original approval. 1.2 Summary of monitoring position at 15 August 2017
Report Status
Final Assurance Draft Category of Audit Fieldwork Comments Issued Level Issued 2016/17 Audit Plan work HB subsidy claim – overpayments Substantial 1% Rent reductions Substantial Equality Act Financial systems Budgetary control Q3 Income management Q3 Main Accounting Q3 Core management Procurement Q4 Report Status
Final Assurance Draft Category of Audit Fieldwork Comments Issued Level Issued Core management cont. Asset management Business planning Q4 Contract management Financial planning and MTFS Q3 Performance management
Recovery of legal fees and court costs
Compliance to scheme of delegation
Salt Ayre leisure
Council house voids Q3 Local plan Q4 Voluntary faith community sector Q4 Learning and development
Green waste collection Q3 Revenue shared service financial systems NNDR – Strategic Council Tax See 1.3 Unified benefit Housing benefit Other areas of work Canal corridor north project On-going Annual governance review and Completed statement Risk management and assurance On-going framework PSIAS review – moderation and On-going preparation for Assessment National Fraud initiative exercise On-going 2016/17 Counter fraud work On-going
1.3Following approval of the audit plan in June 2017, discussions have taken place with the Revenue Manager and it has been agreed that the revenue shared service financial system audits would be as follows;
Report Status
Final Assurance Draft Category of Audit Fieldwork Comments Issued Level Report Revenue Shared Service Financial Systems NNDR – Strategic (rate avoidance) NNDR – Transactional E-Claims Q3 2.0 Investigations / other activity
2.1Following an internal investigation at the White Lund Nursery by the Organisational Development Manager, Internal Audit were asked to give assurance on the key controls in place around policies and procedures, access and security and cash and banking. Overall, a ‘limited’ assurance level was given and eight recommendations were made in total. A follow-up review has been scheduled for December 2017 when it is expected that all recommendations will have already been implemented. The final report has been issued to key personnel, however due to the confidential nature of a number of findings; the report will not be published on the intranet.
3.0Details of Consultation 3.1 Management Team continues to be consulted in developing the plan.
4.0Options and Options Analysis (including risk assessment) 4.1 Regarding the Internal Audit Plan minor changes, the options available to the Committee are either to approve the proposed changes or to propose an alternative course of action.
5.0Conclusion 5.1 Minor changes have been made to the 2017/18 audit plan in respect of internal audit work under the revenue shared service arrangement. There have been no changes made to the number of allocated days, which currently stands at 42 days. 5.2 The programme of audits for the rest of the year continues to be implemented in consultation with senior management.
CONCLUSION OF IMPACT ASSESSMENT (including Diversity, Human Rights, Community Safety, Sustainability and Rural Proofing)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit MonitoringReport | 289 KB | DownloadRead as text |
Follow Audit Committee at Lancaster and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 May 2026 | Appointment of Vice-ChairThat Councillor David Whitaker be appointed Vice-Chair of the Audit Committee for the municipal year 2026/27. | Decided | Open |
| 27 May 2026 | Strategic Risk ManagementThat the report be noted. | Noted | Open |
| 27 May 2026 | AGS Action Plan MonitoringThat the progress and steps yet to be taken on the Action Plan be noted. | Noted | Open |
| 27 May 2026 | Annual Governance Statement 2025/26(1) That the Annual Governance Statement for 2025/26 be recommended for adoption and for signing by the Chief Executi... | Approved | Open |
| 27 May 2026 | Review of the Regulation of Investigatory Powers Act 2020 (RIPA) Policy and ProcedureThat RIPA Policy be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.