That Planning Permission be granted but delegated back to the Planning Manager to allow for an updated site plan to be received and an Arboricultrual Implications Assessment and subject to the following conditions: 1. Standard 3 year timescale. 2. Development to be carried out in accordance with the amended plans. 3. Construction management plan (to detail suitable delivery arrangements, works compound areas and customer, staff and contractors parking provision during construction). 4. Implementation of approved Arboricultural Implications Assessment. 5. Remove polytunnels and structure indicated on site plan prior to erection of any of the extensions hereby permitted. 6. Off-site highways improvement works to signage and road marking prior to first use or occupation. 7. Parking provision and service yard provided in full prior to first use or occupation and retained for this purpose. 8. Landscaping planting scheme is to be submitted and approved in writing prior to the commencement of development, implemented in first planting season following completion of development or first use, whichever is earlier . 9. Sales area and café seating area as per floorplan. Café use incidental to main use and only open to public when garden centre is trading. Restriction for the sales of plants and garden related items only.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Bay View Garden Centre Demolition of various buildings, erection of Mill Lane glasshouse and open sided canopies, construction of Bolton Le Sands car park and associated landscaping Carnforth
Name of Applicant Name of Agent
L And P Clarke [name removed] Target Date Reason For Delay
2 August 2018 Committee cycle
Case Officer [name removed] Yes
Summary of Recommendation Approval subject to agreement on tree details
(i) Procedural Matters
The application would ordinarily be determined under delegated powers, but the scheme is a departure from the Development Plan (given its location within the North Lancashire Green Belt), and Officers are recommending support of the scheme. Therefore it has to be determined by Planning Committee.
1.0The Site and its Surroundings
1.1The application site relates to an established garden centre in Bolton-le-Sands, to the west of the railway (the west coast mainline) and to the north of Mill Lane. The site is immediately north of an existing dwellinghouse within the same ownership, and part of a built cluster of former mill buildings, now converted to predominantly residential dwellinghouses and a small furniture warehouse. The site is within the North Lancashire Green Belt and the District’s Countryside Area, and approximately 150 metres west of the site is the Lancashire Coastal Way public right of way route, beyond which is the Morecambe Bay Special Area of Conservation, Special Protection Area, RAMSAR, and Site of Special Scientific Interest (SSSI).
2.0The Proposal
2.1The application proposes the installation of walls to the existing open ended structure to partially enclose this space for garden centre sales and café seating area, with an extension to this retail space projecting 10.8 metres to the north of the existing structure and a further 9.6 metre projection to provide an open sided canopy for the display of plants under protection from the weather. Another open sided canopy area, measuring 7.6 metres by 22.3 metres, is also proposed to the east of the proposed extension, linking the two existing buildings and the proposed extensions. To facilitate the proposed extensions, the following is proposed: additional car parking and service yard area with associated landscaping; removal and demolition of a number of existing polytunnels and structures; and amalgamation of the covered space into the retained buildings. 3.0 Site History
3.1The most relevant planning application and pre-application advice to the site is set out below:
Application Number Proposal Decision 95/00168/FUL Erection of two poly tunnels Permitted 00/00247/FUL Erection of a greenhouse extension Permitted 06/01576/FUL Erection of a replacement shop and new cafe building and Permitted improvements to car park 16/00127/PREONE Erection of a Venlo greenhouse extension to current Advice provided building
4.0Consultation Responses
4.1The following responses have been received from statutory and non-statutory consultees:
Consultee Response Parish Council No observation received Tree Protection Objection due to the lack of detailed tree related information submitted with the Officer application proposing the removal of trees County Highways No objection, subject to the agreement of a construction method statement and additional signage and road markings to mitigate increased traffic movements and maintain highway safety Environmental Health No observation received Network Rail No objection. Comments regarding requirements for works within proximity to the operational railway Cadent Gas No objection. Comments regarding requirements for works within proximity to gas pipes
5.0Neighbour Representations
5.1No observations received to date, with the publication, advertisement and site notice consultation period due to expire on 10 August 2018. Any consultation responses received will be reported verbally to the Planning Committee meeting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.