That Planning Permission be granted subject to the following conditions: 1. Standard three year timescale. 2. Development in accordance with amended plans. 3. Agreement of details of soil permeability test and surface water drainage and flooding scheme. 4. Accord with Geo-Environmental Appraisal Report recommendations. 5. Accord with the arboricultural details. 6. Accord with Habitat Survey Report recommendations, including external lighting details. 7. Accord with Air Quality Report recommendations, namely 2 electric vehicle charging points. 8. Provide parking, bike and bin store, retain and maintain at all times for the office and leisure centre uses. 9. 10. Implement landscaping and planting scheme. Surface water drainage management scheme.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Land To The East Of 315 Health Club Change of use of car park to facilitate the erection of Mannin Way a three storey office building (B1) with associated Lancaster parking, access road, bin store, landscaping and Lancashire boundary fencing
Name of Applicant Name of Agent
Butarose Ltd [name removed] Target Date Reason For Delay
4 February 2019 None
Case Officer [name removed] None
Approval in principle but delegate back to agree Summary of Recommendation drainage details with Lead Local Flood Authority
1.0The Site and its Surroundings
1.1The site that forms the subject of this application is within the Lancaster Business Park on Mannin Way, accessed off Caton Road near junction 34 of the M6 Motorway. Access to the site is currently managed via a traffic light controlled (signalised) junction from Caton Road. More specifically the site forms part of the existing car parking and landscaping to a Leisure and Health Club, which currently has 428 spaces. This application is located within a modern business park built in 2002 that comprises mainly office development. There are a number of standard trees and low level shrub planting established within designated planting areas of the existing car park. These trees are generally early-mature trees with long periods of useful remaining life potential with good management. To the east of the car park lies disturbed land, colonized by a range of low vegetative cover and no significant trees. To the south and south-east is a significant woodland area, known as Long Bank Wood Biological Heritage Site, which provides a significant backdrop to the site and wildlife resource within the Lansil Golf Course, which is a designated open space. To the north of the site is a slightly raised area of land containing a large number of early-mature trees.
2.0The Proposal
2.1The proposed development seeks to utilise the area of car park to the east of the main leisure centre for the erection of a three storey office building with associated parking, access, bike shelter, landscaping, boundary treatments and bin storage. The proposed 3 storey building measures 42.7 metres long by 13.8 metre wide, with a 1.7 metre eaves overhang to all sides. The development is under a shallow duo-pitched gable roof with a maximum 12 metre eaves height and maximum ridge height of 13.5 metres tall. The development is to be finished in reconstructed stone walling with Cromwell split face sandstone under a merlin grey galvanised steel roof sheeting, with floor to eaves high tinted window openings in aluminium frames in anthracite grey colour. A boundary treatment of 1.2 metre tall green paladin fencing is proposed, with extended parking area surfaces in permeable tarmac. The new parking areas will be illuminated by LED lighting on 5 metre tall poles. 3.0 Site History
3.1The most relevant planning history is set out below.
Application Number Proposal Decision 15/00618/CU Change of use of part of car park for use as car boot sales Permitted on Sundays with associated parking 15/00640/CU Change of use of part gymnasium (D2) to a nursery (D1) Permitted and erection of a single storey front extension 13/00678/CU Change of use of car parking spaces into play area and Permitted construction of fencing and footpath 00/00886/FUL Erection of a two storey exercise, hydrotherapy and Permitted rehabilitation centre with associated car park 00/00939/OUT Outline application for erection of mixed use Business Permitted Park incorporating B1 and B2 uses, hotel and public house, and exercise, hydrotherapy and rehabilitation centre and new access
4.0Consultation Responses
4.1The following responses have been received from statutory and non-statutory consultees:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.