That the application be approved subject to the conditions set out in the Committee Report and subject to a Legal Agreement controlling occupancy and that the Head of Planning and Place be delegated to approve the application after the consultation period has expired subject to there being no new material planning issues raised in any further representations: 1. Standard timescale 3 years. 2. Approved Plans. 3. Foul Drainage Details. 4. Protected Species Method Statement. 5. Eradication of Invasive Species. 6. Submission of Employment and Skills Plan. 7. Contaminated Land. 8. Sustainable Drainage Scheme. 9. Construction SW Management Plan. 10. Materials Samples. 11. Finished Floor levels. 12. External Lighting. 13. Landscape Details and Management Plan. 14. Drainage Management Plan/Verification Report. 15. Homeowner Pack. 16. Electric Vehicle Charging Points. 17. Access and Parking. 18. Landscaping Implementation. 19. Nesting Birds. 20. Development in Accordance with FRA. 21. Approved Tree Details. 22. Approved Biodiversity Enhancements. and subject to the following additional condition: · Construction to take place only on Monday to Friday between 0800-1800 and 0930-1400 on Saturdays with no working on Sundays and Bank Holidays.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Erection of 19 holiday chalets with associated access, car parking, landscaping, retention of existing soil mound and installation of a Proposal package treatment plant
Application site Jackdaw Quarry, Capernwray Road, Capernwray, Carnforth
Applicant Hack Enterprises Ltd
Agent [name removed] [name removed] No
Approval - subject to Legal Agreement (However, delegate back to Summary of Recommendation Head of Planning and Place to enable further publicity to expire on 15 October 2021, subject to no new material planning considerations being raised).
1.0Application Site and Setting
1.1This application relates to the established Capernwray Diving Centre at the flooded former Jackdaw Quarry. The site operates primarily as a diving and open water swimming centre, with an ancillary shop, café, changing facilities, office and holiday lodges. The centre is located east of Capernwray Road and northwest of the open water body. The location for this proposal is north and northeast of the water. South of the centre is a residential property and the existing holiday lodges.
1.2The site boundary areas contain woodland of varying thickness with agricultural land beyond to the south, east and north. The nearest settlement is Over Kellet approximately 1.5km to the south. The surrounding area is characterised by agricultural fields separated by hedgerows, pockets of woodland and a number of other holiday accommodation sites of varying sizes including New England Caravan Park to the north and Old Hall Caravan Park to the southeast.
1.3The site is located within the Open Countryside but outside any AONB. It is part of a larger Biological Heritage Site (Overhead Quarry) and many trees, both within and around the borders of the site are covered by Tree Preservation Order 664 (2018). It is within a mineral safeguarding area, class 4 radon protection area where basic measures are necessary, partly in the Shell Stanlow- Grangemouth ethylene pipeline outer zone and within a SSSI impact zone. A public footpath is located 130m to the east.
2.0Proposal
2.1The proposal has been amended at officer’s request to improve the layout to protect existing trees and provide greater landscaping. An existing soil bund has been added to the description as it was unauthorised. As a result of the amendment, the number of chalets has been reduced by one and the locations of the outside row of chalets moved out of the TPO protected woodland. This does Page 1 of 7 CODE 21/00543/FUL push the front row further south along the edge of the quarry. The application is now for siting 19 no. holiday chalets around the northern and northeast of the quarry. 14 chalets will be situated on the cliff edge overlooking the water. The access track will run behind them beyond which will be the other 5 chalets. Two of these are proposed abutting the woodland in the northeast corner and three partially screened by the bund to the north. All chalets will be located at a higher level than the water and dive centre buildings. Towards the rear of the chalets the land falls away to the adjacent fields.
2.2These chalets will be served by dive centre’s existing access off Capernwray Road through its car park and via a new track leading to the chalets and dedicated parking spaces. Also proposed is a new sewage packet treatment plant to serve the new chalets.
2.3The chalets will be a mix of 2 and 3 beds over 1 and 2 floors. The two floor chalets will make use of level changes. All chalets will be constructed of timber cladding (stained dark grey) and natural slate roofs overlain with a green roof of wildflower planting.
3.0Site History
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.