Resolved : That the application be approved subject to the conditions in the officer’s report and subject to an additional condition requiring details and location of the rails to be removed from the altar, and relocated within the building, and those to be retained on the altar: 1. Standard LB timescale. 2. In accordance with amended plans. 3. Prior to their installation, submission of large-scale details of new oak panelling and oak doors. 4. Details and location of the rails to be removed from the altar, and relocated within the building, and those to be retained on the altar.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Listed Building application for internal alterations to provide kitchen and wc`s including new treatment plant, reset floor levels, works to Proposal ceiling, insulation, new partition doors, architraves, skirting and relocation of wall panel
Sunderland Point Mission Heritage Centre The Lane Sunderland Point Application site Morecambe Lancashire LA3 3HS
Applicant [name removed] [name removed] Officer [name removed] No
Summary of Recommendation Approval
(i) Procedural Matters
This form of development would normally be dealt with under the Scheme of Delegation. However, as the full planning application for the installation of a sewage treatment plant (ref: 22/00284/FUL) was called into committee and these two applications are inextricably linked, this application has also been brought forward to be determined by the Planning Regulatory Committee. The scheme was presented before Planning Committee on 18 July 2022 however it was deferred for a site visit. The site visit occurred on 8 August 2022. The scheme is therefore being re-presented.
1.0Application Site and Setting
1.1Sunderland Point Mission Heritage Centre is a Grade II Listed former mission church dating back to 1894. The building was designed by Austin and Paley and illustrates the process of spreading the Church of England mission to remote coastal locations during the late 19th century and early 20th century. The building is rectangular in shape and has been constructed from local Claughton red brick with a Westmorland slate roof. Its use as a Church has recently ceased with the building now under the ownership of the Mission Heritage Centre Trust. The building stands as an independent structure on the south side of ‘The Lane’ and is bounded by open fields. The site forms part of Sunderland Point Conservation Area.
1.2The official Historic England listing is as follows:
EXTERIOR: a five bay, single-storey building of red brick laid in stretcher bond beneath a pitched roof of Westmorland slate, that sweeps low over the projecting porch and vestry and WC in the form of lean-to roofs. Windows and door openings mostly have brick, camber heads. The west end has a central, projecting timber bell canopy that retains the bell, above an external, stepped brick chimney Page 1 of 6 CODE 22/00481/FUL stack with tumbling-in brickwork. To the left is the main camber-headed entrance, and to the right is a secondary opening of similar style; both with plain boarded doors. The north elevation has projecting end bays, the porch to the right with a plain window beneath a stone lintel, and the vestry with a camber-headed entrance. The blind central bay is demarcated by a pair of slim pilasters, and a flanking bay to either side has a camber-headed window fitted with a six-light fixed timber window. The east end is rendered obscuring the brickwork, but there is a single camber-headed window. The south elevation is similarly detailed to the north elevation but only the westernmost bay is projecting, with a pair of short ventilation slits to its east wall.
INTERIOR: the porch has painted brick walls with three rows of coat hooks, and opens into the main body of the church through double boarded doors. There is a timber baffle screen to the left, and horizontal wainscoting to the lower parts of the walls, which are painted brick above, and there is a boarded floor. The original stove to the west end has been removed but its semi-circular opening remains. At the east end there is a raised dais with an altar and timber rails to the front; the wainscoting raises above the altar table, and above this is a large camber-headed timber panel. The roof structure comprises four triangular tie-beam trusses supported by cast-iron struts. The small vestry niche to the left has wainscotted walls.
2.0Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.