Resolved : That the application be approved subject to: · an additional condition regarding waste and recycling bin storage; · an additional condition for an off-site highway mitigation scheme to Carr Lane following successful resolution of negotiations between the Chief Officer Planning and Climate Change and Lancashire County Council as the Local Highway Authority; and subject to the completion of the Section 106 Legal Agreement and conditions set out in the Committee Report: 1. Time Limit (2 years). 2. Approved Plans. 3. Employment Skills Plan. 4. Construction Environment Method Statement including HRA mitigation (during construction). 5. Development to be carried out in accordance with the mitigation set out in the PEA, with detailed Reasonable Avoidance Measures (RAMS) first greed in writing by the LPA. 6. Surface Water Construction Method Statement. 7. Drainage scheme. 8. Final finished floor levels and garden/amenity space levels. 9. Precise details of the sustainable design measures to be incorporated into the design of the dwellings as per the Energy Statement. 10. Materials and architectural detailing to the dwellings. 11. Construction details of all access roads, footways and turning facilities and timetable for provision in full. 12. Full details of the bus turning facilities and bus stop and timetable for provision. 13. Travel Plan. 14. Provision of Homeowner Packs. 15. Precise details of all play equipment and street furniture. 16. Landscaping Maintenance Scheme. 17. Suds Maintenance Scheme. 18. Site Remediation Strategy. 19. Implementation of approved landscaping scheme. 20. Parking Provision. 21. M4(2) to the identified plots. 22. FRA mitigation. 23. Obscure glazed windows to plot 1. 24. Removal of PD rights (extensions, roof additions and outbuildings).
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Erection of 49 dwellings (C3) with access, associated infrastructure Proposal including provision of bus turning circle, open space and landscaping Site Of Former Pontins Holiday Camp Natterjack Lane Application site Middleton Lancashire
Summary of Recommendation Approve subject to conditions and a legal agreement.
(i) Procedural Matter
Representatives of the Planning Committee visited this site on the 12 June 2023 in preparation for the application being reported to committee after the summer period.
1.0Application Site and Setting
1.1The application site relates to three small parcels of land (totalling 2.4 hectares) within the wider Middleton Towers site, which is identified as a Development Opportunity Site (DOS) allocation in the Local Plan. Middleton Towers, once the former Pontins holiday site, is a 23-hectare site accessed solely from Carr Lane. The allocated site is located just over 1km west of Middleton village with Heysham village located approximately 3km north of the site. Overton is situated approximately 2.4km east (as the crow flies) of the site. It is bound by Ocean Edge Caravan Park, Middleton Nature Reserve and Heysham Industrial Estate to the north with Heysham Power station beyond. East of the site lies Carr Lane Meadows Biological Heritage Site and Middleton Holiday Park with open countryside to the south and a number of caravan sites situated alongside the coastline.
1.2The allocated site currently comprises 53 existing dwellings, originally built as part of the first phase of the retirement village, and three grade II listed buildings (The Tower, Ye Olde Farmhouse and the Tudor Bar). Apart from the Tower, these buildings were previously communal leisure/management facilities for the existing development. The remainder of the wider site remains vacant in varying condition, with large parts overgrown with scrub vegetation. Currently the wider Middleton Towers site is divided into two distinct parcels. The northern parcel is completely undeveloped brownfield land following the demolition and removal of the remnants of the former Pontins holiday park. The southern parcel, which this application site lies within, is partly developed, and includes the 53 dwellings and additional development to the west, including the group of listed buildings.
Page 1 of 32 CODE 23/00398/FUL 1.3 Access is taken off Carr Lane (public highway) into the existing private gated estate. A small gatehouse sits adjacent to the site access though this is not manned on a permanent basis. Access to the estate is via a number keypad for residents of the development. There are no public rights of way through the site.
1.4The application site is split across three parcels of land connected by a section of Natterjack Lane, which forms the main spine road running through the existing development.
1.5The site is broken down into three main parcels of land:
Parcel A – Land north of Natterjack Lane/west of Lavender Way This comprises 0.69 hectares of land. It currently consists of a small semi-circle of managed grassland which is open and accessible to residents. The remainder of this land is enclosed by fencing and is partly used as a site compound for the adjacent development and is vacant scrubland. A small stone substation occupies this parcel of land which is serviced by an existing access road. This section of the site is largely level with an elevation around 11.2 metres Above Ordnance Datum (AOD).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies