Resolved : That the application be approved subject to the conditions in the Committee Report and subject to delegation back to the Chief Officer – Planning and Climate Change for finalisation of planning obligation; - and subject to the following conditions: 1. Timescale. 2. Approved plans. 3. Temporary consent and decommissioning. 4. CEMP. 5. Construction Traffic Management Plan. 6. Surface water drainage strategy. 7. Standard contaminated land condition. 8. Control of invasive species. 9. Details of materials: colour and finish to containers; details of fencing; details of surfacing; details of green roof; details of building colours. 10. Details of external lighting. 11. Soft landscaping scheme. 12. Details and installation of road upgrades. 13. Ecological Impact Assessment mitigation strategy. 14. Risk reduction strategy.