Capital Programme 2026/27 - 2035/36 & Capital Strategy (Invested in the Future)
ApprovedCommittee4 papers
AI summaryLancaster City Council approved its 2026/27 to 2035/36 General Fund Capital Programme and Capital Strategy [D]. The net programme is £44.803M, with £30.187M anticipated from external funding [2.4]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet programme total is £44.803M [2.4]
Money£44.803M net programme [2.4]£30.187M external funding anticipated [2.4]
What happens nextBusiness cases required first [2.5]CAG review, then Cabinet approval [2.5]
Who it affectsResidents and Council services [2.1]Capital investment supports strategic projects [2.1]
What was decided
Council unanimously noted the report and approved the General Fund Capital Programme in Appendix A for 2026/27 to 2035/36, subject to recommendation 2. Report P5, P6
Council approved the Capital Strategy in Appendix B, including the Capital Investment Strategy: Investing in the Future. Report P7
Why
Cabinet had finalised the budget framework proposals so Council could approve the programme and adopt the strategy required by regulation. Report P2
Capital investment plays a key role in strategic projects and in transforming and improving Council services for residents. Report 2.1
The Capital Strategy provides the policy framework for developing, managing and monitoring capital investment. Borrowing must remain affordable, prudent and sustainable. Report 4.0, 2.8
What happens next
Each Under Development scheme needs a full business case approved first by the Capital Assurance Group and then by Cabinet before it can start. The group will also oversee financing for affordability, prudence and sustainability. Except in an emergency, revisions are limited to the October or November committee cycle. Report 2.5, P37, P36
Full business cases will also be subject to independent third party review, depending on factors such as complexity and investment levels such as c.£1.5M. Review results form part of the submissions to the group and Cabinet. Report 2.5
Any funding shortfall must come from borrowing. Business cases must show that investment income covers all borrowing costs and produces a positive return to the revenue budget. Report 2.6
The money
£44.803M Total net programme from 2026/27 to 2035/36 Report 2.4
£74.990M Gross investment currently planned over the next 10 years Report 2.4
£30.187M External funding anticipated for this investment Report 2.4
£71.89M Estimated Council borrowing position in 2025/26 Report 3.4
£81.81M Forecast Council borrowing position in 2027/28 Report 3.4
£110.06M Estimated Capital Financing Requirement in 2025/26 Report 3.2
£119.79M Forecast Capital Financing Requirement in 2027/28 Report 3.2
£16.121M Current year revised net programme, for information only Report 2.4, P14
Options considered
Chosen: Approve the proposed General Fund Capital Programme and Capital Strategy. Cabinet had finalised the proposals and regulation required adoption of the Capital Strategy. Report P6, P7, P2, 5.0
Rejected: Put forward alternative proposals or amendments to the strategy. Proposals for 2026/27 had to balance, and officers might need time to assess risks and implications. Any change would require revised prudential indicators. Report 5.2, 6.2
Implications
Financial: The programme is balanced, with an increase in the underlying need to borrow over the five year period to 2030/31. Report 2.7
Financial: The Council's borrowing position is projected to rise from £71.89M in 2025/26 to £81.81M in 2027/28, then reach £81.69M in 2030/31. Report 3.4
Financial: Capital investment will require borrowing and related costs, subject to financial due diligence. Annual total financing charges are forecast to rise from 2026/27 to 2029/30 before easing in 2030/31. Report P47, P33, 3.7
Risk: The forecast General Fund financing cost ratio reaches 24.32% in 2028/29. The report says rates close to 25% need care with future capital investment. Report P33
Risk: Schemes Under Development cannot start until full business cases are approved. Any funding shortfall will need borrowing, and the business case must show income covers borrowing costs and gives a positive revenue return. Report 2.5, 2.6
Legal: The Council may acquire, use and dispose of land under the Local Government Act 1972 and other Acts. Disposals must obtain best value, subject to very limited exceptions, and other statutory procedures may apply. Report P48, P49
Risk: Any Council change to the Capital Programme would require changes to the prudential indicators in the Treasury Management Strategy. Report 6.2
Other: The proposed budget includes measures for the climate emergency and digital improvement, plus activity for wellbeing, health and community safety. Report P46
Key Council officers, the Finance Portfolio Holder and committee chairs Report 4.2
Budget and Performance Panel and Overview and Scrutiny Committee Report 1.2, 4.2
Canal Quarter and Redevelopment of the City schemes Report 2.6
Major economic development projects Report 4.3
Timeline
12th December 2025: Notice date for the forthcoming key decision Report P3
10 February 2026: Cabinet finalised the budget framework proposals
11 February 2026: Budget and Performance Panel considered the Capital Strategy and made no formal comments Report 1.2
25 February 2026: Council approved the Capital Programme and Capital Strategy Report P1
2025/26: The current year net revised programme is £16.121M and is for information only Report 2.4, P14
2026/27 to 2035/36: General Fund Capital Programme period Report P6
2027/28: Capital Financing Requirement and borrowing are forecast at £119.79M and £81.81M Report 3.2, 3.4
2030/31: Capital Financing Requirement and borrowing are forecast to fall to £110.69M and £81.69M Report 3.2, 3.4
Plain English for the jargon
General Fund Capital Programme: Schedule of proposed capital investment for 2026/27 to 2035/36. [2.4]
Capital Strategy: Overarching policy framework for capital investment, including the programme, asset plan and Treasury Management Strategy. [4.0]
Capital Financing Requirement (CFR): Total capital expenditure not yet paid from revenue or capital resources. It measures the Council's underlying need to borrow. [3.2]
Minimum Revenue Provision (MRP): Annual revenue charge that reduces borrowing need in line with each asset's life. [3.3][3.7]
Capital Assurance Group (CAG): Group that reviews capital business cases and oversees capital financing. [2.5][P37]
Under Development: Schemes with outline business cases approved in principle but not yet able to commence. [2.5]
Treasury's 5 case model: Scoring criteria covering strategy, economics, finance, commercial matters and management. [4.2]
Capital receipts: Monies received from the sale of a capital asset. [3.1]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item124
Resolved
Resolved unanimously: That Council notes the report and approves the following: (1) That the General Fund Capital Programme as set out at Appendix A, be approved subject to recommendation 2 below (2) That the Capital Strategy (Incorporating the Capital Investment Strategy: Investing in th e Future) as set out at Appendix B, be approved
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
COUNCIL Capital Programme 2026/27 – 2035/36 & Capital Strategy (Investing in the Future) 25 February 2026
Report of Chief Finance Officer PURPOSE OF REPORT To present Cabinet’s final budget proposals in order that the Council can approve a General Fund Capital Programme for 2026/27 to 2035/36, and a Capital Strategy 2026/27 as required by regulation.
Key Decision X Non-Key Decision Referral from Cabinet Member Date of notice of forthcoming key decision 12th December 2025
RECOMMENDATION OF CABINET
That Council notes the report and approves the following:
(1) That the General Fund Capital Programme as set out at Appendix A, be approved subject to recommendation 2 below
(2) That the Capital Strategy (Incorporating the Capital Investment Strategy: Investing in the Future) as set out at Appendix B, be approved
1.0INTRODUCTION 1.1 Following its meeting on 10 February 2026 Cabinet has now finalised its budget framework proposals for the General Fund Capital Programme and accompanying Capital Strategy. These are all now reflected in the recommendations of this report.
1.2In line with the Council’s Constitution the Capital Strategy was considered by Budget and Performance Panel on 11 February 2026, no formal comments were made for inclusion in this report.
2.0CAPITAL PROGRAMME
2.1Capital investment, via the Council’s reserves or borrowing, plays a key role in strategic projects and initiatives for the success of the Lancaster district, as well as transforming and optimising the Council’s services to its residents.
2.2The proposed Capital Programme and supporting Strategy, entitled ‘Investing in the Future’ and contained at Appendix B, sets out the relevant context and a proposed framework to support the Council’s approach to capital investment over the medium term. 2.3 The proposed net investment programme for General Fund for the period to 2035/36 is included at Appendix A and summarised in the table below. Note that the shaded column (2025/26) is for information only and not included in the grand total.
Grand 2031/32 2032/33 2033/34 2034/35 2035/36 Total £’M £’M £’M £’M £’M £’M Approved Schemes 6.429 4.994 2.181 2.227 0.050 29.425 Schemes 0.100 0.040 0.200 0.000 0.000 15.378 Under Development TOTAL 6.529 5.034 2.381 2.227 0.050 44.803
2.4The current year’s net revised programme (2025/26) now stands at £16.121M. During the next 10 years, a further gross investment of £74.990M is currently planned with external funding of £30.187M anticipated to support this investment, giving a total net programme from 2026/27 to 2035/36 of £44.803M.
2.5Schemes classified as Under Development have had strategic outline business cases approved in principle by the Cabinet but cannot commence until full business cases have been considered and approved, first by the Capital Assurance Group (CAG), and then by Cabinet. In addition, depending on certain factors such as the complexity of the project, the level of investment required (c.£1.5M) etc the full business cases will be subject to independent 3rd party review, with the results forming part of the CAG and Cabinet submission.
2.6Two schemes included within the Schemes Under Development section of the Capital Programme, Canal Quarter and Redevelopment of the City are anticipated to receive external funding which will at least partially finance the costs of these works. Any shortfall in financing for these schemes plus all other projects currently in this section will need to be funded from borrowing. The business cases will need to demonstrate that income arising from the capital investment can cover all borrowing costs and deliver a positive return to the Council’s revenue budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Allocation of seats to political groupsResolved (unanimously): That the Council note the establishment of the Independent Group of Councillors and approve t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.