AI summaryLancaster City Council approved an extension to the Middleton 400kV electricity substation in Heysham, including two new supergrid transformers, subject to 16 planning conditions covering drainage, ecology and noise.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedExtension to 400kV substation at Heysham
MoneyNot stated
What happens nextNot stated
Who it affectsMiddleton substation site, Faraday Road, HeyshamElectricity transmission infrastructure
What was decided
Planning permission was granted for the extension to Middleton 400kV electricity substation, including a new substation and control building, two supergrid transformers, above ground transmission and below ground cabling, access roads, a culvert, surfacing, boundary fence and car parking. Report P1
Why
The recommendation was made in a positive and proactive way under Article 35 of the Town and Country Planning (Development Management Procedure) (England) Order 2015, having regard to the development plan, the National Planning Policy Framework, Planning Practice Guidance and relevant Supplementary Planning Documents. Report P3
What happens next
Several conditions must be discharged before development starts, including Heysham Moss mitigation details, District Level Licencing confirmation and soft landscaping details; other conditions require drainage, lighting and noise details to be submitted before use or installation. Report P2
Options considered
Chosen: Grant planning permission subject to 16 conditions. Positive and proactive recommendation under Article 35, having regard to development plan and national policy. Report P1, P3
Implications
Environment and climate: Conditions require Heysham Moss mitigation, District Level Licencing confirmation, ecological mitigation in line with the Preliminary Ecological Appraisal, and an invasive species eradication and management plan. Report P2
Risk: Conditions address flood risk mitigation, unforeseen contamination, an amended Construction Environmental Management Plan, and a drainage strategy with maintenance and verification reports. Report P2
Other: External lighting details, materials to match existing, and plant noise and mitigation must be controlled. Report P2
Who and where
Electricity transmission network users served by the Middleton 400kV substation
Surrounding environment at Heysham, including Heysham Moss Report P2
Plain English for the jargon
400kV substation: A facility handling electricity at 400 kilovolts, part of the high voltage transmission network.
Supergrid transformer: A large transformer used on the electricity supergrid to step voltages up or down.
CEMP: Construction Environmental Management Plan, setting out how construction impacts are controlled.
PEA: Preliminary Ecological Appraisal, a baseline survey of ecological features on a site.
District Level Licencing: A scheme used by local authorities to satisfy biodiversity obligations for protected species such as great crested newts.
Heysham Moss: A local site referenced for ecological mitigation requirements.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Extension to Middleton 400kV electricity substation including the construction of substation and control building, siting of two new Proposal supergrid transformers, installation of other above ground transmission and below ground cabling, and associated works including internal access roads, culvert, surfacing, boundary fence and car parking. Middleton Substation Faraday Road Application site Heysham Lancashire
Applicant [name removed], National Grid Energy Transmission
Agent N/A
Case Officer [name removed] No
Summary of Recommendation Approve with conditions
1.0Application Site and Setting
1.1The site to which this application relates is the Middleton 400kV electricity substation, located to the north of the A683 Bay Gateway, Heysham. The land is safeguarded for National Grid infrastructure under Local Plan Policy SG13. The existing substation comprises a large, dark green coloured substation building, with associated hardstanding, transmission infrastructure, secure compound and security fencing. The red edge application site also includes land currently used for grazing, adjacent to the existing compound, and also under the ownership of National Grid.
1.2A public right of way (PROW) FP37 passes the site’s boundary to the north, and beyond this lies grazing land. To the west is further grazing land and the Heysham Branch Line. Faraday Road to the east provides vehicular access to the site off a roundabout on the Bay Gateway. The Adopted Policies Map indicates aspirational cycle routes to the north and east of the site. The site lies within the Health and Safety Executive (HSE) Hazardous Installations consultation zone for Heysham 2.
1.3In terms of ecological constraints, the site is within the buffer zone for the Morecambe Bay designated sites (approx. 1.3km distant), Heysham Moss Biological Heritage Site is located approx. 100m to the northeast, and Heysham Moss Site of Special Scientific Interest (SSSI) is located approx. 165m to the northeast. The site is also within a SSSI Impact Risk Zone for all planning applications and infrastructure development) and parts of the site form part of a Priority Habitat (under Section 41 of the Natural Environment and Rural Communities (NERC) Act 2006).
1.4Land to the east of Faraday Road is within Flood Zone 3. There are ordinary watercourses through and adjacent to the site, which are within Flood Zone 3B. Parts of the site are subject to surface water flood risk, and the whole site is at risk of future flood risk (climate change allowances model).
Page 1 of 10 CODE 25/01055/FUL 2.0 Proposal
2.1This application seeks planning permission for an extension to the Middleton 400kV electricity substation including the construction of a substation and control building. The application also proposes the siting of two new supergrid transformers, installation of other above ground transmission and below ground cabling, and associated works including internal access roads, culvert, surfacing, boundary fencing and maintenance/construction vehicle parking.
2.2The proposed new substation building measures approx. 46.2m in length, 20.8m in depth and 14.4m in height. A green metal finish is proposed to match the existing substation building, to which it will be linked by a canopy. The application is made following formal pre-application advice with the local planning authority.
3.0Site History
3.1A number of relevant applications relating to this site have previously been received by the Local Planning Authority. These include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.