Resolved
That the draft internal audit plan for 2014/15 be adopted.
Eastbourne Borough Council Audit and Governance Committee approved this item on Wednesday 12 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the draft internal audit plan for 2014/15 be adopted.
Body: AUDIT AND GOVERNANCE COMMITTEE
Date: 12 MARCH 2014
Subject: Draft internal audit plan for 2014/15
Report Of: Internal Audit Manager
Ward(s) All
Purpose To propose an internal audit plan for 2014/15
Recommendation(s): To consider and adopt the proposed plan.
Contact: Jackie Humphrey, Internal Audit Manager, Telephone 01323 415925 or internally on extension 5925. E-mail address [email protected]
1.0Introduction
1.1The internal audit function contributes to the Council’s overall governance arrangements through the audits carried out in the annual internal audit plan.
1.2The annual audit plan includes a number of managed audits which are required to be carried out by the external auditors and upon which they place reliance for the work of internal audit.
2.0Reviewing the Audit Universe
2.1The Audit Universe is the list of all areas around the Council which can be reviewed. With the work on the Future Model progressing it was considered timely to fully review the list to ensure that it was still fit for purpose.
2.2Meetings were therefore held with Heads of Service to discuss the areas listed which fell within their departments. Each was considered for its relevance and any new areas to be added to the list were also discussed.
2.3The opportunity was also taken to discuss any specific pieces of work that Heads of Service required for consideration in the annual audit plan.
3.0Production of the draft audit plan for 2014/15
3.1The internal audit plan for each year begins by calculating the number of audit days available.
3.2There are twelve “managed” audits which have to be undertaken every year in order to satisfy the external auditors. These are:-
Benefits Cash and Bank Council Tax Creditors Debtors Housing Rents Main Accounting (Financial Ledger) NNDR Payroll Treasury Management IT Theatres
3.3As well as these core audits, work is carried out annually on verifying the NNDR 3 and Benefits Subsidy Claim and time must also be set aside in the audit plan for unplanned work (contingency), advice, special investigations, follow ups, work on the National Fraud Initiative etc.
3.4Once the days necessary to carry out the work listed above are calculated the figure can be taken from the “auditor time available” and the remaining figure is the number of days available for carrying out other audits specifically for the Council. These calculations can be seen as part of Appendix A
3.5In order to produce the annual internal audit plan a risk assessment of the areas listed in the audit universe is carried out by the Internal Audit Manager. Weighting factors used are :-
The number of transactions in the system; System changes; Internal control score (evaluated from last review); Length of time since last review.
3.6The completed risk assessment can be found at Appendix B. This has been sorted by level of risk and then by the date the last audit review was undertaken.
3.7As a general rule high risk areas will always be included in the annual plan. However this year this is not the case. A review of Catering was only carried out toward the end of the last financial year and is still subject to Follow up reviews. The review of the Redoubt was carried out in February 2012 but when last followed up there were still recommendations outstanding. It is considered appropriate to carry out a follow up of the outstanding recommendations to see where they currently stand and a decision on whether further work needs to be carried out can be considered at that point.
3.8The majority of medium and low risk areas which were last audited before 2010 have been included in the plan in order to ensure that their last evaluated risk level is still appropriate.
3.9During the discussions held with Heads of Service certain areas for review were suggested/requested and have also been included in the plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Internal Audit Plan for 2014/15: Appendix A.Appendix | 17 KB | Download |
PDF |
Draft Internal Audit Plan for 2014/15: Appendix B.Appendix | 32 KB | Download |
PDF |
Draft Internal Audit Plan for 2014/15: Appendix C.Appendix | 23 KB | Download |
PDF |
Draft Internal Audit Plan for 2014/15.Report | 31 KB | DownloadRead as text |
Follow Eastbourne Borough Council Audit and Governance Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Item 11 (part) - Scrutiny Committee Work Programme, update on Local Government Reorganisation programme1) That the Committee continue to maintain oversight of Local Government Reorganisation developments; 2) A standing L... | Decided | Open |
| 9 Sep 2026 | Date of the next meetingResolved to note that the next meeting of the Audit & Governance Committee was scheduled to be held on 25 November 20... | Noted | Open |
| 24 Jun 2026 | Treasury Management Annual Report 2025/26Resolved to note the . | Noted | Open |
| 24 Jun 2026 | Annual Report of Eastbourne Borough Council's Audit and Governance Committee 2025-26RESOLVED to approve the recommendations set out in the Annual Report of the Audit and Governance Committee for submis... | Approved | Open |
| 24 Jun 2026 | Draft Internal Audit Plan for 2026/27Resolved to agree the proposed Internal Audit Plan ... view the full minutes text for item 11. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.