Serco Ltd, Serco Yard, Bedfordwell Road. Application ID: 130907 (PPP)

Agreed Planning 1 paper

Eastbourne Borough Council Planning Committee agreed this item on Tuesday 25 March 2014. Below is the council's own wording, with the papers it was decided on.

Item98

Resolved

(By 5 votes to 2) That permission be granted subject to an agreed Section 106 legal agreement. If a satisfactory Legal Agreement cannot be reached within 9 months from the date of this application then the application be refused, and subject to the following conditions : 1) Time limit. 2) Drawing numbers. Prior to Commencement 3) Materials and samples 4) Construction Environmental Management Plan 5) Construction Traffic Management Scheme 6) Updated phase 2 soil investigation and remediation 7) Details of SUDS (Southern Water) 8) Foul sewage disposal details (Southern Water) 9) Changes to ground levels and finished floor levels 10) Lighting Strategy 11) Details of windows or reconfigured layout to 3 rd floor of Pump House 12) Details of new external doors (Pump House) 13) Full details of windows, glazing, ventilation and section showing floor levels 14) Standing building survey recording 15) Updated noise and vibration report 16) Details of refuse facilities and recycling 17) Details of reptiles receptor site, badgers 18) Submission of drawing C115345-01-02 (exclusion fencing layout) 19) Programme of archaeological work 20) Road construction details. Prior to Occupation 21) Boundary treatment 22) Turning spaces 23) Details of cycle parking provision 24) Parking spaces provided 25) Comprehensive landscape plan and biodiversity enhancement 26) Details of acoustic fence to railway boundary 27) Locations of affordable housing units on site 28) Details of secure cycle storage for flats 29) Installation of 230 fugia and monitored by Ecologist 30) Archaeological site investigation and post investigation assessment. In Perpetuity 31) Restoration and renewal alterations like for like (Pump House) 32) Works cease if Great Crested Newts discovered 33) If work not started in 2 years, all surveys updated and submitted 34) New roads in accordance with Highway standards 35) Development implemented in accordance with the FRA 36) Utility pipes, soil stacks to be run internally (Pump House) 37) Contamination not identified 38) Wheel washing facilities 39) Retained trees 40) Details of work to trees 41) No bonfires 42) Working hours 43) No ... view the full minutes text for item 98.
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Planning Committee

App.No: 130907 (PPP) Decision Due Date: 11 Ward: February 2014 Upperton

Officer: Site visit date: 6 January Type: Planning Leigh Palmer 2014 Permission

Site Notice(s) Expiry date: 18 December 2013 Neighbour Con Expiry: 18 December 2013 Weekly list Expiry: 26 November 2013 Press Notice(s): 3 December 2013 Over 8/13 week reason: Previous officer left the Council.

Location: Serco Ltd, Serco Yard, Bedfordwell Road, Eastbourne

Proposal: Residential development of 102 dwellings (flats and houses), including the conversion of the existing Pump House into flats, together withaccess roads and parking spaces. Applicant: Orbit Housing Ltd

Recommendation: Grant planning permission subject to conditions and a satisfactory Legal Agreement.

If a satisfactory Legal Agreement cannot be reached within 9 months from the date of this application then the application be refused.

INTRODUCTION

The report for the 4th March is attached to this summary report for your information.

Members deferred consideration of this item from Planning Committee on the 4th March 2014 in order to secure improvements to the scheme.

Members expressed a view that the scheme could be enhanced if some/all of the following could be incorporated into the proposal:-

• Improved access onto main highway network • Increase in resident and visitor parking within the scheme • More on site public open play space within the scheme • More on site community facilities/buildings • Improved cycle access through the site to Eastbourne Park

All of the above points have been put to the applicants Orbit Homes who have made the following comments:-

Orbit Homes are ostensibly a Registered Provider of affordable homes and having c37,000 properties in its portfolio across its three operating areas with a commitment to provide a further 12,000 properties by 2020. The site and sale of these homes will yield profits, but unlike other national developers this money is not paid to shareholders but recycled back into our business and used to provide further affordable dwellings and community benefit.

This is our first Orbit market led scheme in Eastbourne for which we are thankful for the support given to date however further the deferred committee item we would like to make the following points;

• The site has been purchased with an extant consent for 154 units; this scheme provided the same amount of parking and utilised the same access to the site. On this issue the current scheme is no different from the approved scheme.

• It is accepted that the extant scheme provided a degree of onsite open play space and that this would be lost with the current scheme however the extant consent was deficient in the amount of public open space and made a financial contribution to off site provision. In this context the current scheme is no different.

• The extant consent did not propose any on site community facilities and this is considered to set a material consideration of significant weight in the current scheme, hence none are proposed now. There are no requirements within the Core Strategy that we have been made aware of for the provision of on site community facilities and therefore none are provided.

• As highlighted by the viability appraisal that has been submitted to accompany the application and as endorsed by the District Valuers consultees response to the application is on the margins of viability and the increased financial burden of the delivery of a cycle path would mean that other infrastructure may have to forsaken for example less public open space contribution, less contribution towards public transport linkages and the deliver of less affordable housing units.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Serco Ltd, Serco Yard, Bedfordwell Road. Application ID: 130907 (PPP)Report 600 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
JU
Councillor John UngarChairman, apologies, sent representative
JH
Councillor Jon HarrisDeputy-Chair, present
PH
Councillor Pat HearnCommittee Member, present
GJ
Councillor Gordon JenkinsCommittee Member, present
TL
Councillor Tom LiddiardCommittee Member, present
MH
Councillor Md. Harun MiahCommittee Member, present
JM
Councillor Jim MurrayCommittee Member, present
BT
Councillor Barry TaylorCommittee Member, apologies, sent representative
JC
Councillor Janet ColesReserve, present as substitute
CM
Councillor Colin MurdochReserve, present as substitute

More from Lewes Eastbourne Borough Council Planning Committee

All decisions
MeetingDecisionOutcome
11 Aug 2026 Greenways, 14 Chatfield Crescent. ID: 260295(unanimously) To delegate authority to the Head of Development Management to negotiate an amendment to the applicatio... Refused Open
11 Aug 2026 56 & 58 Beverington Road. ID: 260284(unanimously) that the application be refused, and to delegate the Head of Development Management to determine the wo... Refused Open
14 Jul 2026 The Tower House, 2 Carlisle Road. ID: 260233 (Full Planning Permission) and 260253 (Listed Building Consent)(unanimously) that the application for planning permission be granted subject to the conditions in the Officer’s repo... Decided Open
14 Jul 2026 1 Attfield Walk. ID: 260039(unanimously) that the application for planning permission be granted subject to the conditions in the Officer’s report. Decided Open
18 Mar 2026 24a Victoria Road. ID: 260046by (3 votes to 3 against and on the Chair’s casting vote) to delegate the Head of Development Management to conclude ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies