Full council recommended to approve (a) HRA budget 2015/16 and revised 2014/15, as set out in appendix 1 to report; (b) rents set in line with the rent convergence target of 2016 set by government resulting in an average increase in rents of 2.28%; (c) void HRA properties due for re-let moved to target rent automatically; (d) service charges for general needs properties increased by 2.31%; (e) service charges for older persons’ sheltered accommodation currently available for let increased by 2.57%; (f) heating costs set at a level designed to recover the estimated actual cost; (g) water charges set at a level designed to recover the estimated cost of metered consumption; (e) garage rents set to increase by 2.28% in line with the average increase in housing rent ; (f) delegated authority be granted to the Senior Head of Community, in consultation with the lead cabinet members for community services and finance and the Chief Finance Officer to finalise Eastbourne Homes’ management fee and delivery plan; ( i ) HRA capital programme as set out in appendix 2 to report.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
SUBJECT: HRA Revenue Budget and Rent Setting 2015/16 and HRA Capital Programme 2014/17
REPORT OF: Senior Head of Community and Chief Finance Officer
Ward(s): All
Purpose: To agree the detailed HRA budget proposals, rent levels, service charges and heating costs for 2015/16, and the HRA Capital Programme 2014/17.
Contact: Pauline Adams, Financial Services Manager Tel 01323 415979 or internally on ext 5979
Recommendations: Members are asked to recommend the following proposals to full Council:
i) The HRA budget for 2015/16 and revised 2014/15 as set out in Appendix 1. ii) That rents are set in line with the rent convergence target of 2016 set by Government resulting in an average increase of 2.28%. iii) That service charges for general needs properties are increased by 2.31%, iv) That the service charges for the Older Persons Sheltered Accommodation currently available for let are increased by 2.57%. v) That heating costs are set at a level designed to recover the estimated actual cost. vi) That water charges are set at a level designed to recover the estimated cost of metered consumption. vii) That garage rents are set to increase by 2.28% in line with the average increase in housing rent. viii) To give delegated authority to the Chief Executive, in consultation with the Cabinet Portfolio holders for Community Services and Financial Services and the Financial Services Manager to finalise Eastbourne Homes’ Management Fee and Delivery Plan. ix) The HRA Capital Programme as set out in Appendix 3.
1.0Introduction
1.1As from the 1 April 2012 the way that council social housing is financed was changed and the HRA became self financing. This means that expenditure has to be entirely supported from rental and other income. The main tool for the future financial management of the HRA is the 30 year Business Plan which was approved by Cabinet on 8 February 2012.
1.2The introduction of HRA self financing does not end the requirement to maintain a statutory ring fenced HRA and the council is still required to maintain a separate account for the income and expenditure on council housing.
1.3This report reflects the recommendations made by Eastbourne Homes in relation to the increases in rent levels, service and other charges.
2.02015/16 HRA Revenue Budget
2.1The 2015/16 budget has been prepared following the principles adopted within the HRA 30 year Business Plan and is attached at Appendix 1.
2.2The 2015/16 budget is showing a surplus of (£296,130) which is due to a number of favourable factors as listed below.
2.3The major changes between the 2014/15 and the 2015/16 budgets are:
Income increases and expenditure reductions: • Effect of rent and service charge review -£390,000 • Change in requirement for Revenue Contribution to Capital -£393,300 • Reduction in contribution towards HEDP team - £50,000 • Effect of borrowing at lower than anticipated interest rates - £60,350
Increase in Expenditure and income reductions: • Additional funding to met pressure on revenue repairs and voids budget - £520,000 • Depreciation, in line with Business Plan to cover the future requirements of the Asset Management Plan £104,300 • Contribution to Housing Regeneration Reserve £284,000
2.4The HRA budget is performance better than expected in the 30 year business plan due to various initiatives to control expenditure, including a reduction in the management fee payable to EHL since the start of the plan and a lower than anticipated interest rates. At the same time income earnings from rents and service charges have remind on target. This allows some scope for some spending to be realigned, as set out in the paragraphs below.
2.5EHL is currently experiencing pressure on the maintenance budget requirement for revenue repairs and void properties and it therefore proposed to increase the Management Fee by £520,000 to deal with this and help met customers’ expectations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.