Eastbourne Borough Council Cabinet noted this item on Wednesday 3 February 2016. Below is the council's own wording, with the papers it was decided on.
(1) Progress of scheme noted. (2) Financial procedure rules waived to allow award of a 10-year lease to the University of Brighton for the café in Princes Park. (3) Senior head, in consultation with lead cabinet member, authorised to take all necessary steps to complete the lease arrangements with the University of Brighton.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report of: Phillip Evans, Senior Head of Tourism and Enterprise.
Ward(s) All
Purpose This report updates members on progress of CCF projects and a proposal for the café in Princes Park.
Decision Type: Key decision.
Recommendation Cabinet is recommended to:
1. Note progress of Coastal Communities Funded capital and revenue projects.
2. Agree a waiver of the Financial Procedure Rules to allow the award of a ten year lease to the University of Brighton for the café in Princes Park without a competitive process.
3. Delegate authority to the Senior Head of Tourism and Enterprise and in consultation with the Cabinet portfolio holder for Tourism to take all necessary steps to complete the lease arrangements with the University of Brighton.
Contact: Paul Turton, Housing and Economic Development Project (HEDP) Director. Telephone: 01323 436314, Mobile [phone removed] E-mail address : [email removed]
1.0Background/Introduction
1.1Eastbourne Borough Council was granted £1.83m Coastal Communities Funds in February 2015 following a successful bid. The key criteria for receipt of the funding are to create 118 jobs (direct and indirect), through a mixed portfolio of capital and revenue projects, and to spend all funds by December 2016.
2.0Project progress
2.1Delivery of projects started in March 2015 and all projects are at various stages. Our revenue partners; Towner Gallery, TechResort and Building Partnerships each have clearly defined targets/outcomes for jobs created, cash flow, individual projects, training and skills.
2.2Recruitment of key posts within HEDP and our partners is complete, progress against key outcomes is monitored regularly and support given where appropriate. Partners are generally on track to deliver their key outcomes, they will achieve them all by December 2016, and all grant monies will be spent.
2.3The improvements to the upper facades in Seaside Road were the first capital project to be successfully completed in October 2015. Of the two commercial units being re-furbished, work is due to start on one in February and we are on site in the second. Both will be complete by the summer.
2.4Sea Houses Square improvements to the plaza will commence in February 2016. They will include new lighting, hard and soft landscaping and a mosaic designed by the community.
2.5Internal audit have reviewed two projects; one capital and one revenue to ensure we meet the funders requirements. Assurance was obtained from the audit which allowed the DCLG declaration to be signed and a report will be issued soon.
3.0Princes Park
3.1Over £900,000 of the CCF funds will be used to improve Princes Park in key areas; a new main entrance linked to the promenade by a new zebra crossing, a new central plaza will lead visitors from the new entrance to the café, which will be completely refurbished including new decking overlooking the lake.
4.0Café
4.1The refurbishment of the café is one of the main projects for CCF. We have full planning approval for the work, been out to tender based on an original budget of £395k. Works are scheduled to start in February 2016.
4.2An option for the refurbished café would be to seek a new arrangement with Pistachios. Given the CCF investment into the café we would expect a higher rent than currently achieved. However, we would not achieve the added value benefits detailed later in this report. Alternatively a new tenant could be identified.
4.3Pistachios in the Park have been the lessee of the café since 2012 on a modest rent which reflected the fabric of the building at the time; their lease was due to end in June 2017. We have been in regular contact with Pistachios; pre and post CCF bid, particularly about closure of the café during the refurbishment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.