(1) Business case for joint transformation programme approved and £6.878m provisionally allocated to the programme. (2) Deputy chief executive granted delegated authority to determine the appropriate allocation of costs against revenue and capital funds. (3) Deputy chief executive granted delegated authority, in consultation with Joint Transformation Programme Board, to determine the methodology for cost and benefits sharing with an overriding principle that joint costs are allocated on the basis of the benefits realisation ratio. (4) Chief executive granted delegated authority, in consultation with Joint Transformation Programme Board, to run the programme within the allocated resources, reporting to cabinets regularly. (5) High level programme plan approved. (6) Full council be recommended to approve the shared services employment model with Eastbourne Borough Council acting as host authority. (7) Procurement approach and contract variation outlined in the report, including the exceptions to contract procedure rules and the proposed changes to information and communications technology service provision, approved and deputy chief executive granted delegated authority, in consultation with Joint Transformation Programme Board, to negotiate the associated cost of pension protection with the service provider. (8) Adoption of the proven ‘Digital 360’ platform as basis for the joint transformation programme approved, subject to procurement. (9) Engagement to be undertaken with local community stakeholders in respect of relevant elements of the programme.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Subject: “Stronger Together" Joint Transformation Programme Business Case and Implementation
Report of: Chief Executive and Senior Head of Projects Performance and Technology Ward(s) All Purpose To approve the Business Case and implementation of the Joint Transformation Programme
Decision Type: Key Decision
Recommendation: It is recommended that Cabinet:
(1) Approves the business case for the Joint Transformation Programme and provisionally allocates a total of £6.878m to the programme (para 4.4). (2) Delegates authority to the Deputy Chief Executive to determine the appropriate allocation of costs against revenue and capital funds (para 4.5). (3) Delegates authority to the Deputy Chief Executive, in consultation with the Joint Transformation Programme Board, to determine to determine the methodology for cost and benefits sharing with an overriding principle that joint costs are allocated on the basis of the benefits realisation ratio (para 4.6). (4) Delegates authority to the Chief Executive in consultation with the Joint Transformation Programme Board to run the Programme within the allocated resources, reporting to Cabinets regularly (para 5.1). (5) Approve the high level programme plan (para 5.3). (6) Approve the shared services employment model with Eastbourne Borough Council acting as host authority (para 5.4). (7) Approve the procurement approach and contract variation outlined in this report including the exceptions to contract procedure rules and the proposed changes to information and communications technology service provision and delegate authority to the Deputy Chief Executive in consultation with the Joint Transformation Programme Board to negotiate the associated cost of pension protection with the service provider (para 5.10 to 5.13). (8) Approve the adoption of the proven ‘Digital 360’ platform as the basis for the Joint Transformation Programme, subject to procurement (para 5.12).
Contact: Henry Branson, Senior Head of Projects, Performance and Technology Telephone 01323 415155 or internally on 5155 E-mail address [email protected]
Page 1 of 23 1.0 Executive Summary
1.1In October 2015, Cabinet approved a strategy for the development of shared services between Lewes District Council (LDC) and Eastbourne Borough Council (EBC) based on the integration of the majority of council services.
This report asks Cabinet to approve the detailed business case, high level plan and technology arrangements for the implementation of that strategy, known as the Joint Transformation Programme (‘the Programme’).
1.2Strategic Case and Objectives Summary
Both councils have significant savings to deliver over the next four years and therefore need to find new ways to deliver public services, for less money.
More than 400 councils nationally are sharing services to deliver efficiencies, and LDC and EBC have a strong established relationship, having shared senior posts and services since 2012.
Therefore, our four strategic objectives of the Programme are: Protect services Protect services delivered to local residents while at the same time reducing costs for both councils to together save £2.8m annually Greater strategic presence Create two stronger organisations which can operate more strategically within the region while still retaining the sovereignty of each council High quality, modern services Meet communities and individual customers’ expectations to receive high quality, modern services focused on local needs and making best use of modern technology Resilient services Building resilience by combining skills and infrastructure across both councils
1.3Financial Case Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.