Sovereign Centre - proposals for improvement and future management.
ApprovedExecutive2 papers
Eastbourne Borough Council Cabinet approved this item on Tuesday 13 December 2016. Below is the council's own wording, with the papers it was decided on.
(1) Construction of new leisure centre adjacent to Sovereign Centre approved. (2) Full council recommended to include £24.48m in capital programme to fund construction of new centre and replacement of adjacent skatepark . (3) Proposed procurement of a new operator for new centre approved. (4) Commencement of public procurement processes referred to in report to deliver the new centre and a new operator approved. (5) Director of tourism and enterprise in consultation with lead cabinet members for tourism and enterprise and finance, chief finance officer and lawyer to the council given delegated authority to work on detailed development, management and approval of public procurement processes to be followed and of all the procurement documentation required to deliver project: Such delegation to include approval to allowing exceptions to council’s contract procedure rules should that be necessary. (6) That officers instructed to investigate options for the joint management of Motcombe Pool and dry side centres together with centres owned and/or operated by Lewes District Council.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Subject: Sovereign Centre – proposals for improvement and future management
Report of: Philip Evans, Director of Tourism and Enterprise
Ward(s) All Purpose To recommend the construction of a new leisure centre adjacent to the Sovereign Centre. To recommend the procurement of an operator to manage the centre when the existing contract end.
Decision type: Key Decision
Recommendation: Cabinet is recommended to:
1. Approve the construction of a new leisure centre adjacent to the Sovereign Centre.
2. Recommend to Council that £24.48m be included in the capital programme to fund the construction of the new centre and replacement of the adjacent skatepark
3. Approve the procurement of a new operator for the new Centre.
4. Approve the commencement of the public procurement processes referred to in this report to deliver the new centre and a new operator.
5. To delegate authority to the Director of Tourism and Enterprise in consultation with the Cabinet Members for Tourism and Enterprise and Financial Services, the Chief Finance Officer and the Lawyer to the Council to work on the detailed development, management and approval of the public procurement processes to be followed and of all the procurement documentation required to deliver the project. Such delegation to include approval to allowing exceptions to the Council’s Contract Procedure Rules should that be necessary.
6. Instruct officers to investigate options for the joint management of Motcombe Pool and the dry side centres together with the centres owned and/or operated by Lewes District Council.
Page 1 of 14 Contact: Graham Cook, Programme Manager, 1 Grove Road, 01323 415867, [email protected]
1.0Introduction
1.1This report considers the business case for the construction of a new leisure centre to replace the Sovereign Centre. It also recommends a mechanism for the future management of the new centre.
1.2The original Sovereign Centre was opened in the 1970s with a large extension added in the 1980s.The Centre contains swimming lanes , training pool, play-pool, gym, sports hall, café and associated offices and storage. The Centre is now aged and requires substantial reinvestment. By the nature of its two stage construction and the changes in leisure management, it is now an appropriate time to examine whether replacement would provide greater long term value for money.
1.3The Centre is let to the Eastbourne Leisure Trust (ELT) which has appointed Serco to operate the Centre. The lease and contracts expire in April 2019. The annual net cost to the council of the Centre is some £340,000.
1.4In late 2015 the council commissioned FMG Consultants/GT Architects, to carry out a high-level review and business case development to test the options for the future of the centre. The review showed that both a refurbishment of the Centre or, the construction of a new centre on the adjacent car park were viable.
However, refurbishment is necessarily a compromise, will not completely address the operational issues caused by the layout of the building, is a higher risk than new build and will cause considerable disruption to the service during construction.
Both ELT and Serco expressed a preference for re-development.
1.5After detailed consideration members decided that the new build option should be taken forward for detailed investigation.
1.6In order to test that a contract with a new operator could fund the revenue costs of constructing a new centre, it will be essential to run an operator procurement in parallel with taking forward the design and procurement of any new building.
2.0Construction of a new Centre
2.1A project team of officers drawn from tourism, planning, property, legal and finance have worked with external consultants, architects and quantity surveyors to develop a cost effective scheme which meets the requirements of the revenue business case.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.