Full council recommended to approve: (a) Treasury management strategy and annual investment strategy as set out in report. (b) Methodology for calculating the minimum revenue provision (para. 2.3 of report). (c) Prudential and treasury indicators as set out in report. (d) Specified and non-specified investment categories (appendix 2 to report).
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
SUBJECT: Treasury Management and Prudential Indicators 2017/18
REPORT OF: Chief Finance Officer
Ward(s): All
Purpose: To approve the Council’s Annual Treasury Management Strategy together with the Treasury and Prudential Indicators for the next financial year.
Decision Type Key decision
Contact: Alan Osborne, Chief Finance Officer, Financial Services Telephone Number 01323 415149.
Recommendations: Members are asked to recommend to Council;
i) The Treasury Management Strategy and Annual Investment Strategy as set out in this report.
ii) The methodology for calculating the Minimum Revenue Provision set out at paragraph 2.3.
iii) The Prudential and Treasury Indicators as set out in this report. iv) The Specified and Non-specified Investment categories listed in Appendix 2.
1.0Introduction
1.1The Council is required to receive and approve, the Prudential and Treasury Indicators and Treasury Strategy as part of the budget setting process each year. This covers: the capital plans (including prudential indicators); a Minimum Revenue Provision Policy (how residual capital expenditure is charged to revenue over time); the Treasury Management Strategy (how the investments and borrowings are to be organised) including treasury indicators; and an investment strategy (the parameters on how investments are to be managed).
1.2These elements cover the requirements of the Local Government Act 2003, the CIFPA Prudential Code, the CLG MRP Guidance, the CIPFA Treasury Management Code and the CLG Investment Guidance.
1 1.3 The Council adopted CIPFA’s Treasury Management code of Practice on 18 May 2010. This code is supported by treasury management practices (TMPs) that set out the manner in with the council seeks to achieve the treasury management strategy and prescribes how it manages and controls those activities.
2.0THE CAPITAL PRUDENTIAL INDICATORS 2015/16 – 2019/20 2.1 Capital Expenditure The Council’s capital expenditure plans are the key driver of treasury management activity. The output of the capital expenditure plans is reflected in prudential indicators, which are designed to assist Member overview and confirm capital expenditure plans. The table below summarises the Council’s capital expenditure plans and how these plans are being financed by capital or revenue resources. Any shortfall of resources results in a funding need (borrowing). The capital expenditure forecasts for the Council are: Capital Expenditure 2015/16 2016/17 2017/18 2018/19 2019/20 £m Actual Estimate Estimate Estimate Estimate Non-HRA 10.89 32.8 39.8 40.6 26.5 HRA 7.04 10.6 4.3 4.3 4.4 Total 17.93 43.4 44.1 44.9 30.9 Financed by: Capital receipts 1.78 9.0 11.5 10.7 2.3 Capital grants 2.67 5.1 6.2 2.7 2.5 Capital reserves 5.38 6.8 4.2 4.3 4.4 Revenue 0.01 0.7 0.0 0.0 0.0 Net borrowing needed for the year 8.09 21.8 22.2 27.2 21.7
The above figures include uncommitted borrowing i.e. borrowing which has been approved but schemes have not yet been identified and will only proceed if they are financially advantageous.
2.2The Council’s Borrowing Need (the Capital Financing Requirement) The second prudential indicator is the Council’s Capital Financing Requirement (CFR). The CFR is simply the total historic outstanding capital expenditure which has not yet been paid for from either revenue or capital resources. It is essentially a measure of the Council’s underlying borrowing need. Any capital expenditure above, which has not immediately been paid for, will increase the CFR. Following accounting changes the CFR includes other long term liabilities (e.g. Serco, finance leases) brought onto the balance sheet. Whilst this increases the CFR, and therefore the Council’s borrowing requirement, these types of scheme already include a borrowing facility and the Council is not required to separately borrow for them. There are currently £0.76m of such schemes within the CFR. The Council is asked to approve the CFR projections below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.