Bar Coda 125 Langney Road. Application ID: 170928.
DecidedPlanning1 paper
Eastbourne Borough Council Planning Committee decided this item on Tuesday 23 January 2018. Below is the council's own wording, with the papers it was decided on.
( Unanimous ) That permission be granted subject to the following conditions: 1) Time 2) Drawings 3) Construction Method Statement – temporary buildings etc. 4) Hours of demolition/construction 5) Car parking 6) Secure and covered cycle parking 7) Vehicle turning space in accordance with plans 8) Construction Management Plan 9) Submitted Travel Plan shall be implemented prior to occupation 10) Visibility splays to be provided prior to occupation and retained thereafter 11) Programme of archaeological works to be submitted prior to development and a written record of findings to be submitted within 3 months of completion of archaeological works 12) No bonfires 13) No contaminated materials to be brought on site 14) Hard and soft landscaping 15) local labour initiatives Informative: 1) Southern water - connection to sewer
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report to Eastbourne Borough Council Planning Committee
App.No: Decision Due Date: Ward: 170928 27 October 2017 Devonshire
Officer: Site visit date: Type: Thea Petts 11th September 2017 Planning Permission Site Notice(s) Expiry date: 25th August 2017 Neighbour Con Expiry: 25th August 2017 Press Notice(s): 25th August 2017
Over 8/13 week reason: Requirement to obtain revised drawings and committee cycle
Location: Coda Bar, 125 Langney Road, Eastbourne
Proposal: Demolition of existing Coda bar Class A4 and erection of a 4 storey building to provide 10 residential apartments with associated secure parking, cycle storage, refuse and recycling storage, amenity space and external landscaping.
Applicant: [name removed]: Approve conditionally
Executive Summary: Scheme proposes the demolition of the existing building (Coda Bar) and replacement with 2 new blocks incorporating 10 flats across four floors with associated parking (12 spaces).
The scheme was reported to Planning Committee in September 2017 and was deferred in order to allow officers to negotiate revisions to the scheme to reduce the maintenance access issues to the existing SW sewer that runs through the site.
The scheme has been following objections from Southern Water in order to allow for continued maintenance of their sewer infrastructure. The loss of the public house is regrettable however the proposed redevelopment would go some way to meeting local housing need within a sustainable centre.
The design/appearance of the replacement building is acceptable providing a suitable level/quality of accommodation that fits within the character of the wider setting. The proposal is recommended for approval Planning Status: Existing public house/bar with bedsits above (across 3 ½ floors) and associated car park
Relevant Planning Policies: National Planning Policy Framework 2012 1. Building a stong, competitive economy 2. Ensuring the vitality of town centres 4. Promoting sustainable transport 6. Delivering a wide choice of high quality homes 7. Requiring good design 10. Meeting the challenge of climate change, flooding and coastal change 11. Conserving and enhancing the natural environment 12. Conserving and enhancing the historic environment
Core Strategy Local Plan 2013 Policies B1: Spatial Development Strategy and Distribution B2: Creating Sustainable Neighbourhoods C3: Seaside Neighbourhood Policy D1: Sustainable Development D5: Housing D10: Historic Environment D10a: Design
Eastbourne Borough Plan Saved Policies 2007 HO2: Predominantly Residential Areas HO20: Residential Amenity NE14: Source Protection Zone LCF24: Redevelopment of Public Houses TR6: Facilities for Cyclists TR11: Car Parking UHT1: Design of New Development UHT4: Visual Amenity US5: Tidal Flood Risk
Local Employment and Training Supplementry Planning Document
Technical Housing Standards Nationally Described Space Standard
Site Description: The application site, which is roughly triangular in shape, stands on the north of Langney Road, where it adjoins Bourne Street. The application site shares boundaries with Rush Court to the side (North West) and Bourne Primary School to the other side and the rear (north and north east). To the immediate east, fronting the road, stands a former substation (outside of the site). A triangular shaped island stands in the road in front of the site in the middle of the Bourne Street and Langney Road junction. This island hosts a pumping station and public conveniences (now closed).
The building on the site is detached, has three and a half floors and is Victorian, retaining some traditional features (such as timber sliding sash windows). A car park stands to the side of the building (east) and is accessed via an existing dropped kerb at the centre of the front of the site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Margaret RobinsonCommittee Member, present
BT
Councillor Barry TaylorCommittee Member, present
Hear about the next one first
Follow Eastbourne Borough Council Planning Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
56 & 58 Beverington Road. ID: 260284(unanimously) that the application be refused, and to delegate the Head of Development Management to determine the wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.