Lewes District Council
Eastbourne Borough Council Cabinet, Wednesday 11 July 2018 at 6.00pm

Housing development update

Noted Executive 1 paper

Eastbourne Borough Council Cabinet noted this item on Wednesday 11 July 2018. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

(Key decision): (1) To note the Council’s housing development pipeline of homes to be delivered through the Housing Revenue Account (“HRA”), Aspiration Homes (“AHLLP”) and Eastbourne Housing Investment Company (“EHICL”) by a mix of purchasing land for new development and acquisitions of existing properties. (2) To give delegated authority to the Director of Regeneration and Planning, in consultation with the Cabinet member for Direct Assistance Services, to dispose of land currently held in the HRA as listed in the programmes set out in the report and identified as held within the HRA to Aspiration Homes or EHICL pending due diligence. This delegation was to include authorisation not to dispose by auction or invitation of tenders following public advertisements is usually required by the Council’s Contract Procedure Rules (paragraph 18.1). To further give delegated authority to the Director of Regeneration and Planning in consultation with the Lead member for Housing to determine the terms for the disposals that may be below market value. (3) In relation to loans from the Council: (a) To note the loan amounts associated with the delegation at paragraph 2 above as follows: ( i ) A loan amount of up to £6,900,000 required to develop or acquire the homes set out under the AHLLP programme that would be covered by £10m loan facility approved in the 2017/21 capital programme; and (ii) A loan amount of up to £6,600,000 required to develop or acquire the homes set out under the EHICL programme that would be covered by £20m loan facility approved in the 2017/21 capital programme; (b) To agree that the Council makes a further loan facility available of up to £10m on market terms to Eastbourne Housing Investment Company Ltd (EHICL) for the purpose of enabling the company to purchase residential accommodation under the existing programme relating to the purchase of such accommodation; and (c) To authorise the Deputy Chief Executive, in consultation with the Cabinet member for Finance, to determine the terms of any loan which would be offered. (4) To approve a housing strategy feasibility budget of £200,000 for site assessments related to housing development. This budget would be spent on emerging development opportunities within the programme. (5) To authorise the Assistant Director for Legal and Democratic Services to ensure that a “Funding Agreement” pursuant to the existing “Deed of Entrustment” is entered into by Aspiration Homes with the Council so that right to buy receipts were appropriated in accordance with legislative requirements and the retention agreement with Government in relation to “social housing”. To give delegated authority to the Director of Regeneration and Planning to determine the terms of such agreements. (6) To delegate authority to the Director of Regeneration and Planning and the Cabinet member for Direct Assistance Services (and where appropriate the Deputy Chief Executive and Assistant Director – Legal and Democratic Services) to progress the projects through the Clear Futures Energy & Sustainability Joint Venture if they consider it appropriate, and at an appropriate future stages to decide if the projects ...
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Cabinet

Body: Cabinet

Date: 11th July 2018

Subject: Housing development update

Report Of: Ian Fitzpatrick, Director of Regeneration & Planning

Cabinet member: Councillor Alan Shuttleworth

Ward(s) All

Purpose This report sets out proposals for the next stage of housing development utilising previously approved loan facilities to Eastbourne Housing Investment Company Limited and Aspiration Homes LLP.

Decision Type: Key decision.

Recommendations: (1) To note the Council’s housing development pipeline of homes to be delivered through the Housing Revenue Account (“HRA”), Aspiration Homes (“AHLLP”) & Eastbourne Housing Investment Company (“EHICL”) by a mix of purchasing land for new development and acquisitions of existing properties.

(2) To give delegated authority to The Director of Regeneration and Planning in consultation with the Lead Member for Housing, to dispose of land currently held in the HRA as listed in the programmes set out in this report and identified as held within the HRA to Aspiration Homes or EHICL pending due diligence. This delegation is to include authorisation not to dispose by auction or invitation of tenders following public advertisements is usually required by the Council’s Contract Procedure Rules (para 18.1). To further give delegated authority to the Director of Regeneration and Planning in consultation with the Lead Member for Housing to determine the terms for the disposals that may be below market value.

(3) In relation to loans from the Council to: (a) note the loan amounts associated with the delegation at paragraph 2 above as follows: (i) loan amount of up to £6,900,000 required to develop or acquire the homes set out under the AHLLP programme that will be covered by £10m loan facility approved in the 2017/21 Capital Programme; and (ii) loan amount of up to £6,600,000 required to develop or acquire the homes set out under the EHICL programme that will be covered by £20m loan facility approved in the 2017/21 Capital Programme;

(b) agree that the Council makes a further loan facility available of up to £10m on market terms to Eastbourne Housing Investment Company Ltd (EHICL) for the purpose of enabling the company to purchase residential accommodation under the existing programme relating to the purchase of such accommodation; and

(c) authorise the Deputy Chief Executive, in consultation with the Lead Member for Finance, to determine the terms of any loan which is to be offered.

(4) To approve a Housing Strategy feasibility budget of £200,000 for site assessments related to housing development. This budget will be spent on emerging development opportunities within the programme.

(5) To authorise the Assistant Director for Legal and Democratic Services to ensure that a “Funding Agreement” pursuant to the existing “Deed of Entrustment” is entered into by Aspiration Homes with the Council so that right to buy receipts are appropriated in accordance with legislative requirements and the retention agreement with Government in relation to “social housing”. To give delegated authority to The Director of Regeneration and Planning to determine the terms of such agreements.

(6) To delegate authority to the Director of Regeneration and Planning and the Lead Member for Housing (and where appropriate the Deputy Chief Executive and Assistant Director – Legal and Democratic Services) to progress the projects through the Clear Futures Energy & Sustainability Joint Venture if they consider it appropriate, and at an appropriate future stages to decide if the projects should be put forward to the Clear Futures Steering Board for inclusion as Part 1 and/or Part 2 projects

Reasons for (1) The pipeline shows the scale and detail of the Council’s recommendations: current housing development programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing development updateReport 105 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 16 attended
DT
Councillor David TuttChair, present
AS
Councillor Alan ShuttleworthDeputy-Chair, present
MB
Councillor Margaret BannisterCommittee Member, present
JD
Councillor Jonathan DowCommittee Member, present
SH
Councillor Stephen HoltCommittee Member, present
CS
Councillor Colin SwansboroughCommittee Member, present
JU
Councillor John UngarCommittee Member, present
RC
Robert CottrillOfficer, present
PE
Philip EvansOfficer, present
IF
Ian FitzpatrickOfficer, present
TW
Tim WhelanOfficer, present
PF
Peter FinnisOfficer, present

All 16 on the meeting page

On this subject at Lewes

Search all
  1. Housing development updateThis decision
  2. Housing Development and Programme UpdateNoted
  3. Housing Development and Property UpdateNoted
  4. Housing Development & Property Update (to follow)Noted
  5. Housing Development and Property UpdateNoted
  6. Housing Development and Property UpdateDecided

More from Lewes Eastbourne Borough Council Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting held on 15 July 2026Resolved – That the minutes of the meeting held on 15 July 2026 be approved and the Chair authorised to sign them as ... Approved Open
16 Sep 2026 Housing Services Progress and Performance Report - 2026/27 - Quarter 1(Non-Key Decision): To note the Quarter 1 2026/27 housing services progress and performance position, including areas... Noted Open
16 Sep 2026 Portfolio Progress and Performance Report 2026/27 - Quarter 1(Non-Key Decision): 1) To note progress and performance for Quarter 1 2026/27. To enable Cabinet Members to consider ... Noted Open
16 Sep 2026 Revenue and Capital Financial Monitoring Report - Quarter 1 2026/27(Key Decision): 1) To note the Quarter 1 forecast financial position for 2026/27 and the associated risks. 2) To dele... Noted Open
16 Sep 2026 Eastbourne Local Plan (Proposed Submission Version Plan) Regulation 19(Key Decision): Cabinet is asked to Recommend to Full Council that it: 1) Agrees the Proposed Submission Local Plan (... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies