Internal Audit Report to 31 March 2018.

Noted Finance 5 papers

Eastbourne Borough Council Audit and Governance Committee noted this item on Wednesday 25 July 2018. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

( Unanimous ) That the report be noted.
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Audit and Governance Committee

Body: AUDIT AND GOVERNANCE COMMITTEE

Date: 25 JULY 2018

Subject: Internal Audit Report to 31ST March 2018

Report Of: Audit Manager (Eastbourne)

Ward(s) All

Purpose To provide a summary of the activities of Internal Audit for the year 1st April 2017 to 31st March 2018.

To document the Internal Audit Manager’s opinion of the internal control environment as required for the Annual Governance Statement.

To consider compliance with the Public Sector Internal Audit Standards.

Recommendation(s): That the information in this report be noted and members identify any further information requirements.

Contact: Jackie Humphrey, Audit Manager (Eastbourne), Telephone 01323 415925 or internally on extension 5925. E-mail address jackie.humphrey@lewes- eastbourne.gov.uk

1.0Introduction

1.1The work of Internal Audit is reported on a quarterly basis to demonstrate work carried out compared to the annual plan and to report on the findings of audit reports issued since the previous meeting of the committee.

1.2The annual audit plan for 2017/18 was agreed by the Audit and Governance Committee in March 2017.

2.0Review of work in the financial year 2017/18.

2.1A list of all the audit reports issued in final from 1st April 2017 to 31st March 2018 is as follows:

NB. These are the Assurance Levels given at the time of the initial report and do not reflect findings at follow up.

Main Accounting (Annual 2016/17) Performing Excellently Payroll (Annual 2016/17) Performing Adequately Security of Data Movement Performing Adequately IT Contract Performing Well Change Controls Performing Well VAT Performing Excellently Box Office Computer System Performing Excellently Cafi Debtors Performing Excellently Engineering Performing Well Insurances Performing Well Building Health and Safety Performing Adequately Cafi GL Performing Excellently Corporate Plan Performing Excellently Benefits (Annual 17/18) Performing Adequately Cash and Bank (Annual 17/18) Performing Well Council Tax (Annual 17/18) Performing Well Creditors (Annual 17/18) Performing Well Payroll (Annual 17/18) Performing Well Treasury Management (Annual Performing Excellently 17/18) IT (Annual 17/18) Performing Well Theatres Reconciliations (Annual Performing Excellently 17/18) W360 Performing Adequately

Levels of Assurance - Key Performing Major weaknesses. Insufficient controls in place inadequately or controls not being applied. Fundamental improvements required. – High risk. Performing adequately Some important weaknesses. Key controls need to be improved. – Medium to high risk. Performing well Important strengths but some areas for improvement. – Medium to low risk. Performing excellently Major strengths. Minor or no recommendations. A good example of internal control. – Low risk.

2.2A joint audit of Prevent and Protect was carried out by the Head of Audit and Counter Fraud. This was issued using the Lewes assurance levels and was given the level of “partial assurance” which equates to “performing adequately” on the Eastbourne assurance levels.

2.3No reports have been issued with an assurance level of inadequate in the financial year.

2.4Appendix A shows the work carried out against the annual plan to the end of March 2018. The following comments explain the main points to be noted from the table:

Previously reported:

 Some annual reviews have exceeded the time allocated. This is due to some being carried out by the new member of staff who has never undertaken annual reviews and others being carried out by a member of staff who has never audited some areas previously.  IT Contract and Change Controls – when the draft audit plan was put together in February 2017, it was not known whether these could be started in 16/17 and therefore they were carried forward into the 17/18 plan. However, these were started in the last financial year and were just completed in the first quarter of 17/18

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Report to 31 March 2018: Appendix A.Appendix 56 KB Download
PDF
Internal Audit Report to 31 March 2018: Appendix B.Appendix 38 KB Download
PDF
Internal Audit Report to 31 March 2018: Appendix D.Appendix 48 KB Download
PDF
Internal Audit Report to 31 March 2018: Appendix E.Appendix 52 KB Download
PDF
Internal Audit Report to 31 March 2018.Report 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
DS
Councillor Dean SabriChairman, present
TT
Councillor Troy TesterDeputy-Chair, apologies, sent representative
SC
Councillor Sammy ChoudhuryCommittee Member, present
PD
Councillor Penny di CaraCommittee Member, present
PM
Councillor Paul Metcalfe MBECommittee Member, present
MH
Councillor Md. Harun MiahCommittee Member, apologies
MR
Councillor Margaret RobinsonCommittee Member, present
BT
Councillor Barry TaylorCommittee Member, present
CS
Councillor Colin SwansboroughReserve, present as substitute

On this subject at Lewes

Search all
  1. Internal Audit Report to 31 March 2018.This decision
  2. Internal Audit and Counter Fraud Report for the financial year 2025-2026 - 1 April 2025 to 31 March 2026Noted
  3. Draft Internal Audit Plan for 2026/27Agreed
  4. Draft Internal Audit Plan 2026-27Agreed
  5. Internal Audit and Counter Fraud Report - Q3Noted
  6. Draft Internal Audit Plan for 2026/27Approved

More from Lewes Eastbourne Borough Council Audit and Governance Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Item 11 (part) - Scrutiny Committee Work Programme, update on Local Government Reorganisation programme1) That the Committee continue to maintain oversight of Local Government Reorganisation developments; 2) A standing L... Decided Open
9 Sep 2026 Date of the next meetingResolved to note that the next meeting of the Audit & Governance Committee was scheduled to be held on 25 November 20... Noted Open
24 Jun 2026 Treasury Management Annual Report 2025/26Resolved to note the . Noted Open
24 Jun 2026 Annual Report of Eastbourne Borough Council's Audit and Governance Committee 2025-26RESOLVED to approve the recommendations set out in the Annual Report of the Audit and Governance Committee for submis... Approved Open
24 Jun 2026 Draft Internal Audit Plan for 2026/27Resolved to agree the proposed Internal Audit Plan ... view the full minutes text for item 11. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies