LW/18/0808 - Caburn Field, Anchor Field, Ringmer, East Sussex
ApprovedPlanning1 paper
Lewes District Council Planning Applications Committee approved this item on Wednesday 3 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved : That planning application LW/18/0808 for proposed residential development of a total of 77 dwellings of a mix of types, sizes and affordability to ensure that efficient use is made of the land, comprising of 10 x 2 bedroom flats, 12 x 2 bedroom houses, 23 x 3 bedroom houses, 9 x 4 bedroom houses, and 13 x 2 bed and 10 x 3 bed affordable houses (amended proposal) be approved, subject to the conditions set out in the report and supplementary report. (Note: Councillor Turner declared a non-prejudicial interest in this item as he was a member of Ringmer Parish Council. He therefore took part in the consideration, discussion and voting thereon.)
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report to Lewes District Council Planning Applications Committee
APPLICATION LW/18/0808 NUMBER: APPLICANTS Bedford Park PARISH / Ringmer / NAME(S): Development WARD: Ouse Valley & Ringmer Planning application for proposed residential development of a total of 77 dwellings of a mix of types, sizes and affordability to ensure that efficient use is made of the land, comprising of 10 x 2 bedroom PROPOSAL: flats, 12 x 2 bedroom houses, 23 x 3 bedroom houses, 9 x 4 bedroom houses, and 13 x 2 bed and 10 x 3 bed affordable houses (amended proposal). SITE ADDRESS: Caburn Field Anchor Field Ringmer East Sussex GRID REF:
PAC – DD/MM/YY Supplemental Information
1. A resolution to grant planning approval for this planning application was approved by the Planning Applications Committee on the 20 February 2019 subject to a legal agreement to secure the delivery 23 affordable homes (see para 6.35 below). That decision has not yet been issued. The applicant has been in extensive discussions with Lewes District Council to agree a plan for delivering all 23 homes on-site.
2. The standard procedure for affordable housing to be acquired from a private developer would be for a Housing Association or the District Council to pay a percentage of the open market value of the homes to the developer, usually up to 75% of the open market value, which would be raised by the housing provider’s own borrowing facilities. However, neither Lewes District Council nor any of the Housing Associations who work within the District are able to purchase all 23 affordable homes.
3. The majority of housing associations have set a threshold on affordable housing purchases of 25 homes and above. Lewes District Council have been able to negotiate an acceptable purchase price on 11 of the 23 homes, however due to the high open market value of 12 of the homes they are not able to afford to purchase the remaining affordable dwellings.
4. The Section 106 agreement for the planning approval will continue to include a requirement for 23 affordable homes, but will also include a cascade mechanism allowing the Lewes District Council to accept a Commuted Sum payment in lieu of 12 of the affordable homes, which will be used to deliver 12 affordable homes as close to the Caburn Field development as possible.
5. Commuted sums are calculated in a number of different ways, but are subject to viability challenge by an applicant prior to an agreement being made with the Council. A commuted sum payment of £480,000 has been agreed between the District Council and the applicant based upon the following considerations:
a. A valuation report commissioned by Lewes District Council and carried out by the District Valuation Service valued a section of scheme as having capacity for 10 residential units and at a residual land value of £40,000 per plot. For 12 plots of land this would equal £480,000. b. An appraisal has been undertaken of all of the costs of the District Council purchasing an alternative site developing 12 x 2-bedroom affordable rented homes, with the benefit of the commuted sum.
6. The appraisals showed that a development site purchase and construction of 12 x 2-bed affordable rented homes is viable for District Council to deliver. This would involve the District Council using the £480,000 as a grant to subsidise its total costs for a developing a scheme, the remaining funds would come from borrowing.
7. Therefore it is the view of the Housing Authority that £480,000 is sufficient for Lewes District Council to deliver 12 affordable rented homes on another site or 12 shared ownership homes.
8. It is therefore recommended that paragraph 6.35 point 1 is amended to read as follows -
PAC – DD/MM/YY 1. 23 affordable dwellings - mix of accommodation to be agreed with LDC Housing officer, or provision of 11 affordable units on site and a financial contribution of £480,000 to deliver 12 affordable housing units off site.
Original report of the 20 February 2019
1. SITE DESCRIPTION / PROPOSAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lewes District Council Planning Applications Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.