Eastbourne Borough Council Cabinet agreed this item on Wednesday 11 September 2019. Below is the council's own wording, with the papers it was decided on.
(Key decision): To agree a budget of up to £115k to carry out additional feasibility and design work for a stand alone energy centre at the Sovereign Centre site; this could potentially provide low carbon heat sourced from the embedded energy in the nearby sewer network. If viable, a decision to invest will be considered at the February 2020 Cabinet.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Purpose of report: Approval to progress a renewable energy centre
Decision type: Key
Officer Agree a budget of up to £115k to carry out additional recommendation(s: feasibility and design work for a stand alone energy centre at the Sovereign Centre site; this could potentially provide low carbon heat sourced from the embedded energy in the nearby sewer network. If viable, a decision to invest will be considered at the February 2020 Cabinet.
Reasons for To invest in solutions that will reduce the town’s overall recommendations: carbon footprint whilst also enabling an income generation.
Contact Officer(s): Name: Nick Adlam Post title: Newhaven & Sustainability Lead, Commercial Business, Property & Development E-mail: [email protected] Telephone number: 01323 415214
1 Introduction
1.1The December 2018 Cabinet agreed to investigate the feasibility of a number of clean-energy solutions that could reduce the overall carbon impact of the Sovereign Leisure Centre. This work has been carried out and concludes that it could be financially viable to meet the heat requirements of the leisure centre by extracting the embedded energy in the local sewer system. However, further detailed design work and contractual discussions need to take place to ensure this continues to be an investable solution.
2 The Potential Heat Solution
2.1The December 2018 Cabinet report suggested the leisure centre made some high level assumptions on standard leisure centre heat demand. Following detailed design iterations for the leisure centre the full heat load requirement is estimated at 6.6GWh and a peak demand of 2MW. 2.2 The potential solution to meet this heat demand would be to install a 2MW heat pump system in a stand-alone building (energy centre) that will extract the embedded energy from the nearby sewer system, convert it to usable heat and then pipe this to the nearby Sovereign Leisure Centre. A standalone energy centre provides future resilience and flexibility to the development of the site.
2.3The heat pump system would comprise of two 1MW heat pumps which taken together will be able to meet the varying demands of the leisure centre. This configuration also builds in resilience should one of the individual heat pumps fail or need to be serviced.
2.4The heat is obtained by taking the liquid sewage and passing it over a heat exchanger which, with a separate loop, extracts this heat and pipes it to where it is needed.
2.5The energy centre would be suitably located so it is able to expand to accommodate any potential increases in future energy demands i.e. additional heat requirements, or batteries to store PV generated electricity. For the additional heat demand you would just need to increase the number of individual heat pumps, a modular based design. The amount of heat that could be extracted from this point in the sewer network could be up to 6MW.
2.6The energy centre usage is not limited to providing heat resource to a leisure facility but could be developed as it will be able to provide energy for other types of development.
2.7Solar PV has not been incorporated into the design of the main building as there was not a clear cost-benefit but this technology could be revisited in the future for solar based car parking canopies, and the energy centre would be ready to support this.
3 Potential Structure & Operation
3.1The preferred solution would be for the Council to own the system and have contracts in place to ensure (i) the leisure centre and/or other developments have a continuous supply of heat and (ii) the energy centre remains operational and viable, thus protecting our investment. We need to finalise the terms, contracts, design and governance arrangements before making the decision to invest and the list of the respective parties we need to contract with is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.