Eastbourne Carbon Neutral 2030: A Plan for Action

Agreed Scrutiny 3 papers

Eastbourne Borough Council Scrutiny Committee agreed this item on Monday 2 November 2020. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

It was agreed that responses to the following questions would be sought: · The location of the 5MW installation · Clarification of the Council’s position by comparison to other authorities in terms of recycling rates. · The ability for the Council to work with the East Sussex County Council in looking at alternative sites for recycling on bank holidays. Members discussed the pledge by Eastbourne Borough Councillors within the Plan. It was felt that it was not endorsed by all members of the Council and that the wording required further consideration. Members also considered reference to the supporting of Eastbourne Eco-Action Network needed consideration. RESOLVED to support the recommendations in the report subject to the following amendments being considered by the Cabinet: (1) The wording of the pledge on page 3 of Appendix 2 to the report – ‘A Plan for Action’ to be amended read: Introduction to the pledge – ‘As we publish this ‘Plan for Action’ heading towards the end of an eventful 2020, we pledge the following:’ (removing the words ‘the Councillors elected by the residents of Eastbourne’) Bullet point 2 - ‘We will support the work of Eastbourne Eco-Action Network CIC’ (add the word ‘work’ and remove the words ‘wherever we can’). Bullet point 3 – ‘We will lead by example, educate ourselves on the impacts of climate change and the changes we can make in our own lifestyles and share this with others.’ (removing the words ‘in the way we live our own lives’ after ‘example’)
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Scrutiny Committee

Report to: Scrutiny

Date: 2 November 2020

Title: Eastbourne Carbon Neutral 2030: A Plan for Action

Report of: Ian Fitzpatrick, Deputy Chief Executive and Director of Planning and Regeneration

Cabinet member: Councillor Jonathan Dow – Cabinet member for Climate Change

Ward(s): All

Purpose of report: To agree the strategy and action plan to deliver Eastbourne Carbon Neutral 2030

Decision type: Key

Officer (1) the Scrutiny Committee Considers the report; and recommendation(s): (2) responds to the Cabinet with any recommendations it wishes to be considered.

Reasons for To progress towards the aims of achieving Eastbourne recommendations: Carbon Neutral 2030 as resolved in July 2019

Contact Officer(s): Name: Kate Richardson Post title: Strategy & Partnership Lead- Sustainability E-mail: [email protected] Telephone number: 01323 415202

Recommendations to the Cabinet: (1) To approve the ‘Eastbourne Carbon Neutral 2030: The Climate Emergency Strategy and Action Plan’ for publication

(2) To approve the ‘Eastbourne Carbon Neutral 2030: A Plan for Action’ summary document for publication

(3) To require the Deputy Chief Executive and Director of Planning and Regeneration to produce an annual progress report detailing the council and borough carbon footprints, and progress against the action plan in September each year.

1 Introduction

1.1This paper introduces 2 documents: Eastbourne Carbon Neutral 2030: A Plan for Action (a summary document designed for public audience); and the Eastbourne Carbon Neutral 2030: Climate Emergency Strategy and Action Plan (a more in-depth, technical report).

1.2These plans have been produced as a result of the Climate Emergency Declaration made at Full Council in July 2019 and set out the borough wide strategy and vision for a carbon neutral Eastbourne by 2030 (ECN2030). The visions and actions contained within the strategy recognise the urgency of the climate emergency being faced whilst ensuring the Council works with the community to co-ordinate our response into meaningful and long-lasting action. With limited financial resources the council needs to ensure it makes the right decisions that will have a lasting positive impact on the town.

1.3The Council originally aspired to producing a full strategy by July 2020. With the arrival of the Corona Virus pandemic and the subsequent lockdown in mid- March it quickly became apparent that the production of the strategy was going to be impacted. Reduced staffing and partnership capacity due to emergency work in particular impacted upon our ability to perform the appropriate engagement that was needed. However, that work has now been undertaken enabling this report to be considered by Cabinet.

1.4The pandemic and lockdown has been mentally and financially challenging for many residents as well as the Council and its staff. However it has also had some positive environmental and social impacts such as: improved air quality; an appreciation of carless streets; renewed interest in cycling and walking; and, an improved sense of community cohesion as society has very quickly pulled together for the greater good.

Some outcomes which could have taken years of encouragement to develop have come together over days during this crisis. The Confederation of British Industry have noted that businesses which have for years insisted their workforce travel miles to an office, have realised that trusting their employees to work flexibly can actually improve the quality of work.

There is an opportunity to harness the positives of this situation and determine how best to take these on into the future. The council’s strategic approach can now build on these positives and work not to revert to the ‘old business as usual’. A new impetus can be given to the sustainability agenda by encouraging support for a sustainable restart and economic recovery.

2 The Strategy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Eastbourne Carbon Neutral 2030 A Plan for Action: Appendix 1 Climate Emergency StrategyAppendix 2 MB Download
PDF
Eastbourne Carbon Neutral 2030 A Plan for Action: Appendix 2 A plan for actionAppendix 3.8 MB Download
PDF
Eastbourne Carbon Neutral 2030: A Plan for ActionReport 322 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
TF
Councillor Tony FreebodyChair, present
DS
Councillor Dean SabriDeputy-Chair, apologies
HB
Councillor Helen BurtonCommittee Member, present
PD
Councillor Peter DiplockCommittee Member, apologies
JL
Councillor Jane LambCommittee Member, present
RM
Councillor Robin MaxtedCommittee Member, present
PR
Councillor Pat RodohanCommittee Member, present
RS
Councillor Robert SmartCommittee Member, present
JH
Jo HarperOfficer, in attendance
HJ
Homira JavadiOfficer, in attendance

On this subject at Lewes

Search all
  1. Eastbourne Carbon Neutral 2030: A Plan for ActionThis decision
  2. Eastbourne Carbon Neutral 2030: Annual Progress ReportApproved
  3. Eastbourne Carbon Neutral 2030: Annual Progress ReportApproved
  4. Eastbourne Carbon Neutral 2030: Annual ReportApproved
  5. Eastbourne Carbon Neutral 2030: Annual Progress ReportApproved
  6. Eastbourne Carbon Neutral 2030: Annual ReportApproved

More from Lewes Eastbourne Borough Council Scrutiny Committee

All decisions
MeetingDecisionOutcome
2 Nov 2026 Minutes of the meeting held on 14 September 2026Resolved that the minutes of the meeting held on 14 September 2026 were submitted and approved and signed as a correc... Approved Open
2 Nov 2026 Update on Local Government Reorganisation Programme - verbal updateResolved – to note the verbal update on the Local Government Reorganisation Programme. Noted Open
2 Nov 2026 Forward Plan of Cabinet DecisionsResolved – to note the Forward Plan of Cabinet Decisions Noted Open
2 Nov 2026 Scrutiny Committee Work ProgrammeResolved – to note the Scrutiny Committee Work Programme, to request that officers arrange a site visit relating to C... Noted Open
2 Nov 2026 Date of the next meetingResolved to note that the next meeting of the Scrutiny Committee was scheduled for 14 December 2026, and would be hel... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies