LW/20/0702 - Land at Railway Quay, Newhaven, East Sussex
ApprovedPlanning1 paper
Lewes District Council Planning Applications Committee approved this item on Wednesday 16 December 2020. Below is the council's own wording, with the papers it was decided on.
That planning application LW/20/0702 for the creation of a community hub with 10 converted shipping containers with PV panels for use as cafe with decked seating area, information hub, travel hubs, workshop hubs and three geodomes to support tourism, community uses and sustainable transport be approved, subject to the conditions set out in the report.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report to Lewes District Council Planning Applications Committee
Executive summary
The proposed development is acceptable in principle. Accordingly approval is recommended, subject to conditions.
Relevant Planning Policies
National Planning Policy Framework 2019 Lewes District Local Plan LDLP: – CP4 – Economic Development and Regeneration LDLP: – CP8 –Green Infrastructure LDLP: – CP10 – Natural Environment and Landscape LDLP: – CP11 – Built and Historic Environment & Design LDLP: – CP12 – Flood Risk, Coastal Erosion and Drainage LDLP: – CP13 – Sustainable Travel LDLP: – CP14 – Renewable and Low Carbon Energy LDLP: – DM1 – Planning Boundary LDLP: – DM25 – Design LDLP: – DM27 – Landscape Design LDLP: – DM33 – Heritage Assets LDLP: – DM35 – Footpath, Cycle and Bridleway Network
Newhaven Neighbourhood Plan 2017-2030 Policy ES1: Regeneration of East Side Policy D1: – Promoting good design Policy D2: – Design and Climate Change Policy E3: – Visitor economy
Site Description
The application site is located to the south of Railway Approach, and to the south of the social club and to the north of the UTC building. It covers an area of approximately 0.22 hectares of a previous railway goods yard, now vacant. The site is bounded by the river along its western side and the access road serving the port/ferry terminal along the eastern boundary. The Newhaven Town railway station is approximately 50m to the east.
Proposed Development
The proposal is to create a ‘hub’ within the port area of Newhaven to serve local residents and tourists to the area. This hub will provide a location for tourist information, active travel and refreshments. It is intended that the proposed Hub and associated structures will be in place for 5 years. The development will consist of installing shipping containers (up to 10) clad in reclaimed timber and set upon the vacant site behind the Railway Club and in front of the UTC building. The site will provide space for five containers initially. Two will be bolted together to form a Refreshment Hub, there will be two separate containers for the Active Transport Hubs and a single container for the Information Hub. Three geodomes will also be erected to encourage a range of community activities. Parts of the site will be raised as decked areas to allow access to the top of the sea defences and to allow views down and across the River Ouse. Toilets will be provided as part of the refreshment hub to serve the whole site. It least 20 secure cycle parking spaces will also be provided. This scheme will form part of the regeneration of Newhaven and was approved by the Newhaven Town Funds Board, which also enabled a £500k capital grant to be obtained to support the site’s development. The Newhaven Town Funds Board included representatives from Newhaven Town Council, Lewes District Council, East Sussex County Council, and a number of key community organisations such as the Newhaven Port Authority. This proposal is coming before the Committee as the applicant is Lewes District Council.
Relevant Planning History
No recent, relevant planning history.
Consultations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lewes District Council Planning Applications Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.