Resolved
That the report be noted.
Lewes District Council Audit and Governance Committee noted this item on Monday 15 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
Report to: AUDIT AND STANDARDS COMMITTEE
Date: 15 November 2021
Title: Internal Audit and Counter Fraud Report for the first half of the financial year 2021-2022.
Report of: Chief Internal Auditor
Ward(s): All
Purpose of report: To provide a summary of the activities of Internal Audit and Counter Fraud for the first quarter of the financial year - 1st April 2021 to 30th September 2021.
Officer That the information in this report be noted and recommendation(s): members identify any further information requirements.
Reasons for The remit of the Audit and Standards Committee includes recommendations: the duties to agree an Annual Audit Plan and keep it under review, and to keep under review the probity and effectiveness of internal controls, both financial and operational, including the Council’s arrangements for identifying and managing risk.
Contact Officer(s): Name: Jackie Humphrey Post title: Chief Internal Auditor E-mail: [email protected] Telephone number: 01323 415925
1 Introduction
1.1The remit of the Audit and Standards Committee includes the duties to agree an Annual Audit Plan and keep it under review, and to keep under review the probity and effectiveness of internal controls, both financial and operational, including the Council’s arrangements for identifying and managing risk.
1.2The quarterly report includes a review of work undertaken by Internal Audit and Counter Fraud.
1.3This report summarises the work carried out by Internal Audit and Counter Fraud across the first half of the financial year 2021-22. 2 Review of the work of Internal Audit carried out in the first half of the financial year 2021-22
2.1A list of all the audit reports (Final, Follow Up and Draft reports) issued from 1st April 2021 to 30th September 2021 is as follows:
REPORT DATE ASSURANCE AUDIT REVIEW STAGE ISSUED LEVEL Building Control Final 14.04.21 Full Council Tax Final 16.04.21 Substantial IR35 Final 01.05.21 No Payroll Final 02.06.21 Substantial IR35 Follow Up 01.07.21 Minimal Revs and Bens Computer System Final 09.07.21 Full Members Allowances Final 14.07.21 Substantial Procurement Follow Up 26.07.21 Partial Business Continuity Planning Follow Up 19.08.21 Partial Benefits Final 24.08.21 Substantial Arrears Collection Follow Up 06.09.21 Partial Creditors Final 07.09.21 Partial Implementation of Housing Follow Up 10.09.21 Substantial Software Leaseholder Management and Follow Up 10.09.21 Partial Recharges Rechargeable Repairs Follow Up 20.09.21 Full Fly Tipping Follow Up 22.09.21 Partial Debtors Draft 22.09.21 N/A Treasury Management Draft 29.09.21 N/A
2.2Please note that there are no assurance levels given for the draft reports as these have not yet been agreed. You will also note that some audit reviews appear twice; this is because the final report and a follow up have been issued within the same financial year.
2.3Below are the descriptions of the levels of assurance referred to above.
Assurance Level Description Full Assurance Full assurance that the controls reduce the risk to an acceptable level. Substantial Assurance Significant assurance that the controls reduce the level of risk, but there are some reservations; most risks are adequately managed, for others there are minor issues that need to be addressed by management. Partial Assurance Partial assurance that the controls reduce the level of risk. Only some of the risks are adequately managed; for others there are significant issues that need to be addressed by management. Minimal Assurance Little assurance that the controls reduce the level of risk to an acceptable level; the level of risk remains high and immediate action is required by management. No Assurance No assurance can be given. The reasons will be explained thoroughly in the report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit and Counter Fraud Work Quarterly ReportReport | 761 KB | DownloadRead as text |
Follow Lewes District Council Audit and Governance Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | External Audit Recommendations Progress - UpdateThat the report and progress against the management actions to address the audit recommendations as set out in the re... | Noted | Open |
| 29 Jun 2026 | Grant Thornton External Audit Plan - 2025/26That the Grant Thornton External Audit Plan 2025/26 for Lewes District Council, as set out in Appendix 1, be noted. | Noted | Open |
| 29 Jun 2026 | Treasury Management Annual Report 2025/261) That the report be noted; and 2) That the Treasury Management activities for the financial year 2025/26 had been i... | Noted | Open |
| 29 Jun 2026 | Internal Audit and Counter Fraud Report for the financial year 2025-2026 - 1 April 2025 to 31 March 2026That the report be noted. | Noted | Open |
| 29 Jun 2026 | Strategic Risk Register Quarterly ReviewThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.