RESOLVED (unanimously): 1. To note the Independent Auditor’s (Deloitte) report as those charged with governance on EBC Accounts, and the Value for Money conclusion report. 2. To delegate authority to the Director of Finance and Performance (Chief Finance Officer – S151 Officer) in consultation with the Chair of the Committee to sign-off the audited Eastbourne Borough Council 2019/20 Statement of Accounts, on condition that the expected unmodified, unqualified opinion did not change. 3. To authorise the Director of Finance and Performance (Chief Finance Officer – S151 Officer) to sign the formal Letter of Representation to Deloitte. An additional recommendation was proposed by Councillor Diplock and seconded by Councillor Shore RESOLVED (unanimously) 4. That two letters should be issued from the Chair, one to the Minister of State, Levelling Up, Housing and Communities, Rachel Maclean MP, and one to the Chair of Audit at Deloitte, to express the disappointment at the situation regarding the backlog of External Audits. The CFO assured Members that they would be informed as ... view the full minutes text for item 45.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report to Eastbourne Borough Council Audit and Governance Committee
Eastbourne Borough Council Update to the Audit & Governance Committee on audit status Issued for the meeting on 1 March 2023 Deloitte Confidential: Government and Public Services Status update on the 2019/20 audit Status update on the 2019/20 audit Our work on the We reported to the November Audit & Governance Committee on our ISA 260 findings from our audit, which was at an 2019/20 audit is advanced stage. substantially We have continued to work with the finance team to finalise the audit, with staff allocated through to April 2023 to progress complete. We will the 2020 and then 2021 audits, and staffing from July for subsequent audits. update you orally in the meeting if No additional unadjusted misstatements have been identified. any matters The audit team has held on-going discussions in the form of weekly meetings and update meetings to resolve any matters remain impacting the audit. outstanding. The table below summarises the status of the matters that had been outstanding in our report. Area Status
Review of the updated statement of accounts which reflects We have reviewed the updated accounts. the agreed adjustments from issues noted during the audit, We have fed back to the Council a number of items to correct (e.g. arithmetic including arithmetic checks and tie through of amounts errors/consistency) in the final version of the statement of accounts, and have reflected on the updated statement of accounts. received an updated version of the financial statements. Completion of work on ICE financial instrument valuations We have received support for the IIL property valuation as at 31 March 2020, and (dependent on receipt of support for fair values), and equity reviewed with support of our property valuation specialist. accounting (dependent on receipt of evidence for underlying We have received support for the fair values used, and considered the property valuation in IIL). appropriateness of the assumptions used with support of our financial instrument specialist. Due to the state of markets at 31 March 2020, there is a greater judgement in the inputs used, including discount rates, than in 2018/19, and this is likely to be the case for future periods also. Our work in this area is subject to completion of quality assurance reviews. Infrastructure assets – review of management’s assessment Following the issue of a Statutory Instrument on Infrastructure on 25 December of asset lives and changes for the code changes. 2022, and the accompanying January 2023 CIPFA guidance, the Council has taken the statutory override and updated the disclosures in the financial statements meaning that only the net book value of infrastructure assets is disclosed. We agree this approach is appropriate, and have no issues to raise from our review of asset lives.
Completion of working through support received for sundry We have received support for the areas of testing outstanding. open areas of testing and any follow-up queries arising.
Completion of quality assurance review procedures, including Following the completion of the above areas, we are completing the final quality on the updated statement of accounts. assurance reviews. Receipt of signed management representation letter, and These final procedures follow completion of above areas. update of our review of subsequent events through to signing. 2
Deloitte Confidential: Government and Public Services Deloitte LLP does not accept any liability for use of or reliance on the contents of this document by any person save by the intended recipient(s) to the extent agreed in a Deloitte LLP engagement contract.
If this document contains details of an arrangement that could result in a tax or National Insurance saving, no such conditions of confidentiality apply to the details of that arrangement (for example, for the purpose of discussion with tax authorities).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Eastbourne Borough Council Audit and Governance Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.