Report to: Scrutiny Committee
Date: 10 February 2025
Title: General Fund Accommodation Programme
Report of: Ian Fitzpatrick, Deputy Chief Executive and Director of Regeneration & Planning
Cabinet member: Councillor Peter Diplock, Cabinet member for housing and homelessness
Ward(s): All
Purpose of report: To establish a new programme to acquire and/or develop additional accommodation within the General Fund to meet immediate housing priorities including reducing the pressures of homelessness.
Decision type: Key
Officer (1) To approve the General Fund Accommodation recommendation(s): Programme in-line with the following business case principles:
i. Each scheme must reduce overall cost to the council; ii. Any HRA land used shall be appropriated into the General Fund; iii. Acquisitions will be limited to the freehold; iv. Third-party leases must be value for money; v. All arrangements are subject to full legal and financial due diligence.
(2) To approve making an initial allocation within the 2025/26 General Fund Capital Programme of up to £3.17m, subject to Full Council approval.
(3) To approve entering into a Nominations Agreement with Eastbourne Housing Investment Company Ltd. (4) To authorise the Assistant Director – Property and Development, in consultation with the Director of Finance and Performance (S151 Officer) and Lead Member for Housing and Homelessness, to take all necessary actions to deliver the programme, including acquisitions, appropriations, and developments, as well as determining and executing all leases, contracts, funding agreements, nominations agreements and fees, and other related documentation.
Reasons for (1) To lessen the reliance and cost of nighty paid recommendations: emergency accommodation.
(2) To increase the provision of better quality, more affordable alternative accommodation.
(3) To make best use of council land, assets, and resources, including Eastbourne Housing Investment Company Ltd.
(4) To provide autonomy and resilience in the programme delivery, enabling the council to be responsive and competitive to opportunities as they arise and in accordance with the business case principles.
Recommendations to 1) Note the Recommendations in the General Fund the Scrutiny Accommodation Programme report; and Committee 2) Respond to the Cabinet with any views it wishes to be considered.
Contact Officer(s): Name: Nathan Haffenden Post title: Assistant Director – Property and Development E-mail: [email protected] Telephone number: 01323 436422
1 Introduction
1.1This report provides Cabinet with an overview of the proposed General Fund Accommodation Programme in-line with 2025/26 budget recommendations.
1.2The programme seeks to increase alternative housing options and target reducing the costs of nightly paid emergency accommodation (EA).
2 Background and context 2.1 As reflected in the budget papers, the largest pressure still faced by the council comes from the increased demand and cost of temporary accommodation (TA) and emergency accommodation (EA) provision.
2.2By January, the council managed 245 placements. The current provision is a vast improvement from the 2023/24 outturn position of 308 and 264 at the end of Q1 2024/25, but the demand continues to fluctuate amidst increasing costs. Although the council continues to find new ways to mitigate the pressures, including increasing the allocation of resources and improving prevention work, the numbers and increasing expenditure continue to drive cost/risk.
2.3Whilst the council continues its strategy to campaign nationally for fairer outcomes and more sustainable solutions for housing need, the existing lack of supply remains an ongoing barrier to reducing the numbers further. The council’s social housing stock within the Housing Revenue Account (HRA) has a generally low turnover and the shortage of affordable private rented accommodation places more reliance on nightly paid EA. This can also mean households being placed within EA for longer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
General Fund Accommodation ProgrammeReport | 155 KB | DownloadRead as text |
Follow Eastbourne Borough Council Scrutiny Committee at Lewes and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Minutes of the meeting held on 14 September 2026Resolved that the minutes of the meeting held on 14 September 2026 were submitted and approved and signed as a correc... | Approved | Open |
| 2 Nov 2026 | Update on Local Government Reorganisation Programme - verbal updateResolved – to note the verbal update on the Local Government Reorganisation Programme. | Noted | Open |
| 2 Nov 2026 | Forward Plan of Cabinet DecisionsResolved – to note the Forward Plan of Cabinet Decisions | Noted | Open |
| 2 Nov 2026 | Scrutiny Committee Work ProgrammeResolved – to note the Scrutiny Committee Work Programme, to request that officers arrange a site visit relating to C... | Noted | Open |
| 2 Nov 2026 | Date of the next meetingResolved to note that the next meeting of the Scrutiny Committee was scheduled for 14 December 2026, and would be hel... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.