Treasury Management Report - Quarter 2

Agreed Finance 1 paper

AI summaryEastbourne Audit and Governance Committee noted the Q2 Treasury Management report and recommended it to Full Council for approval, highlighting a £12.9m discount from early repayment of £25m of PWLB loans.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedUnanimous decision to note report and recommend approval
Money£12.9m discount, £1.49m savingsFrom early repayment of £25m PWLB loans on 29/10/25
What happens nextFull Council approvalReport to be considered by Full Council
Who it affectsCouncil borrowing and investmentsTreasury operations for 2025/26 financial year

What was decided

The Committee noted the Q2 Treasury Management report covering investment and borrowing activities for the first half of 2025/26. Report P7

The Committee recommended the report to Full Council for approval, confirming activities were in accordance with the approved Treasury Management Strategy. Report P7, 1.1

Why

The report is required under the CIPFA Code of Practice for Treasury Management, with mid-year reporting required and quarterly scrutiny undertaken by the Audit and Governance Committee. Report P8, 1.1

Officers confirmed all treasury operations during the period to 30 September 2025 were conducted in compliance with the Council's Treasury Management Practices and within prudential indicators. Report P7

What happens next

The report will be submitted to Full Council for approval. Report P7

Capital monitoring updates will continue to be reported to Cabinet each quarter.

The Council and its advisers will continue to monitor ESG investment opportunities as products become available.

The money

  • £12.9m Discount saving on early repayment of PWLB loans
  • £25m Face value of ten PWLB loans repaid early on 29/10/25
  • £12.1m Actual amount paid to settle £25m of loans after discount
  • £1.49m Total financing cost savings for the year from early debt repayment
  • £1.29m Discount saving spread over 10 years
  • £0.20m Interest cost saving
  • £0.43m MRP saving in 2025/26 from reprofiling
  • £7.10m Total cash balance at 30/9/25
  • £107.0m Total long-term PWLB borrowing at 30 September 2025 Report 5.5
  • £67m Total short-term borrowing at 30 September 2025
  • £177.5m Capital Financing Requirement forecast at Q2 Report P94
  • £30.4m Q2 capital expenditure forecast (GF £13.9m, HRA £16.5m) Report P93
  • £28.2m Loans provided to subsidiary companies and joint venture

Options considered

  • Chosen: Note the report and recommend to Full Council. Activities complied with the approved Treasury Management Strategy and CIPFA Code Report P7

Implications

  • Financial: Financing cost savings of £1.49m in 2025/26 from early PWLB loan repayment using recent asset disposal receipt.
  • Financial: MRP reprofiling provides an additional £0.43m saving in 2025/26.
  • Financial: Capital Financing Requirement revised down to £177.5m from £224.8m in the original strategy due to deferred capital schemes and lower Q2 forecast.
  • Risk: Lloyds bank counterparty limit was breached on two occasions (4/8/25 and 14/8/25); no accounts were overdrawn.
  • Other: Interest received on loans to subsidiary companies forecast at £1.3m.

Who and where

  • Eastbourne Borough Council's treasury operations and capital programme Report P6, 1.1
  • Subsidiary companies Eastbourne Housing Investment Company Ltd, South East Environmental Services Ltd, and Investment Company Eastbourne (ICE) Ltd
  • Aspiration Homes LLP (joint venture with Lewes District Council)
  • Other local authorities lending to and borrowing from the Council (short-term market) Report P63

Timeline

  • 5 March 2025: Full Council approved the 2025/26 Treasury Management Strategy, Investment Strategy, Capital Strategy and Prudential Indicators
  • 7/8/25: Bank rate cut from 4.25% to 4%
  • 30/9/25: End of Q2 reporting period; total cash balance £7.10m
  • 29/10/25: Ten PWLB loans with face value £25m repaid early, yielding £12.9m discount
  • 19 November 2025: Audit and Governance Committee considered and noted the Q2 report Report P2
  • February 2026: Next Bank rate reduction expected, to 3.75%

Plain English for the jargon

  • PWLB: Public Works Loan Board, a statutory body that lends money to local authorities
  • MRP: Minimum Revenue Provision, a prudent revenue charge for repaying debt principal over an asset's life
  • CFR: Capital Financing Requirement, the council's underlying need to hold debt for capital purposes
  • CIPFA: Chartered Institute of Public Finance and Accountancy, which sets treasury management standards
  • DMO: Debt Management Office, an executive agency of HM Treasury
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item39

Resolved

RESOLVED (unanimously) To agree to note the report and recommend it to Full Council for approval.
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Audit and Governance Committee

Report to: Audit & Governance Committee

Date: 19 November 2025

Title: Treasury Management 2025/26 Quarter 2 Mid-Year Review

Report of: Homira Javadi, Director of Finance and Performance (S151 Officer)

Ward(s): All

Purpose of report: To provide an update on the investment and borrowing activities in the first half of the year.

Officer To note the report and the assurances contained within and recommendation(s): that activities have been in accordance with the approved Treasury Management strategy and to recommend the report to Full Council for approval.

Reasons for Requirement of the CIPFA Code of Practice for Treasury recommendations: Management.

Contact Officer(s): Name: Ross Sutton

Post title: Head of Corporate Finance E-mail: [email protected]

Name: Steven Houchin

Post title: Deputy Chief Finance Officer E-mail: [email protected]

1 Introduction

1.1The Council is currently required to receive and approve, as a minimum, three main treasury reports each year, which incorporate a variety of policies, estimates and actuals.

• Treasury Strategy report and Prudential and treasury indicators • A mid-year treasury management report • An annual outturn treasury report The above reports are required to be adequately scrutinised before being recommended to the Full Council and this role is undertaken by the Audit and Governance Committee. In addition, quarterly reporting is required. These reports do not have to be reported to Full Council but do require to be adequately scrutinised and this role is undertaken by the Audit and Governance Committee. 1.2 The 2025/26 Treasury Management Strategy, Investment Strategy, Capital Strategy and Prudential Indicators were approved by Full Council on 5 March 2025.

1.3The following Treasury Management Key Values information is provided throughout the report but is summarised here for ease of reference.

Treasury Management Key Values Budget Forecast at Section of Estimate Q2 report

Authorised Debt Limit £271m £271m Section 7 & Appendix 3 Operational Boundary £260m £260m Section 7 & Appendix 3 Capital Financing Requirement £225m £178m Section 5.2 Total External Debt £223m £158m Section 5 Borrowing position under / (over) £2m £20m Section 5 Borrowing position against Authorised £48m £113m Section 5 Debt Limit under / (over)

UK Base Rate (average for year) 4.19% 4.11% Section 4.4

Cash Balances £7m £7m Section 4.3

Total Capital Expenditure (GF and £41m £30m Section 5.1 HRA) Capital Expenditure (GF & HRA) £22m £2m Section 5.1 being financed through borrowing

Short term borrowing £80m £75m Section 5.5 Long term borrowing £143m £83m Section 5.4 Total External Debt (end of year) £223m £158m Section 5

Capital Financing Costs GF (net of £6.2m £3.7m Section 7 & interest received) Appendix 3 Capital Financing Costs HRA (net) £2.4m £1.5m Section 7 & Appendix 3

2 Economics Update 2.1 Appendix 1 is an economic update provided by MUFG, the Council’s Treasury Management advisers, for the period ending September 2025. This includes information on growth, employment, inflation and borrowing rates. 3 Interest Rate Forecasts 3.1 The bank rate was cut from 4.25% to 4% on 7/8/25. The next reduction is expected in February 2026 to 3.75% on the basis that CPI inflation should have peaked by then and then on a slow downwards trajectory back to 2% by 2027. The September CPI figure of 3.8%, although nearly twice the government’s 2% inflation target, was lower than forecasters expected. Core inflation fell by 0.1% to 3.5%. Further gradual reductions in Bank Rate to 3.25% by September 2027 are anticipated but only if inflation and employment data are supportive of such cuts. The table below details the MUFG interest rate forecast.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Report: Quarter 2Report 452 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
CE
Councillor Christina EwbankChair, present
AD
Councillor Ali DehdashtyDeputy-Chair, present
KB
Councillor Kara BishopCommittee Member, present
TN
Councillor Tom NevillCommittee Member, apologies
HP
Councillor Hugh ParkerCommittee Member, present
PR
Councillor Pat RodohanCommittee Member, present
KS
Councillor Kshama Shore OBECommittee Member, present
DS
Councillor David SmallCommittee Member, present
TS
Councillor Teri Sayers-CooperReserve, present as substitute
SG
Stephen Gilbert Audit Independent PersonCo-Optee, present
PH
Paul Hetherington Audit Independent PersonCo-Optee, apologies
DH
David Horne Audit Independent PersonCo-Optee, present

All 22 on the meeting page

On this subject at Lewes

Search all
  1. Treasury Management Report - Quarter 2This decision
  2. Treasury Management Annual Report 2025/26Approved
  3. Treasury Management Annual Report 2025/26Approved
  4. Treasury Management Annual Report 2025/26Approved
  5. Treasury Management Annual Report 2025/26Noted
  6. Treasury Management Annual Report 2025/26Noted

More from Lewes Eastbourne Borough Council Audit and Governance Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Item 11 (part) - Scrutiny Committee Work Programme, update on Local Government Reorganisation programme1) That the Committee continue to maintain oversight of Local Government Reorganisation developments; 2) A standing L... Decided Open
9 Sep 2026 Date of the next meetingResolved to note that the next meeting of the Audit & Governance Committee was scheduled to be held on 25 November 20... Noted Open
24 Jun 2026 Treasury Management Annual Report 2025/26Resolved to note the . Noted Open
24 Jun 2026 Annual Report of Eastbourne Borough Council's Audit and Governance Committee 2025-26RESOLVED to approve the recommendations set out in the Annual Report of the Audit and Governance Committee for submis... Approved Open
24 Jun 2026 Draft Internal Audit Plan for 2026/27Resolved to agree the proposed Internal Audit Plan ... view the full minutes text for item 11. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies