Eastbourne Local Plan - Draft Local Plan Consultation (Regulation 18)
ApprovedExecutive2 papers
AI summaryEastbourne Cabinet approves Draft Local Plan for eight-week public consultation from 13 February to 10 April 2026, with proposed capacity of 6,010 homes against a calculated need of 14,280.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDraft Local Plan published for Regulation 18 consultation
MoneyWithin existing budgetsConsultation costs covered by existing budgets
What happens nextPublic consultation 13 Feb to 10 Apr 2026Eight-week consultation under Regulation 18
Who it affectsEastbourne Borough residents and developersFuture planning decisions across the Borough
What was decided
Cabinet approved the publication of the Draft Eastbourne Local Plan for an eight-week public consultation under Regulation 18, running from Friday 13 February to Friday 10 April 2026. Report 4.4
Cabinet delegated authority to the Chief Executive, in consultation with the relevant Cabinet Member, to make editorial changes and minor amendments to the consultation document before publication.
Why
The Plan sets out a vision and framework for future development, addressing housing, economic, community facilities and infrastructure needs; without an up-to-date plan the Council lacks control over spatial decisions. Report 1.6
The Plan is prepared under the Government's Standard Method, which gives a local housing need of 14,280 to 2042, or 714 homes per year; the Draft proposes a capacity-led target of 6,010 homes over 20 years (around 301 per year) due to flood risk, tightly drawn boundaries and the South Downs National Park. Report 1.7, 1.8, P5, 2.4, 2.5
Most new homes are expected on previously developed land (82%), with affordable housing requirements of 30% on brownfield and 40% on greenfield sites. Report 2.6, 2.8, 2.10
What happens next
The Draft Local Plan will be published for consultation from 13 February to 10 April 2026, with responses notified via the Council's online portal, press, social media, leaflets and exhibitions. Report 4.4, 4.5
Following consultation, responses will be analysed for the Proposed Submission Local Plan, with a further round of consultation in autumn 2026 ahead of submission to Government in December 2026. Report 3.1, 4.7
Final decisions on the Regulation 19 version are expected in September 2026, alongside continuing engagement with neighbouring authorities on unmet housing need and statutory bodies. Report 2.5
The money
6,010 Proposed new homes over the 20-year plan period Report 1.8, 2.4
14,280 Standard Method local housing need to 2042 Report 1.8, 2.4
714 Standard Method homes per year Report 1.8, 2.4
301 Average proposed homes per year Report 2.4
39,924 sqm Proposed new employment floorspace Report 2.9
35,600 sqm Overall employment floorspace need Report 2.9
94 Net additional homes delivered in 2024/25 Report 2.7
254 Net additional homes delivered in the previous monitoring year Report 2.7
Options considered
Chosen: Publish Draft Local Plan for Regulation 18 consultation now. Required to meet the Government deadline for submitting plans for examination by December 2026 and to keep the plan-making process on track. Report 6.1, 6.2
Rejected: Do not publish the Local Plan for consultation at this stage. Would miss the December 2026 submission deadline, requiring the plan to restart under a new system, prolonging the out-of-date plan and risking Government intervention. Report 6.2
Implications
Legal: The consultation is required under Regulation 18 of the Town and Country Planning (Local Planning) (England) Regulations 2012 and Section 19 of the Planning and Compulsory Purchase Act 2004. Report 8.1, 8.2
Financial: The Plan will affect Council Tax revenues, Section 106 developer contributions, Community Infrastructure Levy receipts and the level of new infrastructure to be funded via the Infrastructure Delivery Plan. Report 7.2
Risk: Without an up-to-date plan, the town is more vulnerable to speculative applications determined under the NPPF presumption, and there is a risk of Government intervention. Report 6.2
Equalities: An Equalities and Fairness Analysis has been undertaken and is expected to have a positive impact, including for groups with protected characteristics; consultation comments will further inform assessment. Report 10.2, 10.3
Climate: Climate Resilience is a key theme, with policies on renewable energy, energy efficiency, sustainable construction, sustainable transport and flood risk; the Plan also supports the Climate Emergency Strategy. Report 11.1, 11.2, 2.12
Who and where
Eastbourne Borough residents and communities Report 1.6, 10.2
Housebuilders, developers and landowners (including of previously developed land) Report 2.6, 2.10, 2.11
Statutory bodies including East Sussex County Council, Natural England and the Environment Agency Report 4.5
Neighbouring local authorities engaged on unmet housing need Report 2.5
Infrastructure providers, including schools, healthcare and transport Report 2.14, 2.15, 2.16
Timeline
Winter 2019/2020: Issues and Options consultation informed the Plan Report 1.7, 4.1
Winter 2022/23: Growth Strategy consultation informed the Plan Report 1.7, 4.1
Spring 2025: Councillor Briefing Sessions held on the Plan Report 4.2
March 2025: Local Development Scheme adopted setting the timetable Report 1.5
November 2025: Engagement with each political group Report 4.2
Friday 13 February 2026: Start of eight-week Regulation 18 public consultation Report 4.4
Friday 10 April 2026: End of Regulation 18 public consultation Report 4.4
September 2026: Cabinet expected to approve the Regulation 19 Proposed Submission version Report 4.7
Autumn 2026: Further round of consultation on the Proposed Submission Local Plan Report 3.1, 4.7
December 2026: Planned submission of the Local Plan to Government Report 3.1, 6.2
Plain English for the jargon
Regulation 18: The stage of local plan preparation under the Town and Country Planning (Local Planning) (England) Regulations 2012 that requires formal public consultation on a draft plan.
Standard Method: The Government set formula in national planning policy for calculating the minimum local housing need for a planning authority.
NPPF: National Planning Policy Framework, the Government's national planning policy document.
Previously developed land (brownfield): Land that has been built on before, often prioritised for new development over greenfield land.
Section 106: Legal agreements under section 106 of the Town and Country Planning Act 1990 used to secure developer contributions towards infrastructure and affordable housing.
CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure.
IDP: Infrastructure Delivery Plan, a document setting out the infrastructure needed to support planned development.
LDS: Local Development Scheme, the council's timetable for preparing local plan documents.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52
Resolved
(Key decision): 1) That Cabinet approves the publication of the Draft Eastbourne Local Plan (Appendix 1 to the report) for public consultation under Regulation 18 of the Town and Country Planning (Local Planning) (England) Regulations 2012 (as amended) for a period of eight weeks between Friday 13 February and Friday 10 April 2026. 2) That Cabinet delegates authority to the Chief Executive, in consultation with the Cabinet Member for Regulatory Services, Staff and Performance, Enterprise, to make any necessary editorial changes and minor amendments to the consultation document prior to publication if necessary.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Eastbourne Local Plan – Draft Local Plan Consultation (Regulation 18)
Report of: Councillor Colin Swansborough, Cabinet Member for Regulatory Services, Staff and Performance, Enterprise
Robert Cottrill, Chief Executive
Ward(s): All
Purpose of report: To seek Cabinet approval to publish the Eastbourne Draft Local Plan at Regulation 18 for public consultation between 13 February and 10 April 2026.
Decision Type: Key
Officer 1) That Cabinet approve the publication of the Draft recommendation(s): Eastbourne Local Plan (Appendix 1) for public consultation under Regulation 18 of the Town and Country Planning (Local Planning) (England) Regulations 2012 (as amended) for a period of eight weeks between Friday 13 February and Friday 10 April 2026;
2) The Cabinet delegate authority to the Chief Executive, in consultation with the Cabinet Member for Regulatory Services, Staff and Performance, Enterprise, to make any necessary editorial changes and minor amendments to the consultation document prior to publication if necessary.
Reasons for 1) To meet the requirements of Regulation 18 of the Town recommendations: and Country Planning (Local Planning) (England) Regulations 2012 (as amended) in the preparation of a Local Plan
2) To ensure that any minor or typographical errors can be corrected prior to the Draft Eastbourne Local Plan being published for consultation
Contact Officer(s): Name: Matthew Hitchen Post title: Senior Planning Policy Officer E-mail: [email protected] Name: Nadeem Din Post title: Head of Planning Policy E-mail: [email protected] Executive Summary
The Government, having been elected in May 2025, has introduced widescale reform of planning as well as embarking on an ambitious agenda to ensure universal local plan coverage across England. It has set a hard deadline of 31 December 2026 for local plans to be submitted for Independent Examination under the current planning system. Failure to progress or submit the Eastbourne Local Plan (the Plan) by the deadline, risks Government intervention, ultimately resulting in plan making powers being withdrawn from the Council.
The Plan has now reached a stage where Cabinet approval to undertake public consultation on the Draft Local Plan is needed. Approval is sought for an eight-week consultation period (in line with the Statement of Community Involvement) to commence shortly after Cabinet approval of this report’s recommendations. Consultation will allow for public representations to be made, and these will be taken into consideration prior to finalisation and submission of the Plan to the Government (within the set deadline).
The Plan must respond to the Borough’s future residential and non-residential development needs. To ensure it complies with the National Planning Policy Framework (NPPF, December 2024), the Plan covers the period to 2042. Upon adoption, it will apply to the area of the Borough outside of the South Downs National Park. The Plan proposes: • a suite of new strategic policies that set out an overall strategy for the pattern, scale and quality of development, and • detailed non-strategic thematic policies that will be used in the determination of planning applications. The Plan’s six themes are: Climate Resilience, Prosperous Economy, Quality Environment, Thriving Communities, Homes for All, and Effective Infrastructure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.