What was decided
Outline application for up to 140 dwellings at Howells Bank Farm was approved, with 40% affordable housing and a new access from Broyle Lane. Report P2, P14, 4.2
Members added enhanced transport measures to the legal agreement, including a car club, higher cycle vouchers and expanded water infrastructure assessment.
Why
Officers recommended approval as the planning balance favoured the scheme, with significant weight given to housing delivery and affordable housing, and moderate weight to public benefits and biodiversity net gain. Report P6, P15, P31, P44, 1.4, 1.5, 1.7, 1.8
Landscape harm was given significant negative weight, but officers considered it did not justify refusal, and the Council's inability to demonstrate a five-year housing supply reduced the weight given to the spatial strategy conflict. Report P68, 1.12
Members had previously raised concerns about sustainability, infrastructure and density, but the applicant maintained the number of dwellings and officers considered refusal on locational sustainability grounds would not be defensible.
What happens next
A Section 106 legal agreement must be completed, with the additional transport measures and amended water infrastructure condition included.
Reserved matters applications covering appearance, landscaping, layout and scale must be submitted later, with further details on drainage, access, footpath diversions and ecology to be secured by condition. Report P118, 4.2, P145, P148, P153, P154
The money
- £1,430 Per dwelling bus service contribution towards service 28 and other routes
- £1,000 Per dwelling strategic transport contribution for A26/B2192/B2124 corridor
- £16,675.14 Sussex Police contribution to mitigate policing impact
- £200 Original cycle voucher value per household (now superseded)
- £750 Increased cycle voucher value per household to be secured in S106
- £40 Driving credit per household for the car club
Options considered
- Chosen: Approve with enhanced transport measures in S106. Members accepted planning balance favoured scheme with additional mitigation Report 1.3
- Rejected: Refuse on locational sustainability grounds. Officers advised such a refusal would not be defensible and could result in cost award
- Rejected: Reduce number of dwellings. Applicant maintained position and officers considered 33 dwellings per hectare appropriate given housing need
- Rejected: Require retail unit on site. Officers considered location unsuitable and could undermine existing Ringmer shopping centre
Implications
- Financial: Per-dwelling contributions secured for bus, strategic transport, community infrastructure and police, plus affordable housing at 40%. Report P14, P23
- Legal: A Section 106 legal agreement is required, with amendment to Condition 10.23 to cover water provision as well as drainage.
- Equalities: Up to 5% of dwellings could be delivered as bungalows, supporting accessible housing. Report P127
- Climate: EV car club with three years free membership, increased cycle vouchers, footway widening and bus service support aim to reduce car dependency.
- Other: Biodiversity Net Gain of 20% or above to be delivered on site for habitat, hedgerow and watercourse units. Report P40
- Risk: Access road is predicted to flood in the 1% AEP plus climate change event, with efforts to manage the flow path to be made at detailed design stage.
Who and where
- Future residents of up to 140 new dwellings on the site Report P2, 4.5
- Existing residents of Broyle Side and Ringmer Report 3.2
- Ringmer Parish Council and local community groups Report P130
- Users of Public Footpaths Ringmer 9 and 16c Report 3.4
- East Sussex County Council highways, rights of way and ecology services
Timeline
- 15 April 2026: Application first reported to committee and deferred for further information
- 17th April 2026: Statutory deadline or agreed extension date Report P2
- 10 June 2026: Application approved by Lewes District Council Planning Applications Committee Report P1
Plain English for the jargon
- BNG: Biodiversity Net Gain, an increase in biodiversity value resulting from development
- CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure
- Section 106: A legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations
- ESCC: East Sussex County Council, the highways and education authority
- SDNP: South Downs National Park
- RNP: Ringmer Neighbourhood Plan