RESOLVED That ( i ) the responses to the statutory notices for the enlargement of Kelvin Grove Primary School and the establishment of a 16 place SEN Resource base at Kelvin Grove Primary School received during the representation period be noted; (ii) the following enlargements should be taken forward to increase permanently the supply of primary places from September 2012; Kelvin Grove Primary School be expanded from 2 to 3 forms of entry; a 16 place SEN resource base be established at Kelvin Grove Primary School; (iii) the following projects should be taken forward to consultation in order to increase permanently the supply of primary school places from September 2013: • Subject to agreement from the governing body and subsequent consultation for implementation in 2013, extend provision at Prendergast Ladywell Fields College so that it becomes an all-age school offering 2 forms of entry in the primary phase whilst retaining its current 8 forms of secondary entry. • Subject to agreement from the governing body and subsequent consultation for implementation in 2013, establish 2 permanent forms of entry on the site of the Mornington Centre as an enlargement of Torridon Junior School , initially with 2 Reception “bulge” classes in 2013 with admissions to either site based on home to school distance to the nearest site . (iv) the measures taken to ensure that sufficient places are available to meet the projected demand for Reception places in 2012 be noted; and (v) an OJEU notice should be published to invite contractors to tender for a further Framework agreement for the provision of modular buildings, ancillary building works and internal re-modelling works.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
1.1This report requests the Mayor’s agreement to proposals to increase the supply of permanent places in mainstream primary schools in 2012 and to his agreement to move to stakeholder consultation on two further proposals with the potential to add places in 2013.
1.2A further report will be brought in February 2012 outlining two further opportunities where there will be further discussions with governors during early January
1.3The report also describes why it will be necessary to extend the current Framework agreement for the procurement of the buildings and ancillary works required to enlarge schools on either a permanent or temporary basis
Recommendations
2.1That the Mayor notes the responses to the statutory notices for the enlargement of Kelvin Grove Primary School and the establishment of a 16 place SEN Resource base at Kelvin Grove Primary School received during the representation period.
2.2That the Mayor agrees that the following enlargements should be taken forward to increase permanently the supply of primary school places from September 2012:
• Expand Kelvin Grove Primary School from 2 to 3 forms of entry.
• Establish a 16 place SEN resource base at Kelvin Grove Primary School.
2.3That the Mayor agrees that the following projects should be taken forward to consultation in order to increase permanently the supply of primary school places from September 2013: • Subject to agreement from the governing body and subsequent consultation for implementation in 2013, extend provision at Prendergast Ladywell Fields College so that it becomes an all-age school offering 2 forms of entry in the primary phase whilst retaining its current 8 forms of secondary entry.
• Subject to agreement from the governing body and subsequent consultation for implementation in 2013, establish 2 permanent forms of entry on the site of the Mornington Centre as an enlargement of Torridon Junior School , initially with 2 Reception “bulge” classes in 2013 with admissions to either site based on home to school distance to the nearest site .
2.4That the Mayor notes the measures taken to ensure that sufficient places are available to meet the projected demand for Reception places in 2012 .
2.5That the Mayor agrees that an OJEU notice should be published to invite contractors to tender for a further Framework agreement for the provision of modular buildings ,ancillary building works and internal re-modeling works.
Background
3.1School expansion 3.1.1 The Mayor and Cabinet have received a number of reports detailing the pressure on Primary School places and the measures taken to increase supply. The following table summarises the additional places that have been opened since 2008:
Year Places opened 2008/09 60 (2FE) 2009/10 255 (8.5FE) 2010/11 555 (18.5 FE) 2011/12 564 (19 FE)
3.1.2 These places have been added as temporary increases (“bulge” classes). The allocation of £12.7m to meet Basic Need in 2011/12 has meant that the authority has been able to launch a programme to increase the supply of places on a permanent basis, particularly using sites such as Kilmorie Primary School and Kelvin Grove where existing Council-owned buildings can be re-commissioned.
3.1.3 Projections are reviewed at least annually as the information on live births, applications to schools and the uptake of places across each year becomes available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.