Re-development of Heathside & Lethbridge

Noted Executive 2 papers

Mayor and Cabinet noted this item on Wednesday 20 February 2013. Below is the council's own wording, with the papers it was decided on.

Item457

Resolved

RESOLVED That ( i ) the progress of the Heathside and Lethbridge Regeneration Scheme be noted; (ii) subject to the consent of the Secretary of State being obtained under Section 19 of the Housing Act 1985, there be an appropriation of the Council owned land within Phase 3 of the Heathside and Lethbridge Estate re-development scheme, from housing purposes to planning purposes under Section 122 of the Local Government Act 1972; and (iii) an application be made to the Secretary of State under Section 19 of the Housing Act 1985 for consent to the appropriation.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Mayor and Cabinet

Summary

1.1On 25 June 2003 Mayor and Cabinet agreed the proposal to expand Lewisham's established estates regeneration programme to include Heathside and Lethbridge. Following the outcome of the open competition, on the 22nd February 2006 Mayor and Cabinet agreed that Family Mosaic become preferred development partner for the re-development of Heathside and Lethbridge.

1.2Through partnership working with our partners Family Mosaic and the Homes and Communities Agency (now part of the Greater London Authority), the regeneration of Heathside and Lethbridge is well developed, builders Rydon have completed completing the Phase 1 site and Ardmore are more than half way through their building works on Phase 2. The Council has been working to obtain vacant possession of the Phase 3 blocks since April 2012 and this site is due to be handed over to Family Mosaic for demolition and building works to commence in mid March 2013.

1.3Following formal consultation with secure tenants, on the 3rd October 2012, Mayor and Cabinet agreed to bring forward Phase 4 which means that tenants are now being re-housed and these leaseholders bought back.

1.4Family Mosaic have requested that the Council appropriate the Council owned land within Phase 3 for planning purposes.

Purpose of report

2.1To update Mayor and Cabinet on the progress of the Heathside and Lethbridge Regeneration Scheme.

2.2To seek the necessary authority for the appropriation, for planning purposes, of the Council owned land within Phase 3 of the scheme, shown in bold edging on the attached plan in order to enable the powers in Section 237 of the Town and Country Planning Act (T&CPA) 1990 to be used to ensure that any restrictive covenants or other rights affecting the land can be overridden in the interests of the proper planning of the area, thereby allowing the redevelopment of the land to proceed.

1 3. Recommendations

It is recommended that the Mayor:

3.1notes the progress of the Heathside and Lethbridge Regeneration Scheme;

3.2subject to the consent of the Secretary of State being obtained under Section 19 of the Housing Act 1985, agree to the appropriation of the Council owned land within Phase 3 of the Heathside and Lethbridge Estate re-development scheme, shown in bold edging on the attached plan, from housing purposes to planning purposes under Section 122 of the Local Government Act 1972; and

3.3approve the making of an application to the Secretary of State under Section 19 of the Housing Act 1985 for consent to the appropriation, as referred to in recommendation 4.2

4. Policy Context

4.1The re-development of Heathside and Lethbridge contributes to key national objectives, particularly meeting the decent homes standard and increasing the supply of affordable housing. The Decent Homes Strategy required all local authorities to carry out a stock options appraisal by July 2005 to determine how Decent Homes will be achieved for all Council housing stock.

4.2Lewisham completed its stock options appraisal in June 2005 and submitted a comprehensive Decent Homes strategy to Government Office for London (GoL) setting out an investment plan for the entire housing stock to meet the Decent Homes standard.

4.3The re-development will see the replacement of 565 non decent or unusable homes with modern high quality homes in a well designed neighbourhood. In addition, the scheme will deliver a minimum of 126 additional affordable units and a supply of intermediate rent or private sale units.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Re-development of Heathside & LethbridgeReport 106 KB DownloadRead as text
PDF
Re-development of Heathside & LethbridgeReport 66 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
CB
Councillor Chris BestCommittee Member, apologies
JD
Councillor Janet DabyCommittee Member, present
DE
Councillor Damien EganCommittee Member, present
PM
Councillor Paul MaslinCommittee Member, apologies
JM
Councillor Joan MillbankCommittee Member, present
CO
Councillor Crada OnuegbuCommittee Member, present
AS
Councillor Alan SmithCommittee Member, apologies
SW
Councillor Susan WiseCommittee Member, present

On this subject at Lewisham

Search all
  1. Re-development of Heathside & LethbridgeThis decision
  2. Re-Development of Heathside and Lethbridge: Section 105 Consultation and Phase 3 DecantNoted

More from Lewisham Mayor and Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. Agreed Open
9 Sep 2026 Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. Decided Open
9 Sep 2026 Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... Approved Open
9 Sep 2026 Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... Approved Open
9 Sep 2026 Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... Approved Open