RESOLVED that ( i ) CRPL be authorised to borrow the additional 13/14 budget amount detailed, if required, to complete the proposed project; (ii) the project will be financed by permitting CRPL to utilise the existing Capital Working Loan facility as agreed by Council on 27 January 2010 and that the terms of the borrowing and final interest rate will be agreed by the Executive Director for Resources and Regeneration; and (iii) the CRPL directors will make the final project decision on the delivery option based on the financial return to the company.