Item22
Resolved
Having considered an officer report, the Mayor agreed that: (1) the financial contribution from the Council towards to the regeneration of the park be as follows: £1.4m from the capital programme £180k from insurance monies arising from the fire at the homesteads in 2011 A target allocation of £200k from section 106 monies. (2) the medium and long term strategy with regards to the buildings in the park be approved; and (3) the proposed response to the Sustainable Development Select Committee shown in Section 9 be approved and reported to the Select Committee.
Word for word from the decision Lewisham published for this meeting.
Source: councilmeetings.lewisham.gov.uk