Having considered an officer report and a presentation by the Cabinet Member for Housing, Councillor Damien Egan, the Mayor agreed that: (1) the progress made on the New Homes, Better Places Programme be noted; (2) the design development and consultation which has been carried out on the proposed development at Bampton Estate (50 homes), summarised at section 6 be noted; (3) the design development and consultation which has been carried out on the proposed development at Hillcrest Estate (22 Homes), summarised at section 7 be noted; (4) having considered the responses to the consultation, Lewisham Homes proceed to submit planning applications to deliver 50 new Council homes at Bampton Estate; (5) having considered the responses to the consultation, Lewisham Homes proceed to submit planning applications to deliver 22 new Council homes at Hillcrest Estate; (6) the design changes to both Grace Path and Silverdale Hall since their Mayoral approval be approved and notes that planning applications for the newly configured projects will be submitted in March
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
1.1This report provides an update on progress in delivering the Council’s new homes programme – ‘New Homes, Better Places’. Good progress continues to be made: since the last Mayor and Cabinet update report (10th January 2018) 2 more homes have been completed, 24 more homes are awaiting start on site, and 1 new scheme is now awaiting planning consent. In total 332 of the 500 homes targeted by the programme are either complete, on-site or are progressing through the planning process.
1.2This report also sets out details of the proposed developments at Hillcrest Estate (Sydenham Ward) and Bampton Estate (Perry Vale Ward). The Hillcrest Estate will deliver 22 general needs new council homes over three sites on the Estate. Bampton Estate will deliver 50 new council homes to support independent living for older people with a view to providing homes for residents’ changing care needs.
1.3This report recommends that Mayor & Cabinet agrees that planning applications should be made for both of these schemes, delivering a total of 72 new Council homes in the borough.
Summary
2.1In July 2012 the Council embarked on a programme to build new Council homes in response to a series of on-going housing policy and delivery challenges, most notably an enduring under-supply of new affordable homes available to the Council to meet housing demand.
2.2A series of update reports has subsequently been considered by both Mayor and Cabinet, and Housing Select Committee, outlining progress in meeting the target of starting 500 new Council homes for social rent in 2018.
2.394 new council homes have now been completed, whilst a further 112 are on- site and are being delivered. 56 homes have received planning permission and are awaiting start-on-site. 70 homes are currently moving through the planning decision process, whilst a further 169 homes are awaiting submission to planning committee (see table below):
Project Status Number of New Council Homes Planning Submission Due 169 Awaiting Planning Consent 70 Awaiting Start-On-Site 56 On Site 112 Completed Schemes 94 Total 501
2.4The programme contains a total of 501 homes, all of which have or will be considered for approval by Mayor and Cabinet in the current municipal year. All homes which are outstanding are projected to start on site during 2018. A full summary of the development programme is appended to this report as Appendix A.
2.5This report also sets out details of the proposed developments at Hillcrest Estate (22 homes) and Bampton Estate (50 homes). Both proposals have been through a series of consultation events and Section 105 (S105) consultation has been undertaken for each proposal. Bampton received one S105 response and Hillcrest received four S105 responses.
2.6Officers consider that all of the concerns raised through these consultation events can be addressed, in-principle, by the design team using the strategies set out in this report, and that the detail of these issues can be properly considered by the planning process and by a Planning Committee as necessary.
2.7The final scheme of the 500 Home Programme requiring consideration by Mayor and Cabinet is the proposed development at Home Park. This scheme will deliver 31 general needs council homes and ground floor community space, as well as wider estate improvements. Following the completion of the Section 105 consultation on 28th February this scheme will be submitted for consideration by Mayor and Cabinet on the 15th March.
Recommendations
It is recommended that Mayor and Cabinet:
3.1Notes the progress made on the New Homes, Better Places Programme;
3.2Notes the design development and consultation which has been carried out on the proposed development at Bampton Estate (50 homes), which is summarised at section 6 of this report;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.