Item50
Resolved
Having considered an officer report, and a presentation by the Mayor, the Mayor and Cabinet agreed that: (1) the progress of the Heathside and Lethbridge Regeneration Scheme and the current position in relation to Phases 5 and 6 as set out be noted; (2) the increase in the number of new homes from the original master plan and that the scheme will now be 52% affordable (by habitable rooms) be noted; and (3) the proposed Phase 5 and Phase 6 Project Briefs on the basis set out be approved.