Members of the LDWG noted the work undertaken to date and proposed next steps. They also noted the updated Programme Plan and the suggested approach for programme closure and legacy planning. Members of the LDWG noted the work undertaken to date and proposed next steps. They also noted the updated Programme Plan and the suggested approach for programme closure and legacy planning.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
LDWG Programme Update Report Date: 12th February 2020
Key decision: No
Class: Part 1
Ward(s) affected: All
Contributors: Interim Chief Finance Officer
Outline and recommendations In April 2019, Full Council agreed the 57 recommendations of the Local Democracy Review and approved the appointment of eight councillors to the retained Working Group to oversee the delivery of these recommendations during 2019/20. The first LDWG meeting took place in May 2019, where members agreed to structure this work into a single programme, with the recommendations clustered into eight thematic areas, each led by a LDWG Champion.
A Programme Update Report (outlining work undertaken and proposed next steps across all the thematic areas) was prepared for the second, third and fourth LDWG meetings, which took place in July, September and December 2019 respectively. As work to deliver the recommendations progressed, the various projects and activities being undertaken within each of the eight thematic areas became more closely aligned. Prior to the fourth LDWG meeting, these thematic areas were grouped under the three overarching themes within the Local Democracy Review’s original terms of reference (openness and transparency, public involvement in decisions and effective decision-making).
This Programme Update Report (for the fifth LDWG meeting) provides an overview of work undertaken and proposed next steps across these three themes. It also updates the LDWG on other work, such as the Local Democracy Review’s presence at the all-staff event on 13th January, the development of a programme closure report (to be presented at the final LDWG meeting in March 2020) and legacy planning for the review (2020/21 onwards). Timeline of engagement and decision-making May 2018 – Mayor Damien Egan promises to launch a review that will make the Council ‘even more democratic, open and transparent’
July 2018 – Full Council agrees to establish a Local Democracy Review Working Group consisting of eight councillors. They are tasked with making recommendations about how the Mayor and Council could enhance their openness and transparency, increase public involvement in Council decisions and promote effective decision-making
September 2018 to January 2019 – the Working Group gathers evidence from a wide range of residents, community groups and local councillors (including an online questionnaire completed by over 700 respondents, workshops at four secondary schools and attendance at over 40 events)
January to March 2019 – the Working Group collects their evidence into a final report, which identifies 57 recommendations for change
March/April 2019 – Mayor & Cabinet and Full Council agree the report and recommendations
April 2019 to March 2020 – the retained Local Democracy Working Group oversees delivery of the recommendations
Reason for lateness and urgency The report has not been available for five clear working days before the meeting and the Chair is asked to accept it as an urgent item. The report was not available for dispatch on 4th February 2020 due to officer capacity and the scale of work being undertaken to deliver the recommendations of the Local Democracy Review. The report cannot wait until the next meeting because members require an update on all matters in order to inform their decision-making.
1. Summary 1.1. The purpose of this report is to provide an update on work to deliver the recommendations of the Local Democracy Review since the fourth meeting of the 2019/20 Local Democracy Working Group (LDWG) on 18th December 2019. The report also outlines the proposed next steps for all thematic areas and other activities undertaken during this period in relation to the review, particularly programme closure and legacy planning.
2. Recommendations 2.1. The LDWG is recommended to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.