Sustainable Development Select Committee noted this item on Tuesday 10 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved : The Committee noted that there was frequent flooding in the vicinity of Verdant Lane and Hither Green Cemetery. In particular – it recognised local residents concerns about the flooding of the former Willow Tree riding stables site (adjacent to Northbrook Park) because of its ecological significance. As such - the Committee agreed it would refer its views to Mayor and Cabinet as follows – · The Committee recommends that the Council should carry out further investigations into the former Willow Tree riding stables site –as an important location for managing flood water runoff and of nature conservation. · The Committee believes that additional consideration has to be given to the capacity of the Thames Barrier to protect London from flooding. The Climate Emergency – and the impending melting of the Greenland ice shelf may result in rises in sea levels which are far beyond the Environment Agency’s current projections. The Committee intends to carry out further scrutiny of the Environment Agency regarding this issue and it would welcome the support of Mayor and Cabinet in this regard.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report to Sustainable Development Select Committee
Sustainable Development Select Committee
Lewisham Lead Local Flood Authority update Date: 10 March 2020
Key decision: No
Class: Part 1
Ward(s) affected: All
Contributors: Climate Resilience Manager
Outline and recommendations The Council published a Flood Risk Management Strategy in 2015 setting out its approach to delivering on statutory role of Lead Local Flood Authority. This report provides an overview of this work and the Council’s current focus in terms of flood risk management in the borough. The Sustainable Development Select Committee is invited to review the Council’s approach to local flood risk and the Lead Local Flood Authority function.
1. Summary 1.1. The Council published a Flood Risk Management Strategy in 2015 setting out its approach to delivering on statutory role of Lead Local Flood Authority. 1.2. This report provides an overview of this work and the Council’s current focus in terms of flood risk management in the borough.
2. Recommendations 2.1. The Sustainable Development Select Committee is invited to review the current focus and priorities of the Council’s approach to local flood risk and the Lead Local Flood Authority function.
3. Policy Context 3.1. In 2019 the Environment Agency consulted on plans to update the National Flood Risk and Coastal Erosion Management Strategy setting out the overall national strategy for managing flood risk. The Environment Agency are expected to publish this strategy in 2020. 3.2. The Flood Risk Regulations (2009) and The Flood and Water Management Act (2010) established the Lead Local Flood Authorities function in England and Wales, giving local authorities statutory duties and powers for local flood risk management in relation to ordinary watercourses, groundwater and surface water flooding. 3.3. Statutory duties and powers for Lead Local Flood Authorities include: Develop, maintain, apply and monitor a strategy for local flood risk management; Producing a Preliminary Flood Risk Assessment; Producing a Surface Water Management Plan; Co-operation with other relevant flood risk authorities; Statutory consultee on planning applications; Recording and investigating all ‘significant’ flooding incidents; Establishing and maintaining a register of structures which may have a significant effect on flood risk; and Administration and enforcement of consents regarding private changes to ordinary watercourses. 3.4. The Environment Agency has responsibility for flood risk in relation to main rivers and tidal flooding.
4. Background 4.1. Lewisham Council published its Strategic Flood Risk Management Strategy in 2015. The strategy was developed alongside those of Greenwich, Bexley and Bromley as part of the south east London sub-regional flood risk partnership. The strategy set out: Roles and responsibilities for flood risk management; An assessment of risk across the borough; Our policies as a lead local flood authority; and A set of actions to manage flood risk locally. 4.2. Lewisham’s Flood Risk Management Strategy included 64 separate actions assessed against national, sub-regional and local objectives. A cost of each of the actions was estimated and they were prioritised as ‘Very High’; ‘High’; ‘Moderate’ and ‘Low’. The actions are wide ranging in nature, some specific and localised, while others are very general in nature. A key issue with the 2015 strategy is the very high costs of the actions, estimated at between £20m-£40m, which are unfunded and in the main not the responsibility of the Council. The basis for prioritisation of these actions is no longer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sustainable Development Select Committee at Lewisham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.